This manual provides detailed instructions for the installation of the Four Seasons LifeRoom Optima. Please read all instructions carefully before beginning assembly. Ensure you have all necessary parts and tools before starting.

Table of Contents

  • LifeRoom Optima Roof & Frame
  • LifeRoom Optima Sidewall Framing
  • LifeRoom Optima Screen

Part 1: LifeRoom Optima Roof & Frame

Step 1A: Attaching the Hanging Rail & Channel

Select the appropriate attachment method (Option #1, #2, or #3). If mounting to a masonry wall, anchors are not included. Select the area on the wall or fascia for the Hanging Rail and snap a level line using a chalkline. Roof panels require a minimum slope of 1/2" per foot for water drainage. If attaching per Option #1, mark the roof truss ends on the fascia board. For Options #2 or #3, mark the wall studs on the wall. Hold the Hanging Rail and transfer the marks of the truss ends or wall studs to the center of the Hanging Rail. Drill a 3/16" hole through the center of the Hanging Rail at each mark.

Set the Hanging Rail against the fascia board or wall and fasten using #12x3" SMS screws through the fascia board into the truss ends or wall studs. After fastening, run a bead of sealant along the top of the Hanging Rail and caulk all screw heads. Ensure there are two screws within 4" of each end of the Hanging Rail.

Step 2A: 3" Edge Beam Preparation

Set two pieces of the 3" Edge Beam (#F) on a smooth, flat surface, being careful not to scratch them. Mark the Edge Beam Splice at 12" and slide it into one Edge Beam (#F) to the 12" mark. Slide the second Edge Beam over the Splice and butt it against the first beam. Center one Top Post Bracket (#I) over the butt joint of the two Edge Beams. Fasten using two #14x1-1/4" tek screws through the face of the Top Post Bracket into one Edge Beam and then into the Beam Splice (#G).

Ensure both halves of the beam are straight. Fasten through the Top Post Bracket into the second beam and then into the Beam Splice using two #14x1-1/4" tek screws. Rotate the beam over twice, ensuring it is straight, then fasten repeating steps C & D, securing through the Top Post Bracket (#I) into both Edge Beams and the Beam Splice (#G). Rotate the beam over once so the Top Post Bracket legs are up. Fasten two #14x1-1/4" tek screws into each 3" Edge Beam (4 total).

Step 2G: Edge Beam Preparation (continued)

Rotate the beam one time. Butt the measuring tape to the Top Post Bracket (#I) and measure to the left. Then, move the measuring tape to the other side of the bracket and measure to the right. Refer to the front view LAYOUT SHEET for your size Patio Cover Critical Post Spacing measurements, adding 3/16" to the post bracket spacing measurement and location of the Top Post Bracket (#I).

Step 3A: Marking the Edge Beam & the Hanging Channel

Set the 3" Edge Beam and Hanging Channel together on a flat, non-abrasive surface, ensuring the right ends are even. Tape the ends together. Hook the measuring tape on the end and mark the Edge Beam and Hanging Channel at 12 3/8", 24 3/8", 36 3/8", and so on, marking every 12" with a pencil. Mark the Edge Beam on the backyard-facing front side. These marks will be the center marks of the mated Roof Panels. Squeeze the Roof Panels slightly to align the mated Roof Panel joints to the marks. This is a critical step when installing the Roof Panels.

Step 4A: Measuring, Leveling, Cutting, Fastening 3 x 3 Posts (#J) Radius Corners to Edge Beam (#F)

The bottom of the 3" Edge Beam (#F) should never be lower than 80". Place a level on the front edge of the slab to determine the LOW side. Measure from the slab up to the bottom of the Hanging Channel (#B) on that LOW side. Subtract 3 1/2" from your measurement and a minimum 1/2" per foot of your roof panels (e.g., 10ft roof panels = 5", 12ft roof panels = 6"). Example: for a 12 feet deep x 22 feet wide LifeRoom Optima, if you measured 98" to the bottom of the Hanging Channel, calculate: 98" - 3-1/2" = 94 1/2". Then, 94-1/2" - 6" = 88 1/2". Cut your first post to this measurement.

Slip the first Post tightly over the Top Post Bracket (#I), fastening through the Post into the internal bracket leg, using 4 #14 x 1-1/4" tek screws evenly spaced on both sides.

