For Publication TIA Manual Jan2015

User Manual:

Open the PDF directly: View PDF PDF.
Page Count: 1

DownloadFor Publication - TIA Manual Jan2015
Open PDF In BrowserView PDF
The TIA Manual

Program Management Plan for
Transportation Investment Act of 2010 (TIA)
January 2015
Prepared for:

Georgia Department of Transportation
TIA Office

Version: v2.2.0

The TIA Manual (Program Management Plan)
Prepared for
Georgia Department of Transportation
TIA Office
Prepared by
AECOM Technical Services, Inc.
In association with
Georgia DOT

January 2015

ISSUED FOR USE

Recommended By:

Approved By:

____________________________________________

________________________________________________

Anthony J Sanger
TIA Program Manager

Mike Dover
State TIA Administrator

The TIA Manual (Program Management Plan)

Contents
1

2

3

4

Introduction ......................................................................................................................................... 1
1.1

The TIA Manual ..................................................................................................................1

1.2

Future Development of the TIA Manual ..............................................................................1

1.3

Purpose of the TIA Manual .................................................................................................1

1.4

Intended Users of the TIA Manual ......................................................................................1

1.5

Abbreviations .....................................................................................................................2

1.6

Definitions ..........................................................................................................................3

1.7

Reference Documents ........................................................................................................5

Program Goals and Objectives ........................................................................................................... 7
2.1

Program Requirements and Regulations ............................................................................ 7

2.2

Program Management Work Flow ......................................................................................8

Program Delivery ................................................................................................................................ 9
3.1

Management Authority .......................................................................................................9

3.2

Roles and Responsibilities .................................................................................................9
Program Team Members and Responsibilities ........................................................ 9

3.2.2

Key Management.................................................................................................. 10

3.2.3

PgM Responsibilities............................................................................................. 10

3.2.4

Certifications ......................................................................................................... 11

3.2.5

Work Authorizations .............................................................................................. 11

3.2.6

Project Cost Estimates.......................................................................................... 11

3.2.7

Band Change Requests ........................................................................................ 11

Communications Management.......................................................................................................... 12
4.1

5

3.2.1

General Policies ...............................................................................................................12
4.1.1

Conflicts of Interest ............................................................................................... 12

4.1.2

Communications Management Policy ................................................................... 12

Scope, Budget, and Schedule Management ..................................................................................... 13
5.1

Project Initiation ................................................................................................................13

5.2

Concept Reports ..............................................................................................................13
5.2.1

Blended Projects................................................................................................... 13

5.2.2

100% TIA Funded projects.................................................................................... 13

JANUARY 2015 UPDATE

Page i

The TIA Manual (Program Management Plan)

5.3

Design to Budget .............................................................................................................. 13

5.4

Project Schedules and Cash Flows .................................................................................. 14

5.5

Program Development and Monitoring ............................................................................. 14
5.5.1

Cost Estimate Reviews ......................................................................................... 14

5.5.2

Value Engineering ................................................................................................ 14

6

Risk Management ............................................................................................................................. 15

7

Procurement and Bidding.................................................................................................................. 16
7.1

Local Delivery Application ..................................................................................... 16

7.1.2

Local Delivery Agreement Hold Points .................................................................. 16

Design Services ............................................................................................................... 16

7.3

Construction .....................................................................................................................16
7.3.1

Plans, Specifications, Special Provisions and Final Estimate (PS&E) ................... 16

7.3.2

Bid Package Development .................................................................................... 16

DBE, Small Business and Veteran Owned Business ........................................................ 17

Contract Administration ..................................................................................................................... 18
8.1

Design Contracts .............................................................................................................. 18

8.2

Bid Review .......................................................................................................................18

8.3

Construction Contracts ..................................................................................................... 18

8.4

9

7.1.1
7.2

7.4
8

Local Delivery ...................................................................................................................16

8.3.1

Compliance ...........................................................................................................18

8.3.2

Supplemental Agreements .................................................................................... 19

Other Fees .......................................................................................................................19
8.4.1

Right of Way ......................................................................................................... 19

8.4.2

Environmental Mitigation ....................................................................................... 19

8.4.3

USACE 404 Permit / Buffer Variance .................................................................... 19

8.4.4

National Pollutant Discharge Elimination System (NPDES) Fees.......................... 19

Environmental Management ............................................................................................................. 20
9.1

Environmental Policy ........................................................................................................ 20

9.2

Environmental Objectives of the TIA Program .................................................................. 20

9.3

9.2.1

Project-Specific Environmental Compliance .......................................................... 20

9.2.2

Environmental Strategy......................................................................................... 21

Environmental Responsibilities Overview ......................................................................... 21

JANUARY 2015 UPDATE

Page ii

The TIA Manual (Program Management Plan)

9.4
10

Local Let and 100% TIA Funded Projects ............................................................. 22

9.3.2

GDOT Let and 100% TIA Funded Projects ........................................................... 22

9.3.3

Borrow/Waste/Stockpile Sites ............................................................................... 23

Environmental Compliance ............................................................................................... 23

Utility and Railroad Coordination ....................................................................................................... 26
10.1

Utility Accommodation Standards ..................................................................................... 26

10.2

Responsibilities ................................................................................................................ 26

10.3

11

9.3.1

10.2.1

Blended Projects................................................................................................... 27

10.2.2

100% TIA Funded Projects ................................................................................... 27

Identification of Utilities and Notification of Utility Companies ........................................... 27
10.3.1

Direct Communication with Utility Companies ....................................................... 27

10.3.2

Need for SUE Services ......................................................................................... 27

10.3.3

Utility Permitting .................................................................................................... 27

10.4

Certification of Utilities ...................................................................................................... 27

10.5

Utility Relocation Work and Construction Schedules ........................................................ 28

10.6

Utility Relocations/Coordination during Construction ........................................................ 28

10.7

Utility Reimbursement ...................................................................................................... 28

10.8

Utility and Railroad Owner Meetings and Correspondence ............................................... 28

10.9

Record Keeping................................................................................................................ 28

Right-of-Way Management ............................................................................................................... 35
11.1

General Acquisition Requirements ................................................................................... 35

11.2

Responsibilities ................................................................................................................ 35

11.3

GDOT ROW Acquisition Management ............................................................................. 36

11.4

Local ROW Acquisition ..................................................................................................... 36
37

12

11.5

Abbreviated Valuation Methods ........................................................................................ 38

11.6

Advanced ROW Acquisition ............................................................................................. 38

11.7

Condemnation .................................................................................................................. 38

Design Management ......................................................................................................................... 40
12.1

Roadway Design ..............................................................................................................40
12.1.1

On-System and Off-System Roadways ................................................................. 40

12.1.2

Roadway Design Specifications ............................................................................ 40

JANUARY 2015 UPDATE

Page iii

The TIA Manual (Program Management Plan)

12.1.3

Responsibilities ..................................................................................................... 41

12.1.4

Survey and Mapping ............................................................................................. 41

12.1.5

Soil Survey ........................................................................................................... 42

12.1.6

Pavement Evaluation and Design ......................................................................... 42

12.2

Municipal Separate Storm Sewer System (MS4) .............................................................. 42

12.3

Highway Signing and Pavement Markings........................................................................ 42

12.4

Traffic Operations .............................................................................................................42
12.4.1

Roundabouts, Alternative Interchanges and Intersection Design .......................... 42

12.4.2

Traffic Control Signals........................................................................................... 43

12.4.3

Intelligent Transportation Systems (ITS) ............................................................... 43

12.4.4

On-System and Off-System Bridges ..................................................................... 43

12.4.5

Bridge Design Specifications ................................................................................ 43

12.4.6

Responsibilities ..................................................................................................... 44

12.4.7

Bridge Details ....................................................................................................... 45

12.4.8

Concept and Preliminary Plans ............................................................................. 47

12.4.9

Final Plans ............................................................................................................ 47

12.4.10 Retaining Walls ..................................................................................................... 48
12.4.11 Bridge Condition Surveys ..................................................................................... 48
12.4.12 Bottomless Culverts .............................................................................................. 48
12.4.13 Construction Phase .............................................................................................. 48
12.4.14 Load Rating .......................................................................................................... 49
12.4.15 Final Acceptance .................................................................................................. 50

13

12.5

Design Exceptions/Variances ........................................................................................... 53

12.6

Field Plan Review.............................................................................................................53

12.7

Airport Projects .................................................................................................................53

12.8

ADA Compliance ..............................................................................................................54

12.9

Lighting ............................................................................................................................54

Construction Administration .............................................................................................................. 55
13.1

Preconstruction Conference ............................................................................................. 55

13.2

Construction Engineering and Inspection ......................................................................... 55

13.3

Construction Audits .......................................................................................................... 55

13.4

Site Manager ....................................................................................................................55

JANUARY 2015 UPDATE

Page iv

The TIA Manual (Program Management Plan)

13.5

Materials ..........................................................................................................................55
13.5.1

13.6

14

Project Closeout ............................................................................................................... 56
13.6.1

Final Inspection..................................................................................................... 56

13.6.2

Final Audit............................................................................................................. 56

13.6.3

Final Payment ....................................................................................................... 56

13.6.4

As-Built Plans ....................................................................................................... 57

13.6.5

Final Acceptance .................................................................................................. 57

Quality Management ......................................................................................................................... 61
14.1

15

Local Let Responsibilities for Material Quality Assurance of On-System Projects . 56

Introduction ......................................................................................................................61
14.1.1

Quality Assurance Elements ................................................................................. 61

14.1.2

Quality Control Elements ...................................................................................... 61

14.1.3

Design ..................................................................................................................61

14.1.4

Construction ......................................................................................................... 62

Safety ............................................................................................................................................... 63

JANUARY 2015 UPDATE

Page v

The TIA Manual (Program Management Plan)

1 Introduction
1.1

The TIA Manual

The TIA Manual is the central coordinating document that describes the essential elements of the TIA Program.

1.2

Future Development of the TIA Manual

The TIA Manual is a living document that applies only to the TIA Program. Updates to the TIA Manual will reflect program
achievements, changes, constraints, remedial measures, and other ongoing variables. The TIA Manual will be reviewed quarterly
with an expected annual revision (refresh) cycle or more frequently as the Program warrants.
The TIA Program Manager (PgM) is responsible for maintaining revisions or additions to the TIA Manual. Once approval from
GDOT has been given on proposed changes, the PgM will finalize the update and distribute the revised TIA Manual through the
TIA website (www.ga-tia.com).

1.3

Purpose of the TIA Manual

The TIA Program contains two different types of project funding:
1.

Regional: 75% of the Special District’s TIA proceeds are used to fund all projects on the Special District’s Approved
Investment List. GDOT is responsible for delivery of these projects.

2.

