ESR 1685 Geopier Foundation Co. D1241

User Manual: D1241

Open the PDF directly: View PDF PDF.
Page Count: 4

DownloadESR-1685 - Geopier Foundation Co. D1241
Open PDF In BrowserView PDF
Most Widely Accepted and Trusted
0

ICC-ES Evaluation Report

ICC-ES
000| (800) 423-6587 | (562) 699-0543 | www.icc-es.org

ESR-1685

Reissued 01/2018
This report is subject to renewal 01/2019.

DIVISION: 31 00 00—EARTHWORK
SECTION: 31 66 00—SPECIAL FOUNDATIONS

REPORT HOLDER:

GEOPIER FOUNDATION COMPANY
130 HARBOUR PLACE DRIVE, SUITE 280
DAVIDSON, NORTH CAROLINA 28036
EVALUATION SUBJECT:

RAMMED AGGREGATE PIER INTERMEDIATE FOUNDATION/SOIL REINFORCEMENT
SYSTEM

Look for the trusted marks of Conformity!
“2014 Recipient of Prestigious Western States Seismic Policy Council
(WSSPC) Award in Excellence”
ICC-ES Evaluation Reports are not to be construed as representing aesthetics or any other attributes not
specifically addressed, nor are they to be construed as an endorsement of the subject of the report or a
recommendation for its use. There is no warranty by ICC Evaluation Service, LLC, express or implied, as
to any finding or other matter in this report, or as to any product covered by the report.

Copyright © 2018 ICC Evaluation Service, LLC. All rights reserved.

A Subsidiary of

ICC-ES Evaluation Report

ESR-1685
Reissued January 2018
This report is subject to renewal January 2019.

www.icc-es.org | (800) 423-6587 | (562) 699-0543
DIVISION: 31 00 00—EARTHWORK
Section: 31 66 00—Special Foundations

A Subsidiary of the International Code Council ®
4.0 DESIGN AND INSTALLATION
4.1 Design:

REPORT HOLDER:
GEOPIER FOUNDATION COMPANY
130 HARBOUR PLACE DRIVE, SUITE 280
DAVIDSON, NORTH CAROLINA 28036
(800) 371-7470
www.geopier.com
info@geopier.com
EVALUATION SUBJECT:
RAMMED AGGREGATE PIER INTERMEDIATE
FOUNDATION/SOIL REINFORCEMENT SYSTEM
1.0 EVALUATION SCOPE
Compliance with the following codes:
 2018, 2015, 2012, 2009, 2006 and 2003 International
®
Building Code (IBC)
†
 2013 Abu Dhabi International Building Code (ADIBC)
†

The ADIBC is based on the 2009 IBC. 2009 IBC code sections referenced
in this report are the same sections in the ADIBC.

Property evaluated:
Structural
2.0 USES
®

Intermediate
The
Rammed
Aggregate
Pier
Foundation/Soil Reinforcement System (hereinafter
referred to as Rammed Aggregated Pier System or RAP
System) is a supplemental foundation system to the
shallow foundations specified in Section 1809 of the 2018,
2015, 2012 and 2009 IBC (Section 1805 of the 2006 and
2003 IBC), as applicable. The Rammed Aggregate Pier
Intermediate Foundation/Soil Reinforcement System is
used to support shallow footings, reinforced concrete mat
foundations, and reinforced concrete floor slabs on-grade.
3.0 DESCRIPTION
The RAP system is constructed by removing a volume of
unsuitable subsurface soils and replaced by a compacted
vertical column of well-graded aggregates. The elements
of Rammed Aggregate Pier Systems are constructed from
generally available graded stone aggregate through use of
processes proprietary to Geopier Foundation Company.
Aggregates must comply with ASTMD1241. The
geotechnical investigation described in Section 4.1 of this
report may specify additional requirements. Aggregate is
densified by ramming, forming rammed aggregate piers
with a stabilized base.