Step 4D: Measuring, Leveling, Cutting, Fastening 3 x 3 Posts (#J) Radius Corners to Edge Beam (#F) (continued)

Place a ladder at the first End Post for Person #1. Place a second ladder near the opposite end for Person #2. Stand up the attached Post and Front Edge Beam assembly while Person #2 holds the Front Edge Beam LEVEL and a POST against the Edge Beam.

Step 4E:

Person #1 tells Person #2 to raise or lower the 3x3 Edge Beam to get it level. When it is level, Person #2 marks along the bottom of the Beam onto the Post. Cut the post under the marked line. Repeat Step 3-D to fasten the Post (#J) to the Edge Beam (#F).

Step 4F: Measuring, Leveling, Cutting, Fastening 3 x 3 Posts (#J) Radius Corners to Edge Beam (#F) (continued)

Using ladders and/or building buddies, hold the assembly of the 2 posts and Edge Beam upright. Double-check to ensure the Edge Beam is LEVEL. If it is not LEVEL, cut one of your posts to make that adjustment.

Step 4G:

Once the Edge Beam assembly is LEVEL, take a third Post, hold it against the Edge Beam in the center location near the Top Post Bracket (#I), and mark a line on the post along the bottom of the beam. Cut the post above the marked line. Repeat Step 4-C to fasten the Post (#J) to the Edge Beam (#F). If you have more than 3 posts, repeat Step 4-G for the remaining Posts.

Step 4H: Measuring, Leveling, Cutting, Fastening 3 x 3 Posts (#J) Radius Corners to Edge Beam (#F) (continued)

Lay down the Edge Beam and Post Assembly. Insert the Bottom Post Bases (K) into the bottom of each Post (#J). Fasten through the side of Posts into the internal legs of the bottom base with 4 #14 x 1-1/4" tek screws on both sides of the Posts.

Step 5A: Setting First and Last Roof Panels (#A)

Carefully unpack and lift out two roof panels. Set the Roof Panels on saw horses carefully so as not to scratch the bottom sides.

Step 5B:

Measure and mark the REAR SIDE of the Post locations. For 10' roof panels, measure and mark 8' 9". For 12' roof panels, measure and mark 10' 9". Mark Post locations out from the house wall for the first and last Post. Pop a chalkline, connecting the first and last marks.

Step 5C: Setting First & Last Roof Panels (continued)

Stand up the Edge Beam and Post Assembly, tying Posts to the ladders or with help from building buddies. Square up the left end of the Edge Beam with the left end of the Hanging Rail on the house. Set the Posts in front of your post chalkline.

Step 5D: Setting First Roof & Last Panels

Ensure the RIGHT end of the 3" Edge Beam (#F) is square with the RIGHT end of the Hanging Channel (#B) at the house. Slide the first Roof Panel into the Hanging Channel tightly against the Foam Weatherstripping with the FEMALE lock of Roof Panel on the RIGHT, having the RIGHT edge of Roof Panel FLUSH with the right end of the 3" Edge Beam.

Step 5E: Setting the First & Last Roof Panels (continued)

The pre-punched holes in the Roof Panel should be aligned with the screw groove in the bottom leg of the Hanging Channel. Use one #10x3/8" SMS to fasten the first section of roof panel to the Hanging Channel as shown.

Step 5F:

Using a 4' level, plumb level the front side of the Post while the Post is set in front of the chalk line. Use a framing square against the roof panel inside the hanging channel to ensure the right Female edge of the roof panel is square with the right end of the 3" Edge Beam. If not square, move the Edge Beam and Posts to be square and aligned properly. Fasten the first section of the Roof Panel to the 3" Edge Beam using one #10x3/4 tek screw. DO NOT anchor the Post bottom yet.

Step 5G:

Take the second Roof Panel to the far left end of the Hanging Channel and 3" Edge Beam. Align the left male side of Roof Panel with the end of the 3" Edge Beam. The pre-punched holes in the Roof Panel should align with the screw groove in the bottom leg of the HANGING CHANNEL. Use ONE #10x3/8" SMS to fasten the last section of roof panel to the Hanging Channel. Do not anchor the Post bottom yet.