Local: 25% of the Special District’s TIA proceeds are divided among all local government within the Special District for
use on transportation projects as determined by the local government (the discretionary funds).

Projects that have federal funds and require a future federal action will follow GDOT’s PDP.
The TIA Manual is the core document for defining how the TIA Program is managed. The TIA Manual is intended to provide high
level guidance necessary to efficiently and effectively deliver the projects on the Approved Investment List(s) from the
Transportation Investment Act of 2010 (Program). All parties involved with any facet of this project delivery process must stay
focused on delivering the intended projects to the citizens of each Special District on schedule and within budget. For any specific
areas that are not included in the PMP, please seek guidance from the PgM.
In the event of a conflict between the TIA Manual and any individual contract, the legally–binding contractual agreements will
prevail.
Regardless of whether the roles and responsibilities are defined by this TIA Manual or a contract, the PgM with the concurrence of
GDOT, determines whether costs associated with the delivery of a project are eligible for payment or reimbursement using TIA
funds.

1.4

Intended Users of the TIA Manual

The audience for the TIA Manual will be the Program Management team, GDOT, participating counties and municipalities, design
consultants, contractors, and other consultants and specialist advisors.

JANUARY 2015 UPDATE

Page 1

The TIA Manual (Program Management Plan)

1.5

Abbreviations

Table 2-1: List of Abbreviations
Abbreviation
AASHTO
ADA
BFI
BMP
BV
CE
CEI
CSRA
COP
CM
CES
CRP
DC
DE
DP & S
DPM
DV
EA/FONSI
EDG
EOR
EPD
EPM
ESPCP
FHWA
FPR
GDNR
GDOT
GDOT OES
GEPA
GSFIC
GUCC
GUPS
HOGA
IGA
ITS
L&D
LAP
LFR
LIA
LRFD
LRFR
MOU
MPO
MS4
MUTCD
NEPA
NHPA
NOI
NPDES
O.C.G.A.
PID
PDP
PPG
QA
JANUARY 2015 UPDATE

Description
American Association of State Highway and Transportation Officials
Americans with Disabilities Act
Bridge Foundation Investigation
Best Management Practices
Buffer Variance; impacts to vegetative buffers of Waters of the State
NEPA Categorical Exclusion
Construction Engineering and Inspection
Central Savannah River Area Special District
Communications and Outreach Plan
Construction Manager
Cost Estimation System [ Trns•port Cost Estimation System (CES®) ]
Citizens Review Panel
Design Consultant
Design Exception
GDOT’s Office of Design Policy & Support
GDOT Design Policy Manual
Design Variance
NEPA Environmental Assessment/Finding of No Significant Impact
Electronic Data Guidelines
Engineer of Record
Environmental Protection Division
Environmental Procedures Manual
Erosion, Sediment, and Pollution Control Plans
U.S. Department of Transportation, Federal Highway Administration
Field Plan Review
Georgia Department of Natural Resources
Georgia Department of Transportation
Georgia Department of Transportation Office of Environmental Services
Georgia Environmental Policy Act
Georgia State Financing and Investment Commission
Georgia Utility Coordination Council
Georgia Utility Permitting System
Heart of Georgia – Altamaha Special District
Intergovernmental Agreement between GDOT and GSFIC dated 1/1/2013
Intelligent Transportation System
Location and Design
Local Administered Project
Load Factor Rating
Local Issuing Authority
Load and Resistance Factor Design
Load and Resistance Factor Rating
Memorandum of Understanding
Metropolitan Planning Organization
Municipal Separate Storm Sewer System
Manual on Uniform Traffic Control Devices
National Environmental Policy Act
National Historic Preservation Act
Notice of Intent
National Pollutant Discharge Elimination System
Official Code of Georgia, Annotated
Public Interest Determination
GDOT Plan Development Process
Plan Presentation Guide
Quality Assurance
Page 2

The TIA Manual (Program Management Plan)

Abbreviation
QC
QPL
RFI
RFP
ROW
RFQ
PgM
PM
PMIS
PMP
PPM
QBS
RV
SAAG
Section 404
SME
SUE
SOQ
SWMP
TIA
TRC
UAM
UCM
UPC
USACE
WBS
VE
WFI

1.6

Description
Quality Control
Qualified Product List
Request for Information
Request for Proposal
Right-of-Way
Request for Qualifications
Program Manager
Project Manager
Program Management Information System
Program Management Plan, also known as the TIA Manual
Program Procedure Manual
Qualifications Based Selection
River Valley Special District
Special Assistant Attorney General
Section 404 of the Clean Water Act; impacts to Waters of the U.S.
Subject Matter Expert
Subsurface Utility Engineer
Statement of Qualifications
Storm Water Management Program
Transportation Investment Act of 2010
TIA Regional Coordinator
GDOT Utility Accommodations Manual
Utility Coordination Manager
Utility Protection Center
U.S. Army Corps of Engineers
Work Breakdown Structure
Value Engineering
Wall Foundation Investigation

Definitions

Bridge Foundation Investigation (BFI) – Engineering report documenting the existing subsurface conditions, identifying the
recommended foundation type, and defining the parameters to be used for the design of bridge foundations.
Blended Project – A project funded in part with federal money.
Chief Engineer – The Engineering Executive appointed by the Commissioner, or other authority as provided by law, and acting for
GDOT within the authority and scope of duties assigned.
Construction Manager – PgM staff member responsible for coordinating field operations, CE&I and materials testing coverage and
overall execution of construction of the TIA projects.
Design Build – Combining of design engineering and other preconstruction services with construction services into a single
contract.
Design-to-Budget – A requirement in the contract between an owner and a design professional that requires the design
professional to design a project which meets the needs of the owner without exceeding the budget established by the owner or
redesign the project at no additional cost to the owner if the construction bid exceeds the owner's budget.

JANUARY 2015 UPDATE

Page 3

The TIA Manual (Program Management Plan)

Engineer of Record (EOR) – A licensed professional engineer in Georgia who develops and/or is responsible for the overall design,
design criteria and components of a project. This person may delegate responsibility for the design of a system or component part
to a delegated engineer but is ultimately responsible for the delegated engineer’s design and the project’s total design.
Environmental Documentation – The documentation necessary to ensure a project’s compliance with the National Environmental
Policy Act of 1969 (NEPA), or the Georgia Environmental Policy Act of 1991 (GEPA) and/or all federal and State permit
requirements as applicable.
Local Government – Any municipal corporation, county, or consolidated government created by the General Assembly or pursuant
to the Constitution and laws of the State of Georgia.
Load Resistance Factor Design (LRFD) – A design methodology for structures that utilize load factors developed using
probabilistic methods for the design of structural elements.
Off-System – Work on a Local road system that does not meet the definition of an On-System route.
On-System – Work on a roadway designated as a State route, Interstate route, or locally owned roadway that traverses over or
under a state or interstate route which is designated to be designed to On-System criteria by the Chief Engineer.
Political Subdivision – The State or any local subdivision of the State or public instrumentality or public corporate body created by
or under authority of State law, including, but not limited to, municipalities, counties, school districts, special taxing districts.
Plan Development Process (PDP) – GDOT manual that outlines the current process of project development from the project
identification through construction award or Final Acceptance for all federal aid projects under GDOT oversight.
Plan Presentation Guide (PPG) – A guide that sets forth the criteria for the electronic appearance and format of plans. These
criteria establish, define, and clarify procedures and standards for plans to be used by GDOT. These criteria are not intended to
establish design processes; rather, they are guidelines to assure that all drawings have uniform appearance and include all
pertinent information, avoid unnecessary information, and reflect high quality workmanship.
Program Manager (PgM) – GDOT’s consultant representative that will manage, provide oversight and approve all project phases
and activities to ensure that all elements of the work meet the required laws, regulations, quality, design standards, schedule and
budget. The Program Manager has delegated authority to act on GDOT’s behalf, and will provide the resources and expertise
necessary to understand, and be responsible for, a broad spectrum of services related to the TIA Program.
Project Manager (PM) – PgM staff, GDOT staff or consultant representative responsible for leading a project from its inception to
execution, including planning, execution and managing the people, resources and scope of the project.
Soil Survey – A report developed to provide project designers with safe, effective and cost efficient recommendations for the
design of roadway foundations, embankments and the treatments for Geotechnical and other problems on the project. Soil Survey
reports may also be used by contractors to assist in preparing bids and by project engineers during construction to identify and
help solve problems.
Special Districts – The twelve special districts based on existing Regional Commission boundaries as created by O.C.G.A. § 48-8241. A link to a map indicating the District boundaries can be found on the GDOT TIA website. To date, there are three Special
JANUARY 2015 UPDATE

Page 4

The TIA Manual (Program Management Plan)

Districts which voted to levy the special district transportation sales and use tax: Central Savannah River Area, Heart of Georgia –
Altamaha, and River Valley.
State TIA Administrator – GDOT representative from the TIA Office with oversight responsibility for the TIA Program and the TIA
Regional Coordinator(s).
Storm Water Management Program (SWMP) - The program to provide requirements to Local Governments and staff on
addressing storm water runoff to both improve storm water quality and reduce quantity impacts, and protect downstream areas and
receiving waters. It does not cover construction site sediment and erosion control practices. Guidance on these practices can be
found in the Manual for Erosion and Sediment Control in Georgia.
Subject Matter Expert (SME) – An individual who exhibits the highest level of expertise in performing a specialized job, task, or skill
within the organization performing the work; anyone with in-depth knowledge of the subject.
TIA Regional Coordinator (TRC) – GDOT representative from the TIA Office with responsibility for coordinating with the Local
Governments within their assigned Special District(s).
The Source – The Source is GDOT’s online reference for contractors. Within The Source, contractors will find information
pertaining to bridges, culverts and retaining walls, construction manual, erosion control, earthwork, pavements, special provisions,
specifications, and sampling, testing, and inspection.
Transportation Investment Act of 2010 (TIA) - The Act that created 12 Special Districts of the State and authorizes elections to be
held in each Special District which would allow each Special District independently of any other Special District to approve and
authorize the imposition of a special district transportation sales and use tax to fund transportation projects within the Special
District. O.C.G.A. § 48-8-240 et seq.
Wall Foundation Investigation – Engineering report documenting the existing subsurface conditions, identifying the recommended
foundation type, and defining the parameters to be used for the design of wall foundations.