The Rammed Aggregate Pier Intermediate Foundation/Soil
Reinforcement System, including aggregate type and size
and pier diameter and depth, must be designed for its
intended use, in accordance with Chapter 18 of the IBC,
and account for the site-specific geotechnical investigation,
described in Section 4.1. The design must be prepared by
a registered design professional, retained by the local,
licensed RAP system installer, using the Geopier
Foundation and Soil Reinforcement Manual, dated
September 1998. Additionally, each system design must
be approved by the Chief Engineer of the Geopier
Foundation Company of Mooresville, North Carolina.
A geotechnical investigation must be conducted and
reported in accordance with Section 1803 of the 2018,
2015, 2012 and 2009 IBC (Section 1802 of the 2006 and
2003 IBC), as applicable. At a minimum, the geotechnical
investigation must address the following: soil strength,
ground-water table, the effect of moisture variation on soil
bearing capacity, compressibility, liquefaction and
expansiveness. For structures assigned to Seismic Design
Category C, D, E or F, Site Class E or F sites, the
geotechnical investigation must include an evaluation of
potential geologic and seismic hazards, such as
liquefaction, soil instability, differential settlement and
surface displacement, and provide recommended
mitigation measures. Drainage, and the effects of
surcharges from new site grading fill, shall be considered,
when applicable.
Loading imposed on the RAP system and the
corresponding induced force and deformation, must be
determined using accepted structural and geotechnical
engineering procedures appropriate for the soil and
geometric conditions specific for the RAP system, and
must address the effect of geologic and seismic hazards
described in Section 4.1, and consider soil-RAP pier
supported shallow foundation-structure interaction, when
applicable.
4.2 Installation:
Rammed Aggregate Pier systems must be installed using
®
either a replacement (trade name Geopier ) system, or
®
displacement (trade name Impact ) system.
Each replacement Geopier element must be constructed
by first excavating a hole in the soil. Most holes are from
10 to 40 feet (3048 to 12192 mm) deep, with diameters
ranging from 18 to 36 inches (457 to 914 mm). The size
and depth of the holes must be determined by the Geopier
system designer on the basis of the geotechnical site

ICC-ES Evaluation Reports are not to be construed as representing aesthetics or any other attributes not specifically addressed, nor are they to be construed
as an endorsement of the subject of the report or a recommendation for its use. There is no warranty by ICC Evaluation Service, LLC, express or implied, as
to any finding or other matter in this report, or as to any product covered by the report.
Copyright © 2018 ICC Evaluation Service, LLC. All rights reserved.

Page 1 of 3

ESR-1685 | Most Widely Accepted and Trusted
conditions and structural requirements of the project. Once
a hole is excavated, a bottom bulb is created by placing
graded stone aggregate into the bottom of the hole and
ramming the aggregate using equipment with a specially
designed rammer head having 45-degree angled sides.
Once the bottom bulb is in place, successive lifts of graded
stone aggregate, with an average compacted lift thickness
of 12 to 36 inches (305 to 914 mm), are placed in the hole
and rammed. Figure 1 of this report illustrates the Geopier
system construction process.
Each displacement Impact element must be constructed
by first driving a specially designed 14- to 16- inchdiameter (356 to 406 mm) tamper foot and 10- to 12- inchouter diameter (250 to 305 mm) hollow mandrel into the
soil using a large static force augmented by high-frequency
vertical impact energy. The piers can typically extend
between 25 and 45 feet (7.6 to 13.7 m) below grade, but
may extend deeper depending on project requirements
and equipment size. A sacrificial steel plate placed at the
bottom of the tamper or other flow restrictors in the
mandrel prevent soil from entering the mandrel during
driving. After driving to the design depth, aggregate is
placed inside the mandrel and the mandrel is raised
approximately 3 to 5 feet (914 to 1524 mm) and then
re-driven down to 1 to 3 feet (305 to 914 mm), forming an
approximate 1 to 3-foot-thick (305 to 914 mm) compacted
lift. Compaction is achieved through the static crowd force
and dynamic impact energy from the hammer. Subsequent
lifts are performed using the same approach of raising and
lowering the mandrel. Upon completion of the pier to the
top-of-pier elevation, the crowd force is used to pre-stress
the top of the pier. Figure 2 of this report illustrates the
Impact system construction process.
The combined effect of the pattern of RAP elements
(either by Geopier or Impact system installation) and the
pre-strained soil matrix between and around RAP elements
results in a reinforced block of RAP/matrix soil beneath the
footing to the depth of the RAP element construction.
Spread footings must be placed over the top of the RAP
elements in accordance with Chapter 18 of the IBC.
Depending on the soil conditions and loads to be
supported from the structure, RAP elements are typically
constructed to cover 10 percent to 35 percent of the
footprint of the supported spread footing. The RAP
designer must provide the allowable design bearing
pressure for spread footings, mats or slabs placed over the
RAP reinforced soil.
Geopier elements are constructed to a level 6 to 12
inches (152 to 305 mm) above the scheduled bottom of the
shallow foundations, and the remaining portion of the open
holes is temporarily filled to the ground surface with loosely
placed drilling spoils. Impact piers are constructed in a
similar manner except that the hole is often backfilled with
aggregate as the mandrel is withdrawn. For placement of
the concrete footings over the Geopier or Impact elements,
the soil is excavated to the specified level of the bottom of
the footing. The tops of the exposed RAP elements, as
well as the bottom of the footing excavation, are tamped
with a mechanical compactor prior to placement of the
concrete footings.
4.3 Special Inspection:
Special inspection must be provided in accordance with
Section 1705 for 2018, 2015 and 2012 IBC (Section 1704
for 2009, 2006 and 2003 IBC), as applicable. The special
inspector’s responsibilities include, but are not limited to,
review of the RAP designer’s use of soil parameters as