Step 5H:

Using a 4' level, plumb level the front side of the Post while the Post is set in front of the chalkline. Have the left male edge of roof panel in line with the left end of the 3" Edge Beam. Fasten the last section of the roof panel to the 3" Edge Beam using one #10x3/4 tek screw. Do not anchor the Post bottom yet.

Step 6A: Running the Roof Panels & Pre-formed Flashing

Take the third Roof Panel, starting on the RIGHT end, having FEMALE lock on the right side.

Step 6B

Set the FEMALE lock on top of the MALE lock of the first panel. Raise both panels upward so the bottoms almost touch, making a V, then slowly lower them to lock together. Check to ensure they are locked together, then slide the new Roof Panel into the Hanging Channel tightly against the Foam Weatherstripping.

Step 6C: Running the Roof Panels & Pre-formed Flashing (continued)

The pre-punched holes in the Roof Panel should align with the screw groove in the bottom leg of the Hanging Channel (#B). It is CRITICAL to align the CENTER of the MATED ROOF PANEL SEAM with the 12" marks made on the Hanging Channel (#B) from STEP 1. Use one #10x3/8" sms to fasten the first section of Roof Panel to the Hanging Channel.

Step 6D:

It is CRITICAL to align the CENTER of the MATED ROOF PANEL SEAM with the 12" marks made on the 3" Edge Beam (#F) from STEP 1. Then, fasten the Roof Panel to the 3" Edge Beam (#F) using one #10x3/4 tek screw through BOTH sections of each Roof Panel.

Step 6E:

Now that you have 3 Roof Panels started on the right side, take one Pre-formed Flashing, holding it upright so the 5/16" leg is aligned into the Flashing Groove in the Hanging Rail. Slowly lower the Flashing down to the Roof Panel. Bend the tabs downward to go into the Roof Panel grooves to block leaves. NOTE: If the tabs do not line-up into the Roof Panel, check your 12" spacing marks.

Step 6F: Running the Roof Panels & Pre-formed Flashing (continued)

Put a dab of caulk sealant under the 1st notch on the right side where it rests on the Roof Panel. Fasten through the Flashing into the Roof Panel top using one #10 tek screw. Then, put another dab of caulk over the screw head.

Step 6G:

After installing 2 more Roof Panels, with 3 roof panels exposed, run the next Pre-formed Flashing, repeating Steps 6 D&E. NOTE: As you run the Roof Panels, ensure the Roof Panel seams are in line with the 12" spacing marks from Step I. Be sure to caulk and fasten through both pieces of Flashing where they overlap, then fasten the Flashing through every other notch. Run the remaining Roof Panels and Pre-formed Flashings. When nearing the last Roof Panel, remove it so you can run the last 2 Roof Panels. Caulk around and on top of all the screw heads.

Step 7A: Anchoring the Posts

Each Post must be plumb level in both directions (front and side). Keep the Critical Post Spacing Measurements between the front Posts at the top and bottom. Set the posts in front of your post chalkline, double-checking with the level and Critical Post Spacing Measurements. Drill 3/8" holes with a masonry bit (not included).

Step 7B:

Spin the nut down the Wedge Anchor so the hammer does not hit it, and only hit the top of the anchor shaft. Tap the Wedge Anchor into the hole and tighten with a wrench.

Step 7C:

Repeat Steps 7 A&B for the remaining posts. The Critical Post Spacing Measurements are important for the future installation of the LifeScreens.

Step 8A: Installing Front Fascia & Fascia Clips

The Roof Panels should be flush/even with the top lip of the Front Fascia. Two workers on ladders must hold up the Front Fascia so the rear short leg hits the bottom of Roof Panels. Ensure the ends are even with the ends of the roof panels. Fasten down through the Roof Panel into the rear short leg of the Front Fascia using one #10 x 3/4 tek in each section of the roof panels. (If your LifeRoom Optima is wider than 16', refer to page 26.)

Step 8B:

The Fascia Clips should be centered where the 2 Roof Panels overlap and are mated together. Insert the clip into the groove of the Front Fascia, slowly pushing the clip down until it locks.

Step 8C:

Fasten the clip to the mated Roof Panel joint using one #10 x 3/4 tek. Caulk around and on top of all the screw heads.