1.7

Reference Documents

GDOT Bridge and Structures Design Manual

http://www.dot.ga.gov/doingbusiness/PoliciesManuals/roads/BridgeandStructure/GDOT_Bridge_and_Structures_Policy_Manual.pdf

GDOT Design Policy Manual
http://www.dot.ga.gov/doingbusiness/PoliciesManuals/roads/DesignPolicy/GDOT-DPM.pdf
GDOT Disadvantaged Business Enterprise (DBE) Program
http://www.dot.ga.gov/doingbusiness/dbeprograms/Pages/default.aspx
GDOT Environmental Procedures Manual
http://www.dot.ga.gov/doingbusiness/PoliciesManuals/roads/Pages/EnvironmentalProceduresManual.aspx
GDOT Guidelines for Geotechnical Engineering Manual
http://www.dot.ga.gov/doingbusiness/materials/qaqc/pages/default.aspx
GDOT Local Administered Project Manual (LAP)
http://www.dot.ga.gov/localgovernment/FundingPrograms/Documents/LAPManual.pdf
JANUARY 2015 UPDATE

Page 5

The TIA Manual (Program Management Plan)

GDOT Pavement Design Manual
http://www.dot.ga.gov/doingbusiness/PoliciesManuals/roads/Pavement/Pavement%20Design%20Manual.pdf
GDOT Plan Development Process (PDP) Manual
http://www.dot.ga.gov/doingbusiness/PoliciesManuals/roads/PDP/4050-1.pdf
GDOT Prequalification for Contractors
http://www.dot.ga.gov/doingbusiness/prequalification/Pages/Contractors.aspx
GDOT Small Business Program
http://www.dot.ga.gov/doingbusiness/sbp/Pages/default.aspx
GDOT Utility Accommodation Policy and Standards Manual (UAM)
http://www.dot.ga.gov/doingbusiness/utilities/pages/manual.aspx
GDOT Survey Manual
http://www.dot.ga.gov/doingbusiness/PoliciesManuals/roads/SurveyManual/SurveyManual.pdf
Georgia Stormwater Management Manual
http://www.atlantaregional.com/environment/georgia-stormwater-manual
Regional Commission (RC) Boundaries Map
http://www.ga-tia.com/regions.aspx
The Source
http://www.dot.ga.gov/doingbusiness/TheSource/Pages/home.aspx
Transportation Investment Act of 2010 – Approved Investment List(s)
• Central Savannah River Area: http://www.ga-tia.com/Images/FactSheets/CSRA-finalinvestmentlistreport.pdf
• Heart of Georgia-Altamaha:
http://www.ga-tia.com/Images/FactSheets/HOG-finalinvestmentlistreport.pdf
• River Valley:
http://www.ga-tia.com/Images/FactSheets/RiverValley-FinalInvestmentListReport.pdf
Municipal Separate Storm Sewer System (MS4) Permit
http://www.georgiaepd.org/Files_PDF/techguide/wpb/Final_DOT_SW_NPDES_Permit_MS4_Dec_2011.pdf

JANUARY 2015 UPDATE

Page 6

The TIA Manual (Program Management Plan)

2 Program Goals and Objectives
The goals and objectives of GDOT in delivering the projects included in the TIA Program are as follows:
•

Support Georgia’s economic growth and competitiveness through transportation improvements

•

Improve access to jobs

•

Reduce congestion costs

•

Improve efficiency and reliability of commutes

•

Ensure more efficient and reliable movement of freight, cargo and goods

•

Improve interregional connectivity

•

Support local connectivity to statewide transportation network

•

Ensure safety and security: reduce accidents that result in injury and loss of life

•

Maximize the value of Georgia’s transportation assets: optimize capital asset management as well as flow of people and
goods through the network

•

2.1

Minimize the impact of transportation on the environment

Program Requirements and Regulations

The TIA Program is a “project driven program” designed to fund projects that have limited or no funding but are significant to each
Special District. Each Special District project list reflects prioritized decisions that have been made by local elected officials and
the public. GDOT is prepared to deliver these transportation improvement projects in these Special Districts by implementing a
streamlined delivery process that will assure strict attention to project delivery, budgets, and schedules. This process will
incorporate coordination with Regional Commissions and Local Governments, and will demonstrate transparency and
accountability to the Special Districts, Citizen’s Review Panel and the public.
The projects in the Approved Investment List(s) constitute the program for each Special District. The fundamental elements of the
management of the budget, schedule, execution, and delivery of the projects contained in the Approved Investment List(s) are:
•

All the projects on the Approved Investment List(s) must be delivered for each Special District

•

The project budgets are defined in the Approved Investment List(s) and are the maximum amount of special district
transportation sales and use tax proceeds (TIA funds) available for the project. Therefore, projects will be designed and
constructed to budget. GDOT is not responsible for supplementing or providing any additional funds unless otherwise
shown in the Approved Investment List(s).

•

Projects will be delivered on a pay as you go basis or as approved by GDOT should other funding be provided from a
sponsor. GDOT is responsible for determining when a project or project phase is initiated if TIA funds are required for the
phase.

•

The obligation for payment/reimbursement is limited to the amount of TIA funds available. Eligible Project Costs, as
defined in O.C.G.A. § 48-8-242(2) and in the IGA between GSFIC and GDOT, will be paid/reimbursed to the sponsor
and/or consultant/contractor upon the completion of the following:
o

Project element or project is complete and invoicing is submitted to PgM

o

GSFIC’s approval of GDOT’s certification

o

GDOT’s certification of invoices to GSFIC

o

GSFIC’s payment/reimbursement to GDOT

JANUARY 2015 UPDATE

Page 7

The TIA Manual (Program Management Plan)

To define the limitation of tax funds and payment obligations of GDOT to any entity under contract with GDOT relating to the TIA
Program, all contracts will include the following or similar provisions:
1.

The parties acknowledge that the program is one hundred percent (100%) funded with special district transportation sales
and use tax proceeds collected pursuant to the Act and that the Department’s payment obligations related to the program
and project are strictly limited as set forth herein. The parties further acknowledge that no entity of the State of Georgia
other than the Department has any obligations to the Consultant/Contractor related to this program or project.

2.

The obligation of the Department to pay or reimburse any incurred cost or pay any lump sum cost is expressly limited to
the amount of special district transportation sales and use tax proceeds remitted to the Department by GSFIC and
designated by the Department for the program in general and the project specifically. This agreement does not obligate
the Department to make any payment to the Consultant/Contractor from any funds other than those made available to the
Department from the special district transportation sales and use tax proceeds by GSFIC and designated by the
Department for the program in general and the project specifically.

In the event the funds made available to the

Department from the special district transportation sales and use tax proceeds are insufficient for the program and project
as designated by the Department, the Department’s payment obligations shall not exceed the availability of such special
district transportation sales and use tax proceeds and the Department shall have the right at its sole discretion to
terminate this agreement immediately upon notice to the Consultant/Contractor without further obligation of the
Department to the extent that the obligations exceed the availability of such the special district transportation sales and
use tax proceeds for the program and project as designated by the Department. The Department’s certification as to the
availability of the special district transportation sales and use tax proceeds as designated by the Department for the
program and project shall be conclusive.

2.2

Program Management Work Flow

To determine the approach and procedures to deliver of TIA projects, users need to understand the standard work flow as shown
in Figure 2-1. Procedures are based on these primary questions:
•

What is the funding source?

•

Who is letting the project to construction?

Figure 2-1 TIA Standard Work Flow
Projects that are a blend of TIA funding and Federal and State funding will follow GDOT PDP for those phases where federal funds
apply. Procedures for projects that are 100% TIA funded will follow this TIA Manual and will further depend on whether the project
is let to construction by GDOT or the Local Government sponsor and whether the project is on the GDOT managed roadway.
JANUARY 2015 UPDATE

Page 8

The TIA Manual (Program Management Plan)

3 Program Delivery
3.1

Management Authority

O.C.G.A. § 48-8-249 and the IGA delegates to GDOT the management of the budget, schedule, execution, and delivery of the
projects contained in the Approved Investment List(s) “for all transportation projects except bus and rail mass transit systems and
passenger rail in any special district the boundaries of which are not wholly contained within a single MPO.”

3.2

Roles and Responsibilities

GDOT’s organization chart, which includes the TIA Office, can be found on GDOT’s website at the following link:
http://www.dot.ga.gov/aboutGeorgiadot/Documents/OrgChart.pdf

3.2.1

Program Team Members and Responsibilities

Key entities of the TIA Program team include:
•

Department of Revenue

•

GSFIC

•

TIA Office

•

Program Manager

•

Design Consultants / Engineers of Record

•

Construction Engineering and Inspection consultants

The graphic below depicts the role of each team member. Citizen Review Panels (CRPs) provide oversight of the TIA Program.
The Regional Commissions support the CRPs and provide a forum for the Special Districts to address issues of a regional
significance that may occur.

Figure 3-1 TIA Program Agency Roles
JANUARY 2015 UPDATE

Page 9

The TIA Manual (Program Management Plan)

There are a number of GDOT offices, as well as other State offices and agencies that support the core team with the delivery of
the Program. Detailed roles and responsibilities for each GDOT Office can be found at
http://www.dot.ga.gov/aboutGeorgiadot/dotoffices/Pages/default.aspx . Coordination with other agencies will include, but not
limited to, the following:
o

Georgia Department of Natural Resources (GDNR)

o

Federal Highway Administration (FHWA)

o

Federal Emergency Management Agency (FEMA)

o

Environmental Protection Division (EPD)

o

U.S. Army Corp of Engineers (USACE)

3.2.2

Key Management

The PgM will report directly to the TIA Administrator and is charged with overall management of the PgM services and personnel to
ensure that the management activities are conducted in accordance with the TIA Manual, the Act and the contractual provisions
between GDOT and the PgM. As the principal contact with GDOT, the PgM is responsible and accountable for the successful
completion of the PgM contract within the agreed scope, which will include the requirements of being on budget and schedule. The
PgM is supported by a Program Team consisting of pre-construction managers, construction managers; program controls
specialists, subject matter experts and administrative support staff.

3.2.3

PgM Responsibilities

ANY AND ALL DISCUSSIONS OF THE PROGRAM, LOCAL GOVERNMENT, GDOT OR OTHER THIRD PARTY
RESPONSIBILITIES OR DUTIES IN THIS TIA MANUAL DO NOT IN ANY WAY MODIFY, SUPPLEMENT OR AMEND ANY
CONTRACTUAL REQUIREMENTS. TO THE EXTENT THAT THERE IS ANY CONFLICT BETWEEN CONTRACTUAL TERMS
AND THE TIA MANUAL, THE CONTRACTUAL PROVISIONS WILL CONTROL.
The following table provides an overview of PgM's duties.