Page 2 of 3
presented in the project-specific soils report; and, during
construction, verification of aggregate properties, type and
number of lifts of aggregate, pier size and depths and top
elevations of constructed RAP elements, and applied
rammer energy. Additionally, results of qualitative tests on
production RAP elements, outlined in the Geopier
Foundation and Soil Reinforcement Manual, dated
September 1998 and the RAP specification, such as
modulus load testing, uplift pull-out testing, bottom or
crowd stabilization tests and dynamic cone penetration
tests, must be reviewed to verify compliance with the
design specifications. Testing must be conducted by an
approved testing laboratory and the results must be
approved by the code official.
5.0 CONDITIONS OF USE
The RAP Intermediate Foundation/Soil Reinforcement
®
®
System, constructed with Geopier and Impact system
installation methods, described in this report complies with,
or is a suitable alternative to what is specified in, those
codes listed in Section 1.0 of this report, subject to the
following conditions:
5.1 The installation of the system must comply with this
evaluation report, the Geopier Foundation and Soil
Reinforcement Manual dated September 1998, and
the RAP QC and construction specifications dated
December 2006 and October 2008.
5.2 The system must be installed by a Geopier
Foundation Company licensed installer. The evidence
of such approval by the Geopier Foundation
Company must be submitted to the code official upon
request.
5.3 Copies of the Geopier Foundation and Soil
Reinforcement Manual, dated September 1998, RAP
QC and construction specifications, dated December
2006 and October 2008, and the RAP specification,
dated April 1, 2011, must be provided to the code
official upon request.
5.4 Special inspection must be provided in accordance
with Section 4.3 of this report.
5.5 Engineering design of the Rammed Aggregate Pier
Intermediate Foundation/Soil Reinforcement System
in accordance with the Section 4.1 of this report,
prepared by a Geopier Foundation Company
authorized registered design professional and
approved by the Geopier Engineer, must be
submitted to the code official for approval at the time
of permit application- In the event of conflict between
the Geopier Foundation and Soil Reinforcement
Manual and this report, this report governs.
6.0 EVIDENCE SUBMITTED
Descriptive information and the Geopier Foundation and
Soil Reinforcement Manual, dated September 1998, and
construction specifications, dated December 2006 and
October 2008.
7.0 IDENTIFICATION
The engineering design of the Rammed Aggregate Pier
Intermediate Foundation/Soil Reinforcement System,
®
®
constructed with Geopier or Impact installation method
must include reference to the Geopier Foundation
Company name and address, and the ICC-ES evaluation
report number (ESR-1685).

ESR-1685 | Most Widely Accepted and Trusted

1.

Make cavity.

3. Make a bottom bulb. Densify
and vertically prestress matrix
soils beneath the bottom bulb.

Page 3 of 3

2. Place stone at bottom of cavity.

4. Make undulated-sided RAP
shaft 12 to 36-inch thick lifts. Build
up lateral soil pressures in matrix
soil during shaft construction.

FIGURE 1—RAP CONSTRUCTION PROCESS USING THE GEOPIER SYSTEM

1. Drive Impact
mandrel to
bottom of pier
depth

2. Fill hopper and
mandrel with
aggregate

3. Raise mandrel a
preset distance
(3 or 5 ft typ)
while discharging
aggregate

4. Redrive mandrel a
preset distance
(1 or 3 ft typ) to
create 1- to 3-ft
(typ) compacted
lift

5. Repeat Steps 3
and 4 until pier
construction is
complete

FIGURE 2—RAP CONSTRUCTION PROCESS USING THE IMPACT SYSTEM



Source Exif Data:
File Type                       : PDF
File Type Extension             : pdf
MIME Type                       : application/pdf
PDF Version                     : 1.6
Linearized                      : No
Encryption                      : Standard V4.4 (128-bit)
User Access                     : Print, Extract, Print high-res
Create Date                     : 2012:03:23 14:17:47-05:00
Modify Date                     : 2018:01:04 11:40:48-08:00
Subject                         : Rammed Aggregate Pier Intermediate Foundation/Soil Reinforcement System
XMP Toolkit                     : Adobe XMP Core 5.4-c005 78.147326, 2012/08/23-13:03:03
Creator Tool                    : PScript5.dll Version 5.2.2
Metadata Date                   : 2018:01:04 11:40:48-08:00
Producer                        : Acrobat Distiller 10.1.2 (Windows)
Format                          : application/pdf
Creator                         : 
Title                           : ESR-1685 - Geopier Foundation Co.
Description                     : Rammed Aggregate Pier Intermediate Foundation/Soil Reinforcement System
Document ID                     : uuid:42bac4bd-44df-4639-b829-91f0bfaedeb5
Instance ID                     : uuid:382fb032-6d55-407f-ae28-314ad3dc5091
Page Count                      : 4
EXIF Metadata provided by EXIF.tools

Navigation menu