Step 9A: Attaching Side Fascia

With assistance, hold the Side Fascia against the house and Front Fascia. Check if you need to trim the Side Fascia at an angle to fit tightly against the wall or house fascia.

Step 9B:

Cut and test fit the Side Fascia against the house wall or fascia. With a pencil, trace the Front Fascia onto the Side Fascia, and then cut the Side Fascia to fit.

Step 9C:

Set the Side Fascia top leg onto the Hanging Channel at the house end. Mate and fasten the Side Fascia and Front Fascia as shown.

Step 9D:

Fasten through the side of the Side Fascia into the Male or Female sides of the Roof Panel. Continue with 24" spacing. Caulk the inside corner joint of the Front Fascia and Side Fascia heavily with the sealant, and then stuff in the Fascia Dam and caulk again.

Step 10A: Corner Angles

Place each Corner Angle flush with the bottom of the Front Fascia covering the corner joint.

Step 10B:

Mark the desired height of the corner and cut it.

Step 10C: Corner Angles (continued)

Fasten each corner using 2 #10 x 3/4 teks each side.

Step 11A: Installing Fascia Drains

Measure 6" from both ends of the Front Fascia and mark with a pencil on the bottom in the center. Use a 2" hole saw to drill a hole through the bottom of the Front Fascia.

Step 11B:

Run a small bead of caulk around the flange of the Fascia Drain. Center the Fascia Drain over the hole, pressing it against the bottom of the Front Fascia. Fasten using only 2 #10x3/4" tek screws upward into the Front Fascia.

Step 11C:

Inside the Front Fascia, caulk the 2 screws that fastened the Fascia Drain.

Step 12A: Preparing to Splice the Front Fascia for LifeRoom Optimas OVER 16'

Lay the Front Fascias parallel and even on a flat non-abrasive surface.

Step 12B:

If you live in the Midwest or Western U.S., your splice may be 12" and silver. If you live in the Central or Eastern U.S., your splice may be 30" and white. If you have a 30" Splice, measure and mark at 15" inside the Splice. If you have a 12" Splice, measure and mark at 6" inside the Splice.

Step 12C:

For 30" Splice, hook your measuring tape on the back side of Front Fascia. Measure 2" and 13" in both directions of each piece, marking with a pencil. For 12" Splice, measure 2" and 4" in both directions of each piece. Then, measure up 3/4" from the bottom and down 3/4" from the top. Mark these locations with a pencil.

Step 12D: Preparing to Splice the Front Fascia for LifeRoom Optimas OVER 16' (continued)

For the 30" Splice, hook your measuring tape on the ends of the Front Fascia. Measure over 2" and 13" on both pieces and mark with pencil. For 12" Splice, measure over 2" and 4" on both pieces. Then, measure up 1 1/4" from the bottom and down 1 1/4" from the top, marking with a pencil.

Step 12E:

Caulk inside both Fascias, staying one inch away from the ends of both Fascias. Caulk both bottom corners, up and down the front, back, and bottom.

Step 12F:

Insert the Fascia Splice halfway. Push the Splice down into the caulking and fasten using the #10 tek screws through the front and the back marks on the Front Fascia. Caulk inside the second Front Fascia, and then slide over the Splice, making sure both pieces are straight in-line. Then, fasten together using the #10 tek screws.

Step 12G: Preparing to Splice the Front Fascia for LifeRoom Optimas OVER 16' (continued)

Caulk inside the Front Fascia at the ends of the Splice, going up the front and back. Smooth out the caulk so it won't block water drainage. Caulk all the screw heads inside.

PROCEED to STEP 8A to INSTALL the FRONT FASCIA

Part 2: LifeRoom Optima Sidewall Framing

Step 13:

Measure against the house wall and cut the 3" Receiving Channel. The Channel must be in line with the front Corner Post of the Patio Cover. Plumb level the Channel up the wall and mark the location on the wall. Pre-drill holes in the Channel. Caulk the back side of the channel and fasten to the house wall using 5 fasteners.

Step 14:

Remove the screws fastened through the backside (or inside) of the Top Post Bracket of the 3x3 Front Beam at the Corner Post. Fasten the hidden Post base to the Top Post Bracket 3/16" down from the Roof Panel using 5 #14 tek screws.