JANUARY 2015 UPDATE

Page 10

The TIA Manual (Program Management Plan)

The PgM assists with developing the strategy best suited for the successful delivery of the Program. The PgM provides
collaboration, guidance, and acceptance of schedules and reliable cost estimates to GDOT. The PgM maintains the Master
Program Schedule, the cash flow model, and communicates program status through dashboard reporting.
It is the PgM’s responsibility to ensure that proper coordination is occurring between the EOR, Local Government, GDOT and all
other project team members involved in each of the projects. In conjunction with GDOT, the PgM will determine the frequency of
project status meetings to ensure effective management of the projects.
For 100% TIA funded projects, the PgM will manage the scope, schedule and budgets for of all projects in each special district;
keep GDOT well-informed of the progress of the projects through all phases; ensure that approvals and certifications are obtained,
close-out documents are completed in a timely manner, and warranty items are properly addressed; and serve as PM on projects
as directed by GDOT.
For blended projects, the PgM will coordinate with the GDOT designated PM and manage the project schedule and cash flow.

3.2.4

Certifications

For 100% TIA funded projects, the PgM is responsible for compiling all certifications and information, required from the project
delivery team, prior to beginning subsequent project phases or project letting. Responsibilities related to certification of
Environmental Compliance, Utility Clearance, and Right-of-way can be found in the applicable sections of this manual

3.2.5

Work Authorizations

The PgM will provide work authorizations with GDOT concurrence for each phase or any sub phase of a project regardless of
project sponsor or as otherwise specified in an intergovernmental agreement.

3.2.6

Project Cost Estimates

TIA budgets presented on the Approved Investment List(s) include all costs associated with administration, design, construction,
construction inspection, and material testing necessary to complete the project. The total cost to the project must be less than the
budget and funds must be available for payment at the time each element of the work, or portion of the work, is complete. At each
phase of design development, the EOR will produce an engineer’s estimate. The PgM will review these estimates, establish
contingencies, monitor cash flow and evaluate impacts to the program. The PgM and the EOR will work together to modify the
scope as necessary to deliver the project in a manner which meets the intent or predetermined benefit for the project.

3.2.7

Band Change Requests

The projects are to be let to construction in their original band, unless the band change requested by the local governments using
the Band Change Request Procedure is followed and approved by the TIA Administrator.

JANUARY 2015 UPDATE

Page 11

The TIA Manual (Program Management Plan)

4 Communications Management
4.1
4.1.1

General Policies
Conflicts of Interest

PgM staff, consultants, and contractors shall adhere to policies and provisions of O.C.G.A. § 45-10-20 through § 45-10-28 relating
to Conflict of Interest.
For the purposes of the TIA Manual, the definition of “Consultant” as contained in the Consultant Services Conflict of Interest Policy
shall include Consultants, Local Governments and Contractors. All references to consultant services shall include any and all
services provided by Local Government or the Contractor.

4.1.2

Communications Management Policy

Communications procedures are designed to support all program functions by ensuring smooth communications among all
participants and organizations.
Except for matters contractual in nature as specifically spelled out in a consultant or contractor’s contract, all communications
regarding the TIA Program shall be addressed to:
GDOT TIA Office
State TIA Administrator
One Georgia Center
600 West Peachtree Street
Atlanta, GA 30308

JANUARY 2015 UPDATE

Page 12

The TIA Manual (Program Management Plan)

5 Scope, Budget, and Schedule Management
5.1

Project Initiation

GDOT is responsible for delivering the projects in all Special Districts which voted to levy the special district transportation sales
and use tax. O.C.G.A. § 48-8-249(c) requires GDOT to determine if a project design and construction should be managed by
GDOT, a Local Government, or another public or private entity. Once that determination has been made, the project must be
implemented in accordance with applicable federal, state and local requirements. It is critical that projects be delivered in the most
cost effective manner possible as to maximize the use of the available TIA funds.
GDOT will coordinate with the Local Governments to determine their interest in project delivery. Each Local Government wishing to
deliver a TIA project must complete a Local Project Delivery Application as required by O.C.G.A. § 48-8-249(c). At GDOT’s
discretion, delivery by Local Governments may be by phase or by the entire project. Upon review and approval by GDOT, a project
specific contract, defining the responsibilities of GDOT and the Local Government for delivery, will be executed.

5.2

Concept Reports

The Concept Report is a record of the defined scope of work to be delivered for the project. The scope of the project shall

meet the stated benefit described in the Special District’s Approved Investment List(s) and must be clearly
stated in the Concept Report. With the exception of minor projects, Concept Reports shall be completed and approved for all
TIA funded projects at the discretion of the PgM. GDOT’s Chief Engineer must approve the Concept Report before a project can
be advanced to preliminary plans phase.

5.2.1

Blended Projects

Concept Reports for blended projects will follow the processes and templates defined by the latest GDOT Plan Development
Process (PDP) manual.

5.2.2

100% TIA Funded projects

Concept Reports for 100% TIA funded projects will be circulated to GDOT and local sponsors. For 100% TIA funded projects,
Concept Team Meetings will be scheduled at the discretion of the PgM and may not be required based on the PgM’s
recommendation and acceptance by GDOT.
Any changes to the original approved Concept Report for 100% TIA funded projects shall be summarized in a technical
memorandum. This technical memorandum shall be included with the original approved Concept Report and will serve as a
Revised Concept Report. Revised Concept Reports require PgM concurrence and GDOT’s approval.

5.3

Design to Budget

All projects will be designed and constructed to the project budget as established in the Approved Investment List(s). Appropriate
contingencies will be included in the project cost estimates. Each project must be delivered as presented in the Special District’s
Approved Investment List(s). The project scope shall be based on the work necessary to achieve the stated public benefits, if
identified in the Approved Investment List(s), while staying within the project budget. The non-regional projects in the HOGA do not
have a public benefit identified on the Approved Investment List.
The EOR shall take a practical design approach so to provide the most cost efficient design possible that satisfies the project
scope and budget. The scope of work approved in the Concept Report shall not change unless there are revenue shortfalls.
JANUARY 2015 UPDATE

Page 13

The TIA Manual (Program Management Plan)

Should a project budget be determined to be insufficient, the engineer of record will have flexibility, with PgM concurrence, to
modify certain project elements to reduce project cost as necessary to bring the project into alignment with the budget. The cost
estimate at the concept stage should identify any scope reduction that would cause the project benefits not to be satisfied. At a
minimum, cost estimates will be evaluated semi-annually throughout the development process to track cost to complete budget
requirements.
Below is the order of precedence of project elements that the engineer of record should use in designing to budget, without
compromising applicable engineering guidelines and standards. The list starts with the most important elements to the items of
less critical.
•

Safety features

•

Structural members and appurtenances

•

Operational features

•

Pavement Structure

•

Typical sections

•

Aesthetic and enhancements (unless necessary to satisfy the stated benefit)

The PgM will ensure the project is designed and constructed within budget as shown in the Approved Investment List(s). The PgM,
with GDOT’s concurrence, is responsible for approving the use of project contingencies regardless of the letting responsibility.

5.4

Project Schedules and Cash Flows

Project schedules and an initial cost estimate shall be included with the Concept Report. The TIA Program utilizes Primavera®
scheduling software to maintain the Master Program Schedule and will typically include a requirement in the contract that the
designer and contractor will utilize the same in the development of the project schedule. Regardless of the scheduling tool, the
consultants and contractors must include major milestones and activities with sufficient details and of reasonable durations to
properly describe and manage all phases of the Work. The PgM will review the impacts of the project schedules and cash flow
prior to recommending concept reports for approval.

5.5
5.5.1

Program Development and Monitoring
Cost Estimate Reviews

For GDOT let projects, the EOR is required to prepare the project cost estimate using Trns•port Cost Estimation System (CES®)
and submit it to the PgM at each stage of plan development (at a minimum annually), or as necessary when the project cost
significantly changes. The project manager will set up the CES® Estimate in the system. The PgM will review estimates for
compliance with the established project budget and coordinate scope changes and project contingencies with the EOR. The PgM
will ensure that estimates accommodate administrative, testing, CEI services and other appropriate costs.
Prior to each project submittal, the PgM will review the CES® Estimate for accuracy.

5.5.2

Value Engineering

Formal Value Engineering studies are not required on 100% TIA funded projects.

JANUARY 2015 UPDATE

Page 14

The TIA Manual (Program Management Plan)

6 Risk Management
Risk management supports a proactive approach to decision making in the project through identification, analyses, and responses
to project risks. It promotes quantification of project uncertainty and includes maximizing the results of positive events, and
minimizing the consequences of adverse events.
The Program’s risk management policies are based on the “Practice Standard for Project Risk Management” published in 2009 by
the Project Management Institute, and International Standard ISO 31000:2009 titled “Risk management – Principles and
guidelines.”
As the Program has and continues to evolve, the project and programmatic risk profiles will change. The PgM’s approach to risk
management is to perform risk assessments of the projects and the Program; quantify risk at the project, region and program level;
incorporate awareness of project risk exposure on the cash flow and its potential consequences; actively employ risk mitigation
measures in the management of the Program; report on the major risk issues to GDOT management; track progress of risk
mitigation efforts; and incorporate lessons learned from previous risk assessments continuously throughout the Program.

JANUARY 2015 UPDATE

Page 15

The TIA Manual (Program Management Plan)

7 Procurement and Bidding
7.1
7.1.1

Local Delivery
Local Delivery Application

GDOT created a Local Project Delivery Application for Local Governments interested in delivering their own projects. The
application is to be completed by the Local Government, or their authorized representative, and submitted to GDOT for approval.

7.1.2

Local Delivery Agreement Hold Points

The Local Agreement will typically contain language setting a schedule of expected milestone (hold) points that may include, but
are not limited to the following:
(1)
(2)
(3)
(4)
(5)

Preliminary Engineering Activities – Concept Report Approval
Preliminary Engineering Activities – Field Plan Review Approval
Right of Way
Construction – Notice to Advertise
Construction – Notice to Proceed

No work on any phase of the PROJECT shall begin without a written notice to proceed from the DEPARTMENT to the LOCAL
GOVERNMENT for each of the following separate phases. Each Notice to Proceed that is issued should contain a Completion
Date for that phase. If unforeseen conditions are encountered and an extension of the completion date is warranted, the LOCAL
GOVERNMENT may request in writing an extension of the completion date for written approval by the DEPARTMENT.

7.2

Design Services

Procurement of design services by GDOT must adhere to all state laws. Locally procured design services must adhere to the
procurement laws and regulations of the Local Government.

7.3
7.3.1

Construction
Plans, Specifications, Special Provisions and Final Estimate (PS&E)

The EOR is required to develop a complete P &E package including all of the required technical Special Provisions for the project.
The PgM will facilitate reviews of any supplemental specifications or special provisions and make any necessary recommendations
to GDOT regarding special provisions.
The PgM will review the EOR’s CES® Estimate for compliance with the project budget.
On GDOT Let projects, final corrected plans will be submitted to the Office of Engineering Services as required by the GDOT
Letting Schedule.
On Local Let projects, project sponsors shall submit the complete bid package to the PgM allowing 14 days for review and
approval. Upon acceptance of the bid package, the PgM will give written notification to the sponsor that the PS&E are acceptable
to bid.