Step 15:

Measure the 3x3 Side Beam. Measure from the front 3x3 Beam to the inside of the Receiving Channel against the house wall, then subtract 1/2". Cut the 3x3 Beam to that measurement. Slip the 3x3 Beam over the hidden post base against the Front Beam, and then slide the other end into the Receiving Channel.

Step 16:

Level the 3x3 side beam. Fasten through the side Beam into the hidden Post Bracket using 2 #14 tek screws inside and outside. At the house wall, fasten through the Receiving Channel into the Side Beam using 2 #14 tek screws inside and outside.

Step 17:

Measure and cut 3x3 posts for the house wall. Measure from the floor to the bottom of the 3x3 Side Beam, and then cut the 3x3 post to fit, pushing it into the Receiving Channel. DO NOT FASTEN until installing the screen units. Measure from the top of 3x3 Side Beam to the roof. Cut a short 3x3 Post to fit, pushing it into the Receiving Channel. Fasten using 2 #14 tek screws on each side.

Step 18: Assembling the Trapezoid Filler Panel

a) Measure across the top of the 3x3 Side Beam and cut the 1x1 angle to fit. Line-up the angle flush with the outside edge of the Side Beam and fasten using #10 tek screws spaced every 16".

b) Cut the short piece of the 1x1 angle for the short 3x3 Post in the Receiving Channel & fasten using #10 tek screws.

c) Measure, cut and fasten the 1x1 angle for the bottom of the roof panel, in line with the Side Beam using #10 tek screws.

Step 18 d:

Measure the trapezoid opening; transfer and mark measurements onto the 2" Filler Panel. Cut the Filler Panel with a skillsaw fitted with a typical carbide tip blade. Test fit it and push it into the opening.

Step 19:

Measure, fit and fasten the remaining pieces of 1x1 angle. Repeat Steps 18 for the second side wall Filler Panel.

Part 3: LifeRoom Optima Screen Installation Guide

What's Included

  • Entry Guide (2x)
  • Side Track (2x)
  • Receiving Channel (1x)
  • Hood Assembly (1x)
  • #8 x 3/4" Self Drilling Screws (20x)

What You Need

  • Drill / Driver
  • 5/16" Hex Head Driver
  • Tape Measure
  • Saw
  • Ladder
  • Gloves

Step 20:

Remove the screws as shown from both sides of the hood assembly.

Step 21:

Remove the Front Cover and set aside.

Step 22:

Measure up the post as shown, from the top of the floor post bracket—not the floor—to the bottom of the 3x3 beam.

Step 23:

Subtract 3 3/4" from the measurement you just made (H), and cut the Side Track. Then, subtract 3 1/4" from the measurement (H) and cut the Receiving Channel.

Step 24:

Slide the Receiving Channels over the leg of the End Caps as shown.

Step 25:

Using two people, lift the Hood Assembly and Receiving Channels between the Posts of your LifeRoom Optima, and push it up tight against the beam.

Step 26:

Ensure the Hood Assembly is tight against the Beam. Fasten through each End Cap through the Receiving Channel and to the Posts as shown.

Step 27:

Secure the Receiving Channels to each Post using self-drilling screws. Keep the bottom screw 5" up from the floor and then equally space the remaining screws.

Step 28:

Insert the Side Rails into the Receiving Channels as shown. The Plastic Entry Guide should be on the top; do not fasten the Rails yet.

Step 29:

Pull the Screen down into the Side Rails, ensuring that the Zipper goes through the Entry Guide as shown.

Step 30:

Pull the Screen down to the floor. Adjust the Side Rail Tracks so they are parallel with each other. Minor Screen wrinkles are normal; sunlight will typically help smooth them out.

Step 31:

Fasten the Track to the Receiving Channel using 3 self-drilling tek screws on each side. Be sure not to screw into the Zipper groove.

Step 32:

With the Screens pulled down, attach a fastener through the End Cap on both sides as shown below.

Step 33:

For 10'-5" screens, use 2 additional screws to fasten the hood upward to the 3" Edge Beam, spaced into thirds. For all other Screen units, use one screw in the center of the Hood to the Edge Beam. Reinstall the Front Cover using the two screws removed in Step 1.