7.3.2

Bid Package Development

For GDOT let projects, the PgM team reviews the PS&E package, checks the plans, obtains all required certifications and
authorizations and then provides the completed package to Office of Construction Bidding Administration (CBA) for advertising
bidding and award.

JANUARY 2015 UPDATE

Page 16

The TIA Manual (Program Management Plan)

7.4

DBE, Small Business and Veteran Owned Business

All projects in the TIA Program that include federal funds will adhere to existing GDOT DBE participation goals and are subject to
all oversight in that regard.
However, on May 17, 2012, the Georgia Department of Transportation, acting by and through its Board, passed a Resolution that:
1.

Reaffirmed its commitment to Title VI of the 1964 Civil Rights Act of nondiscrimination in the delivery and management of
TIA funded projects; and

2.

Encouraged the use of DBE's (including minority and woman owned businesses), small businesses, and veteran owned
businesses in any project that is funded in whole or in part by TIA funds, and encouraged wherever practical and feasible,
the Local Government or governments that manage TIA funded projects to include the same in its delivery and
management of a project.

Reference to this resolution shall be included in all 100% TIA funded projects contracts regardless of letting responsibility.
Contractual requirements will further detail reporting requirements.

JANUARY 2015 UPDATE

Page 17

The TIA Manual (Program Management Plan)

8 Contract Administration
8.1

Design Contracts

The PgM will manage the design process in order to ensure compliance with the scope, schedule, budget, and technical
requirements. See the Chapter 12 - Design Management of this manual for more information on the Design Management
responsibilities and requirements.
Design contract compliance is monitored throughout the duration of the contract. For design contracts, progress and payment for
services are tracked by the PgM in terms of progress achieved through plan development. If a consultant is found not to be in
compliance with the contract, GDOT may withhold payment and/or request that the work be redone.

8.2

Bid Review

8.2.1.1

GDOT Let Projects

GDOT Policy 2425-1: Bid Evaluation defines the internal procedures used to evaluate contractor bids for construction projects in
GDOT administered lettings. GDOT will tabulate bids and review the submitted bids for irregularities including but not limited to
unbalanced bids. GDOT will compare the apparent low bid with the Engineer’s Estimate and the project construction budget to
determine ability to award the project. The PgM will make a recommendation based on cash flow to GDOT whether to award,
defer, or reject the apparent low bid.

8.2.1.2

Local Let Projects

The Local Government is to submit bid tabs to the PgM for review. PgM will compare the apparent low bid with the Engineer’s
Estimate, project budget and projected cash flow to determine the ability to award each project. The PgM will make a determination
and provide a Notice to Proceed to the Local Government provided the project is compliant and funds are available. Where
possible and legally permitted, the PgM will provide the Local Government an opportunity to coordinate a resolution to budget
issues on a project prior to rejecting bids.

8.3

Construction Contracts

8.3.1 Compliance
For blended projects, the Office of Construction Bidding Administration (CBA) will administer TIA related contracts with support
from the PgM.
For GDOT let, 100% TIA funded projects; construction contract compliance is monitored throughout the construction duration.
Contractor progress and payment are computed based on amount of quantity constructed for each pay item. The Construction
Manager (CM) or designated CEI provider will verify quantity of materials used on construction and certify that materials are listed
on the QPL. The CM or designated CEI provider will enter progress into Site Manager software, which is used to generate
construction invoices.
For Local let projects, the Local Government must certify the construction for reimbursement with TIA funds.

JANUARY 2015 UPDATE

Page 18

The TIA Manual (Program Management Plan)

8.3.2 Supplemental Agreements
Supplemental Agreements may be initiated by the Local Government, Contractor, PgM, or GDOT. Supplemental Agreements
must be approved by the PgM and GDOT for conformance with the project budget and scope of services regardless of letting
responsibility. All changes in contract amount due to Supplemental Agreements must be reviewed and approved by the PgM and
GDOT to ensure compliance with project budget.

8.4

Other Fees

8.4.1 Right of Way
For GDOT let projects that are 100% TIA funded, the PgM will manage the ROW process.
For Local let projects that are On-System, the PgM will review and approve all ROW information and expenses. See Chapter 11.
For local let projects that are Off-System, the Local Government will certify the ROW. See Chapter 11.

8.4.2 Environmental Mitigation
When wetland acreage is disturbed, a stream is impacted or a variance is needed for a stream buffer on state waters, the PgM will
review the procurement of purchase of environmental mitigation credits in order for the project to move ahead. It is important to
note that all environmental mitigation must be complete prior to certification of letting.

8.4.3 USACE 404 Permit / Buffer Variance
The PgM will obtain confirmation of the number of credits that must be purchased from the project ecologist, review the estimated
cost for the mitigation credits based on recent purchases, and coordinate with the mitigation banks after approval.
After the bid is awarded, the bank(s) will send an invoice together with a copy of the PO, a copy of the letter sent to the USACE
notifying of the transfer of credits and any other supporting documents to the PgM.

8.4.4 National Pollutant Discharge Elimination System (NPDES) Fees
NPDES fees are paid each month to the Environmental Protection Division of the Department of Natural Resources (DNR) for land
disturbed as a result of projects awarded by GDOT. The fees are based on the amount of disturbed acreage.
GDOT Construction Bidding Administration staff will process the NPDES fees and the PgM will review and process and approve
them for payment.

JANUARY 2015 UPDATE

Page 19

The TIA Manual (Program Management Plan)

9

Environmental Management

9.1

Environmental Policy

GDOT and the PgM recognize that implementing the projects within this TIA Program may affect the natural, social, and/or human
environment. GDOT and the PgM are committed to identifying and documenting environmental resources; obtaining applicable
permits and authorizations; and avoiding/minimizing/mitigating impacts associated with program activities or works.
The TIA projects are required to follow an environmental process commensurate with the sources of funding, potential
environmental impacts, and jurisdiction of Federal and State agencies. The environmental process is a multi-disciplinary effort that
often requires consultation with a number of agencies and involvement with the public.

9.2

Environmental Objectives of the TIA Program

All works for the Program shall seek to enhance the built environment and, during construction, to avoid/minimize/mitigate
environmental impacts by:
•

Ensuring the design and construction of the projects is undertaken in an environmentally responsible manner and in full
compliance with the provisions of the relevant environmental statutory requirements

•

Identifying and mitigating environmental impacts

•

Committing resources to comply with the requirements, as presented in this TIA Manual

9.2.1

Project-Specific Environmental Compliance

Environmental impacts associated with TIA projects may require the involvement of local, State and Federal agencies through
approvals or permit obtainment. Examples include, but are not limited to, impacts to vegetative buffers of State Waters (Stream
Buffer Variance [BV] application approvals from the Georgia Department of Natural Resources [GDNR], Environmental Protection
Division [EPD]), impacts to Waters of the U.S. (Section 404 of the Clean Water Act Permit approval from the U.S. Army Corps of
Engineers [USACE]), and impacts to State and/or Federal protected species (coordination with the EPD and U.S. Fish and Wildlife
Service, respectively).
The funding type, letting responsibility, and location of the project (on or off the GDOT State Route system) are important in the
determination of environmental documentation requirements (see Figure 9-1, TIA Environmental Flowchart). Projects that use
Federal funds fall under Federal jurisdiction and are generally required to comply with National Environmental Policy Act (NEPA).
Projects that are 100% TIA funded and GDOT let, and projects that are 100% TIA funded and locally let that occur on the GDOT
State Route system are required to comply with the Georgia Environmental Policy Act (GEPA) process and all environmental
documentation to the TIA PgM for review. The TIA PgM functions as GDOT Office of Environmental Services (OES) for 100% TIA
funded projects. The GDOT Environmental Procedures Manual (EPM) shall be followed for GDOT let projects and for locally let
projects that occur on the GDOT State Route system. If a 100% TIA funded project shares common termini with a Federal Aid
project, then consultation with the GDOT TIA Office is required to determine if NEPA must be followed to protect the environmental
decision of the adjacent project. GDOT’s EPM describes in detail the policies and procedures of the GEPA and NEPA processes.
For projects that are 100% TIA funded and locally let that do not occur on the GDOT State Route system, the project sponsor shall
obtain all necessary state and federal environmental permits and approvals and provide certification to the TIA Office of same..
Consultants performing environmental surveys on the TIA Program shall carry a current copy of the Field Survey Right of Entry
letter at all times during field work. During field work this letter shall be provided to property owners whose property could be

JANUARY 2015 UPDATE

Page 20

The TIA Manual (Program Management Plan)

accessed by field personnel within the project study limits. See a sample Field Survey Right of Entry letter at the end of this
section.

Figure 9-1 TIA Environmental Flowchart
9.2.2

Environmental Strategy

An initial screening and project background research should be conducted as early as possible to determine the potential for
environmental impacts.
The preparation of environmental deliverables is one step in a series of approvals for a project to achieve construction
authorization. Early coordination with parties that have jurisdiction over the project will help clarify requirements and avoid
unnecessary delays. The responsible party for completion of the project’s Environmental Deliverables should identify critical path
tasks in the schedule and manage these tasks to expedite the delivery of the Environmental Documentation for environmental
processes associated with the applicable GEPA, NEPA, and environmental permitting and approval processes. There are a
variety of environmental deliverables that projects may require depending upon the funding source, letting authority, and
occurrence on or off the GDOT State Route system.
For all agency coordination, the TIA PM shall be included in any communications.
Efficiencies in the process should be considered and may include, but are not limited to initiating right-of-way acquisition
concurrently with the local environmental process to expedite project delivery. Elements of risk are inherent in allowing concurrent
activities rather than the typical sequential activities; however, these risks must be identified and actively managed by the project
sponsor.
GDOT’s TIA Office will have oversight responsibility for construction projects let by GDOT. It is the responsibility of the PgM to
ensure compliance with environmental commitments and NPDES permit requirements.

9.3

Environmental Responsibilities Overview

JANUARY 2015 UPDATE

Page 21

The TIA Manual (Program Management Plan)

Local, State, and Federal projects, regardless of letting responsibility, are required to coordinate, as applicable, with the GDNR
regarding the NPDES permit requirements, with the EPD to obtain BV encroachment approval for vegetative buffer impacts to
Waters of the State and purchase associated mitigation credits, and the USACE to obtain the appropriate Section 404 Permit for
impacts to Waters of the U.S. and purchase associated mitigation credits. If the project is locally let and not on a State Route, then
the project sponsor is the applicant for all applicable Federal and State permits and approvals (i.e., BV, Section 404 Permit, etc.)
and will purchase the appropriate mitigation credits. For GDOT let projects and local let on a State Route: 1) the project
environmental consultant will prepare and obtain Section 404 Permits and/or BV applications, 2) the PgM will review all Section
404 Permit and BV applications prior to transmittal to the applicable regulatory agency, and 3) the PgM will facilitate the purchase
of all Section 404 Permit and/or BV mitigation credits. It should be noted that the Section 404 permit is a Federal action and
Section 106 of the National Historic Preservation Act (NHPA) requires documentation of the archaeological and historic resources
within the project’s study area. For GDOT let projects, any Tribal consultation for GEPA/NEPA will be coordinated through GDOT.
The PgM will track the status of obtainment of applicable environmental permits and approvals relative to the project letting
schedule.
The responsible party for completion of the project’s Environmental Deliverables shall have the experience and qualifications, or
retain the experience and area class qualifications necessary to complete local, State, and Federal processes to ensure that
applicable requirements are being met. It is important to recognize the context within which the project resides to identify required
documentation. For instance, projects that cross federal jurisdictions or have federal funding are required to provide documentation
under the NEPA process (i.e., CE, EA/FONSI, EIS/ROD) since the project falls within the federal jurisdictional boundaries.

9.3.1

Local Let and 100% TIA Funded Projects

For locally let projects that do not occur on the GDOT State Route system, the sponsor or the sponsor’s duly authorized
representative shall complete the Environmental Certification Form at the end of this section, which certifies that compliance with
applicable local, State, and Federal environmental requirements.
For locally let projects that occur on the GDOT State Route system, the sponsor is required to prepare the appropriate GEPA
documentation (i.e., Type A Letter, Type B Letter, or EER/NOD). In addition to preparing the appropriate GEPA documentation, it
is the local sponsor’s responsibility to submit all necessary local, State, and Federal environmental permits in accordance with the
GDOT EPM to the TIA PgM for review and approval. Sponsors of local let projects that occur on the GDOT State Route system
shall implement appropriate construction monitoring activities to avoid environmental non-compliance.

9.3.2

GDOT Let and 100% TIA Funded Projects

Projects that are 100% TIA funded and that are GDOT let are required to follow the GEPA process. The preparation of all
environmental studies, GEPA documents and applicable permits must comply with the procedures outlined in the GDOT EPM.
The consultant will prepare all applicable environmental studies and GEPA documentation for the review and approval by the PgM
and the GDOT TIA Administrator.

The PgM will review all environmental applications prior to transmittal to the applicable

resource agency. Additionally, the PgM will facilitate the purchase of all Section 404 Permit and/or BV mitigation credits on behalf
of GDOT. For GDOT let projects all pre-construction environmental commitments must be obtained in order for the PgM to
complete the environmental certification for let (at least 11 weeks prior to the GDOT let date). For projects that require a 404
Permit and/or BV, “Final Plans” must be submitted to TIA PgM according to the schedule shown below. “Final Plans” are Plans to
which there can be no changes to impacts of the Waters of the US or State protected buffers once submittal is made.
•

404 Individual Permit – 27 weeks prior to let date

•

404 Nationwide or Regional Permit – 25 weeks prior to let date

•

BV only – 26 weeks prior to let date

JANUARY 2015 UPDATE

Page 22

The TIA Manual (Program Management Plan)

9.3.3

Borrow/Waste/Stockpile Sites

Blended projects will follow the PDP and EPM.
For 100% TIA projects, if it is determined that project requires the use of a borrow/waste/stockpile sites for the placement of
construction materials (i.e., soil cement base, sand clay base, base, etc.), or disposal of excess material, common fill, and inert
waste, the letting authority determines the process by which sites achieve environmental clearance by the local sponsor or by
GDOT and the TIA PgM.
For locally let projects, the local sponsor shall provide confirmation to the PgM indicating that environmental clearance work has
been completed and no significant environmental resources (i.e., waters of the U.S., state waters, cultural resources, and protected
species) would be affected. This confirmation can be achieved by a letter or copy of report documentation from the local sponsor.
For GDOT let projects the GDOT contractor shall submit to GDOT and the PgM a request for environmental survey and approval
to use an area for a borrow/waste/stockpile site. Upon receipt of the request of approval form, the PgM shall conduct
environmental survey and prepare an environmental survey results memo. It is the responsibility of the contractor to obtain all
local, State, and Federal permits and approvals. Within 45 calendar days/30 business days, the PgM shall issue an environmental
approval memo to the contractor if the site would not impact historical, archaeological, or federally protected species.

9.4

Environmental Compliance

GDOT’s Environmental Compliance Bureau will have oversight responsibility for all projects let by GDOT. It is the responsibility of
the PgM to ensure compliance with environmental commitments and NPDES permit requirements.

JANUARY 2015 UPDATE

Page 23

The TIA Manual (Program Management Plan)

JANUARY 2015 UPDATE

Page 24

The TIA Manual (Program Management Plan)

< Latest DOT letterhead >

Date:

Subject:



, , , County
Transportation Investment Act of 2010 (TIA) Project
Field Survey Right of Entry

Dear Property Owner,
We are requesting your cooperation in our continuing effort to provide a safe and efficient transportation system for the people of
Georgia.
The Georgia Department of Transportation (GDOT) is currently conducting environmental surveys for the above referenced
project. GDOT has contracted with  to provide professional services for this project. This project is in the
early stages of development and several alternative alignments are under consideration. A larger area of potential effect (APE) is
being considered for preliminary engineering purposes. The proposed alignment will be developed within the APE to minimize
harm to the natural, cultural, and built environment based on the location of sensitive ecological, historic, and archaeological
resources. These field surveys may require access to your property for the purposes of identifying ecological resources (protected
species, wetlands, streams, etc.), which may involve small auger tests and flagging of vegetation; identifying historic buildings by
evaluating properties 50 years of age or older and documenting them photographically and with a site plan and floor plan
sketches; and identifying archeological resources, which may require the excavation of small, temporary shovel or auger tests.
These surveys may also require the collection of samples for analysis and may include ecological specimens, archeological
collections, and soil samples, along with readings regarding air quality and noise levels. If more extensive work is required, (i.e.,
excavation of larger test unites), you will be personally contacted by GDOT or GDOT’s consultant.
During the course of our work it may be necessary for personnel to enter upon your property as provided for by Georgia Law,
Code 32-2-9(9) which states: The Department and its authorized agents and employees shall have the authority to enter upon any
lands in the state for the purpose of making such surveys, soundings, drillings, and examination as the Department may deem
necessary or desirable to accomplish the purpose of this title, and such entry shall not be deemed a trespass, nor shall it be deemed
an entry which would constitute a taking in a condemnation proceeding, provided that reasonable notice is given the owner or
occupant of the property to be entered and that such entry shall be done in a reasonable manner with as little inconvenience as
possible to the owner or occupant of the property. Please be assured that this work will be done in a professional manner with as
little inconvenience to you as possible.
The following contact information should be used regarding any questions you have about the project or the work to be
performed:
• GDOT Project Manager,  -- , 
• Consultant,  -- , 
I sincerely appreciate your cooperation and regret any inconvenience this work may cause.
Sincerely,


TIA Administrator
MD/
cc:



JANUARY 2015 UPDATE

Page 25

The TIA Manual (Program Management Plan)

10 Utility and Railroad Coordination
Existing utilities may be located within or in the vicinity of the existing or proposed ROW of TIA projects, some pursuant to statutory
rights or written permission and some pursuant to property rights. Existing utilities may need to be relocated or otherwise adjusted
in order to accommodate TIA projects. This Chapter establishes procedures and requirements for utility relocations, including such
processes as coordination with utility owners, preliminary engineering, construction and other activities necessary for utility
relocations, and the required documentation.
Effective coordination, communication, cooperation and commitment between GDOT, PgM, TIA Utility Engineer (TIAUE), utility
owners, Georgia Utility Coordinating Council (GUCC), Georgia Utilities Protection Center (UPC/811), District Utility Engineers
(DUE), railroads, municipalities, counties, contractors, and consultants are the key to successful utility coordination.
All existing policies and procedures governing railroads and railroad coordination will be used for TIA projects.

10.1 Utility Accommodation Standards
GDOT policies and procedures for utility relocation and coordination are defined in the GDOT Utility Accommodation Policy and
Standards Manual, current edition, also referred to as the GDOT Utility Accommodations Manual (UAM). All Utilities, whether
privately or publicly owned, will be required to comply with the policies and standards of the UAM when occupying or crossing any
part of the ROW of the State Highway System.
There may be circumstances where some variances to the UAM may be considered to accommodate the utility owners, GDOT,
counties, municipalities, contractors, property owners, locally impacted businesses or potentially affected third parties. Variances
will be addressed on a case by case basis and project by project basis. TIA utility special provisions will be required to cover any
approved variances. All variances from the UAM must be approved by GDOT’s State Utilities Office for blended projects; and
recommended for approval by the PgM to the TIA Administrator for 100% TIA funded projects prior to implementation.

10.2 Responsibilities
The roles and responsibilities related to utility certification on TIA projects are outlined in the following sections.

Figure 10-1 TIA Utility Responsibility Workflow
The TIAUE will assist the project consultants and contractors in accomplishing all Utility Coordination from Project Concept to
project closeout. The PgM will coordinate, provide direction and assist the contractor, railroads and the utility owners in the Utility
Coordination process.

JANUARY 2015 UPDATE

Page 26

The TIA Manual (Program Management Plan)

10.2.1 Blended Projects
The GDOT Utilities Office will manage the utility relocation process for blended projects. Utility coordination and work will follow
the PDP and comply with the policies and standards set forth in the UAM.

10.2.2 100% TIA Funded Projects
The TIAUE will serve in the role of GDOT’s District Utilities Engineer as outlined in the UAM.
For On-System projects, utility coordination and work will comply with the policies and standards set forth in UAM.
For Off-System projects let by the Local Government, utility coordination and work will comply with the Local Government’s policies
and procedures. For Off-System projects let by GDOT, the TIAUE will provide certification of utilities.

10.3 Identification of Utilities and Notification of Utility Companies
Utilities are identified through field surveys, topographic surveys, coordination with utility companies, and subsurface investigations
using SUE methods. The EOR incorporates utility location data into its base drawings. The TIAUE will submit a request to
Georgia 811 for a list of utilities specific to a given project once the consultant has been given NTP and conceptual plans are
underway.

10.3.1 Direct Communication with Utility Companies
The EOR will obtain a list of utility companies in the vicinity of a project prior to the beginning of design with the assistance of the
TIAUE. Once conceptual design is complete, the EOR will send base plans to each of the utility companies requesting markups
identifying existing utility locations and relocation designs, which are incorporated into the final construction drawings by the EOR.
The EOR will determine if there are any existing utility agreements in place, and identify and resolve any utility conflicts associated
with a project. It shall be the Consultant’s responsibility to submit plans to each utility owner using the Request for Project
Information form letters at the end of this section on their company letterhead. This will be done on a timely basis to ensure that
the utility owners have adequate time to respond to requests for information. The Consultant shall maintain a Utility Tracking
Report to document submission of plans to utility owners. This information shall be submitted to the TIAUE at each milestone
(existing facilities submission, proposed facilities submission, etc.).
The Consultant will copy the TIAUE on all correspondence with any railroad or utility company.
All construction documents shall include requirements to contact the Georgia Utilities Protection Center (UPC/811).

10.3.2 Need for SUE Services
For projects with 100% TIA funding, the PgM and the TIAUE will determine if SUE is needed for GDOT let projects.

10.3.3 Utility Permitting
For projects on or connecting to state routes, each utility owner on a TIA project will be required to submit a relocation permit in
GUPS, and the DUE for that district shall approve each permit prior to the certification of utilities. The TIAUE shall coordinate with
the DUE to ensure that the DUE has enough information to approve the permits and will notify the DUE when utility owners submit
their permits in GUPS. As per the UAM, a permit must be submitted by all of the utility owners even if there no relocations
required.

10.4 Certification of Utilities

For 100% TIA funded projects that are GDOT Let or On-System, the design procedures will follow the UAM and the TIAUE will
function as both the District and State Utilities Engineer. Therefore, the TIAUE will complete the the Utilities Certification at the end

JANUARY 2015 UPDATE

Page 27

The TIA Manual (Program Management Plan)

of this section, which certifies that all utility conflicts have been identified and resolved and that GDOT has no payment obligation
for utility related costs on the project.
For 100% TIA funded Off-System projects the sponsor or the sponsor’s duly authorized representative shall complete the Utilities
Certification.

10.5 Utility Relocation Work and Construction Schedules
Utility companies are required to attend the pre-construction conference and to coordinate the construction schedule. The
Contractor will work closely with the utility company throughout construction. During construction, the construction manager or
designated CEI staff shall monitor utility relocation progress, attend / hold coordination meetings, and confirm that utility
construction fulfills the MOU and contract requirements.

10.6 Utility Relocations/Coordination during Construction
The PgM and the EOR will coordinate with Utility and Railroad Owners before project certification to determine conflicts, necessary
relocations, utility adjustment schedules, and issuance of the Georgia Utility Permitting System (GUPS) permits. It is common for
utilities to be unexpectedly encountered during construction. If this occurs, the contractor will notify the CM and initiate
coordination to identify and coordinate relocation of the newly discovered utility.

10.7 Utility Reimbursement
Obligation of GDOT, counties, and municipalities regarding reimbursement to utility owners for utility relocation is outlined in the
UAM.
Reimbursements for utility relocations are determined and negotiated prior to construction letting. The negotiated amount of
reimbursement may require a Force Account Agreement between GDOT and the utility company.

10.8 Utility and Railroad Owner Meetings and Correspondence
The TIAUE will be responsible for assisting the Consultant in identifying utility owners, tracking plan submissions, scheduling and
inviting utility owners to the Field Plan Review meetings, holding other coordination meetings, as needed, and otherwise
communicating with Utility and Railroad Owners as necessary to timely accomplish any required Utility Relocations on GDOT let
projects.
At least ten (10) calendar days in advance of each scheduled project utility and railroad meeting, the PgM shall provide written
notice and an agenda for the meetings with the appropriate Utility and Railroad Owner. The PgM shall prepare and distribute
minutes via US mail and/or electronic mail of all meetings within seven (7) days after the date of the meeting with Utility and
Railroad Owners and shall keep copies of all correspondence between PgM and any Utility and Railroad Owner.

10.9 Record Keeping
The PgM shall ensure that utility construction and inspection records are maintained in order to ascertain that Utility Relocation
Work is accomplished in accordance with the terms and in the manner proposed on the approved Utility Work Plan and the
applicable Utility Agreement.
Documentation forms currently used by GDOT, counties and municipalities will be used for utility relocation whenever possible.
When new documentation forms, such as a variance, are required, approval will be required from the relevant governmental
agency and GDOT State Utilities Office. Utility owners will be notified in writing within ten (10) calendar days prior to any
documentation form changes and its respective implementation.

JANUARY 2015 UPDATE

Page 28

The TIA Manual (Program Management Plan)

Figure 2 - TIA Utility Letter 1 - 1st Submission Existing Utility Facilities (Page 1)

JANUARY 2015 UPDATE

Page 29

The TIA Manual (Program Management Plan)

Figure 3 - TIA Utility Letter 1 - 1st Submission Existing Utility Facilities (Page 2)

JANUARY 2015 UPDATE

Page 30

The TIA Manual (Program Management Plan)

Figure 4 - TIA Utility Letter 2 - 2nd Submission Existing and Proposed Utility Facilities (Page 1)

JANUARY 2015 UPDATE

Page 31

The TIA Manual (Program Management Plan)

Figure 5 - TIA Utility Letter 2 - 2nd Submission Existing and Proposed Utility Facilities (Page 2)

JANUARY 2015 UPDATE

Page 32

The TIA Manual (Program Management Plan)

Figure 6 - TIA Utility Letter 2 - 2nd Submission Existing and Proposed Utility Facilities (Page 3)

JANUARY 2015 UPDATE

Page 33

The TIA Manual (Program Management Plan)

Figure 7 - TIA UTILITY CERTIFICATION FORM
JANUARY 2015 UPDATE

Page 34

The TIA Manual (Program Management Plan)

11 Right-of-Way Management
11.1 General Acquisition Requirements
Titles 32 and 23 should be used for all Right-of-Way (ROW) acquisition regardless of who acquires the ROW for the TIA projects.
Reimbursements to Local Governments for property acquisitions and payments to property owners will be paid out of TIA funds
through reimbursement in accordance with the Local Agreement.
For all GDOT acquired parcels, all reviews and approvals noted in the GDOT Right-of-Way Manual to be completed by GDOT
ROW Office staff will be completed or coordinated by the PgM.
For parcels that are on-system or system adjacent, regardless of who acquires the ROW, all consultant acquisitions must be
performed by GDOT prequalified ROW consultants for each level of work being performed during the acquisition process.
Additionally, all appraisals and appraisal reviews must be conducted by an independent appraiser, pre-qualified by GDOT.

11.2 Responsibilities
For 100% TIA funded projects that are GDOT let or are Local let, On-system (or parcels that are system adjacent), GDOT’s ROW
Office has delegated the authority to the TIA Administrator to manage ROW. The TIA Administrator has contractually delegated the
management of those acquisitions to the PgM. The PgM is responsible for:
•

Ensuring that all acquisitions are in accordance with state laws and regulations

•

Reviewing and approving ROW plans for 100% TIA funded projects

•

Establishing a ROW budget and ensuring the project scope and cost is within budget

•

Approving any proposed financial transaction associated with the acquisition of ROW on a 100% TIA funded project

•

Certifying for each project all Right-of-Way has been acquired; or a plan for acquisition is in place that will not impact the
construction schedule

•

Validating that ROW acquisitions by Local Governments are eligible for reimbursement from the TIA Program

•

Verifying ROW stipulations between Local Governments and property owners are included in the construction contract

•

Coordinating the submittal of approved ROW plans to the Electronic Document Management Office

•

Preparing deeds and closing documents as needed

•

Ensuring GDOT project management software used to track the ROW acquisition process for all projects is current

•

If applicable, overseeing the ROW acquisition being performed by the Right of Way consultant on the behalf of GDOT

For 100% TIA funded projects that are Off-system and Local Let;
The Local Government is responsible for:
•

Ensuring that all acquisitions are in accordance with state laws and regulations (e.g. review of all appraisals by second
reviewer)

•

Reviewing and approving ROW plans

•

Ensuring the ROW cost is within budget

•

Certifying for each project all Right-of-Way has been acquired; or a plan for acquisition is in place that will not impact the
construction schedule

•

Verifying ROW stipulations between Local Governments and property owners are included in the construction contract

•

Preparing deeds and closing documents as needed

•

Providing ROW certification to PgM prior to construction let in accordance with Section 11.4 below.

The PgM is responsible for:
JANUARY 2015 UPDATE

Page 35

The TIA Manual (Program Management Plan)

•

Establishing a preliminary ROW budget

•

Approving reimbursement invoices associated with the acquisition of ROW on a 100% TIA funded project for compliance
with TIA legislation.

•

Validating that ROW acquisitions by Local Governments are eligible for reimbursement from the TIA Program

•

Auditing as necessary

11.3 GDOT ROW Acquisition Management
For GDOT let or Local let, On-system (or parcels that are system adjacent),the Engineer of Record will establish a preliminary cost
estimate for the project and ensure ROW acquisition costs are within the project budget. At a minimum the information contained
in the TIA Preliminary ROW Cost Estimate (see Figure 11-1) must be developed and used to verify that the projected costs are
within the project budget. This form is available as an MS Excel file here. A copy of the Preliminary ROW Cost Estimate must be
provided to the PgM. The TIA ROW Program Manager will review and validate the cost estimate at the concept report submission
and prior to ROW plan approval.
A GDOT approved appraiser will generate the property estimate for Market Value. The TIA review appraiser will approve Market
Value.

11.4 Local ROW Acquisition
Local ROW acquisition is eligible for reimbursement for both administrative and real property value up to amount budgeted.
The administrative costs associated with the acquisition of ROW and the real property costs are eligible for reimbursement by the
TIA Program. Local Governments must provide a ROW Cost Estimate to the PgM for approval, at a level of detail sufficient to
justify the project ROW costs, prior to issuance of a Notice to Proceed. Budgets for ROW cost will be agreed to by GDOT and the
Local Governments through a Local Agreement. If ROW costs are found to be in excess of the budgeted amount, coordination
between the Local Government and the PgM is necessary to determine the impacts to the project. ROW costs that exceed the
amount agreed upon in the Local Agreement, and deemed necessary to complete the project, may be the responsibility of the
Local Government.
The Local Government or its Engineer of Record will establish a preliminary cost estimate for the project and ensure ROW
acquisition costs are within the project budget. At a minimum the information contained in the TIA Preliminary ROW Cost
Estimate (see Figure 11-1) must be provided to the PgM and used to verify that the projected costs are within the project budget.
This form is available as an MS Excel file here.
Consultants who contract with the Local Governments to acquire ROW can establish the Market Value for the real property based
on the approved detailed cost estimate. TIA projects that cross county lines with ROW acquisition will require a Local Agreement
for acquisition services with each county acquiring the right-of-way.
The Local Governments must certify ROW with the Right of Way Certification form at the end of this section. This is a condition
precedent to reimbursement of ROW costs.

JANUARY 2015 UPDATE

Page 36

The TIA Manual (Program Management Plan)

Figure11- 1 - ROW Cost Estimate Form
JANUARY 2015 UPDATE

Page 37

The TIA Manual (Program Management Plan)

11.5 Abbreviated Valuation Methods
Abbreviated Valuation Methods may be used in compliance with procedures outlined in GDOT ROW Manual. Deviation from these
procedures is granted for the monetary threshold. The monetary threshold is limited to $50,000 and is only allowed for properties
that do not suffer any damages. This is an amendment to the values established in the ROW Manual. All other procedures must be
followed.

11.6 Advanced ROW Acquisition
Advanced ROW acquisition may be considered if the project meets one of the following as defined in the GDOT ROW Manual:
•

Protective Buying

•

Hardship

Advanced ROW acquisition can only be approved by the PgM and the TIA Administrator. Funding for advanced acquisitions,
requested by the local sponsor and determined eligible by the PgM and TIA Administrator, must be provided by the Local
Governments and will be reimbursed by the TIA Program after the advanced ROW acquisition parcels are certified and as funds
become available in the project’s ROW phase.

11.7 Condemnation
Condemnation of a property requires Notice of Location and Design (L&D) Approval before advertisement. Condemnation shall not
be used for advanced acquisitions on TIA projects. ROW plans that are approved at the time of the condemnation petition convey
exactly the impacts of ROW acquisition for the condemnation proceeding. Any design changes after the condemnation petition has
been filed will not be reflected in the condemnation proceedings and are to be avoided if at all possible. All ROW to be acquired at
the time of the condemnation filing will be acquired through that process; additional ROW needs for a condemned property will be
treated as a new acquisition and should be avoided. The condemnation petition will not reflect design changes that occur after the
condemnation filing which change the ROW footprint impacted.
For projects where the ROW is to be acquired in the name of GDOT, a Special Assistant Attorney General (SAAG) is required for
all condemnation proceedings. If it is determined that SAAG services are needed, the PgM will submit a request for assignment of
a SAAG to a project through the Office of Right of Way Funding and Certifications. This request must include Project Number, PI#,
and charging information for the SAAG billing.

JANUARY 2015 UPDATE

Page 38

The TIA Manual (Program Management Plan)

JANUARY 2015 UPDATE

Page 39

The TIA Manual (Program Management Plan)

12 Design Management
12.1 Roadway Design
Unless otherwise determined by the TIA Office during project development, roadway design as part of a blended project is required
to follow the GDOT PDP manual and all policies, procedures and manuals required by GDOT.
Roadway design as part of a 100% TIA funded project is required to follow the TIA Manual.

12.1.1 On-System and Off-System Roadways
For the TIA Program, roadway designs are classified as either On-System or Off-System as defined by Section 1.6 of the TIA
Manual.

12.1.2 Roadway Design Specifications
For 100% TIA funded projects that are On-System, roadway projects shall be designed in accordance with the policies, guidelines,
and standards published and referenced in the GDOT Design Policy Manual, the design criteria published in the AASHTO-A Policy
on Geometric Design of Highways and Streets and AASHTO-A Policy on Design Standards Interstate System, the guidelines and
standards published by the FHWA Manual on Uniform Traffic Control Devices, and the PPM 10-Design Management, as may be
amended from time to time.
In the event of conflicting information or guidance, the DPM supersedes AASHTO guidelines.
Design traffic volumes may not be necessary for 100% TIA funded projects and for which the project description included a specific
number of lanes for the widening. Design year volume is important and may be necessary on various project types and may be
needed for other design elements.
Current GDOT Standard Specifications for the Construction of Transportation Systems (as supplemented by the Supplemental
Specification Book, Special Provisions, Supplemental Specifications, GDOT Standards, and Construction Details) will be used in
the design and construction of On-System projects.
For 100% TIA funded projects that are Off-System, the Local Government will determine the roadway design criteria. The
following are suggested minimum standards for roadway design:
•

For ADT > 400, AASHTO: A Policy on Geometric Design of Highways and Streets

•

For ADT ≤ 400, AASHTO: Guidelines for Geometric Design of Very Low-Volume Local Roads

JANUARY 2015 UPDATE

Page 40

The TIA Manual (Program Management Plan)

Figure 12-1 TIA Roadway Design Guidance

12.1.3 Responsibilities
The roles and responsibilities of the EOR and Local Government related to roadway design of TIA projects are outlined in the
following sections.

12.1.3.1 Engineer-of-Record
The EOR is responsible for all aspects of design, plan development and specifications related to a roadway design. Designs and
plans for On-System roadways shall follow the DPM. Every design must be certified by a licensed engineer registered in Georgia.
Engineering firms providing design work for On-System roadways are to be prequalified with GDOT area classes necessary for the
project.
The EOR is responsible for ensuring that roadway designs are complete, accurate and constructible. Construction plans should be
of sufficient quality to ensure that the contractor can easily understand the design and how the roadway is to be constructed. If
errors occur during construction due to errors on the roadway plans, the EOR is responsible to provide a remedy at no additional
cost to the project. The EOR may be held responsible for covering the additional contractor costs, liquidated damages or legal
claims as a result of errors and/or omissions in the plans.

12.1.3.2 Local Government
For Off-System roadways, the Local Government shall submit plans and specifications to the PgM for review before letting the
project.

12.1.4 Survey and Mapping
The electronic database shall be completed in accordance with the GDOT Survey Manual, unless deviations are approved by the
PgM or the TIA Administrator.
For all GDOT let and On-System projects, QC Check for database and cad files will be reviewed and approved by GDOT.

JANUARY 2015 UPDATE

Page 41

The TIA Manual (Program Management Plan)

12.1.5 Soil Survey
For all major, GDOT let and On-System projects, soil survey(s) will be completed for all TIA funded projects unless the EOR
provides acceptable justification which is accepted by the PgM for not performing the soil survey. The soil survey(s) will follow the
requirements and guidance set forth in GDOT’s PDP, GDOT’s Guidelines for the Geotechnical Engineering Manual, and by
GDOT’s Office of State Materials Engineer.
The soil survey(s) should be coordinated and developed as soon as possible to provide safe, effective and cost-efficient
recommendations for the project design. The PgM will have the authority to accept all soil surveys for Off- System projects.
GDOT’s Office of State Materials will be responsible for providing acceptance for all On-System projects.

12.1.6 Pavement Evaluation and Design
The need for a Pavement Evaluation will be determined by the TIA Office for all GDOT Let projects.
For 100% TIA funded projects that are On-System, pavement design and evaluation submittals shall be developed in accordance
with GDOT’s PDP and GDOT Pavement Design Manual and reviewed and approved by the PgM.
For 100% TIA funded projects that are Off-System and Local Let, pavement evaluation and design shall follow local guidelines and
recommend practices established by the Local Government. GDOT can provide pavement design recommendations and review if
requested by the Local Government and agreed to by GDOT.
For 100% TIA funded projects that are Off-System and GDOT let, pavement design will be approved by the TIA Office.
For On System, the recommended pavement design life is 20 years. If a 20 year design is not achievable, the EOR should
reduce/remove section thickness and/or layers from the top of the pavement structure in lieu of the base or sub-grade.

12.2 Municipal Separate Storm Sewer System (MS4)
All TIA funded projects must comply with the MS4 permit for those areas outlined in the MS4. Provisions in the MS4 permit allow
GDOT to present evidence to the Environmental Protection Division (EPD) regarding why certain control measures are not feasible
or reasons why a project should be exempt from their Storm Water Management Program (SWMP). Extra attention should be
undertaken by the PgM and EOR for each control measure, especially post-construction Best Management Practices (BMP) for the
SWMP, to determine its feasibility for implementation on the project.

12.3 Highway Signing and Pavement Markings
For all TIA projects, highway signing and pavement markings will be installed in accordance with the MUTCD. For On-System TIA
projects, highway signing and pavement markings will also conform to the GDOT Signing and Marking Design Guidelines.
Modification of posted speed limits will be performed in accordance with State Code and local ordinances.

12.4 Traffic Operations
TIA projects that are On-System or GDOT let, regardless of funding, will follow the GDOT processes for the installation of all traffic
control devices.

12.4.1 Roundabouts, Alternative Interchanges and Intersection Design
For 100% TIA funded projects, roundabouts are viable intersection alternatives.

JANUARY 2015 UPDATE

Page 42

The TIA Manual (Program Management Plan)

For 100% TIA funded projects that are On-System, requests for roundabout studies should be submitted to the PgM and TIA
Administrator for review and approval prior to beginning the study. Peer review of roundabouts is required unless the PgM and/or
the Chief Engineer determines otherwise. See Chapter 8 of the GDOT Design Policy Manual (DPM) and State website for Modern
Roundabouts.
For 100% TIA funded projects that are Off-System, the use of conventional intersection solutions that meet both the safety
improvement goals and budget limitations should be considered when roundabout alternatives exceed the project budget.
All on-system projects will be reviewed by GDOT Traffic Operations.

12.4.2 Traffic Control Signals
Traffic control signal permits, including signal modification permits, approved by the GDOT Chief Engineer will be required for all
new traffic control signals installed for On-System TIA projects only. Off-System TIA projects with new traffic control signals will
follow MUTCD’s requirements and will be approved by the local agencies in accordance with the MUTCD.

12.4.3 Intelligent Transportation Systems (ITS)
Blended projects, and locally funded projects on the state highway system, will follow the GDOT PDP process for the installation of
all ITS improvements. The installation of ITS improvements on TIA projects, which include local funding on Off-System highways,
will follow the TIA Manual. The option of implementing minor ITS projects without construction plans will be reviewed and approved
by the PgM on a case-by-case basis.
Bridges and Structures
Bridge designs that are part of a blended project are required to follow the GDOT PDP manual and all policies, procedures and
manuals required by GDOT.
Bridge designs that are part of a 100% TIA funded project are required to follow the TIA Manual. It is preferred that bridge design
development include a preliminary bridge plan phase (including Hydraulic and Hydrological Studies (H&H) as required) and a final
bridge plan phase.

12.4.4 On-System and Off-System Bridges
For the TIA Program, bridge designs are classified as either On-System or Off-System as defined by Section 1.6 of the TIA
Manual.
On-System bridges are to be maintained and inspected by GDOT following the completion of construction.
If a project involves a bridge that carries the interstate or a bridge crossing the interstate, FHWA coordination is required and may
involve submitting plans to FHWA for review.
Off-System bridges will be maintained by the Local Government owner of the bridge. The PgM will develop an Intergovernmental
Agreement between GDOT and the Local Government to define the maintenance responsibilities for Off-System bridges.

12.4.5 Bridge Design Specifications
Bridges are to be designed using the most recent editions of the Georgia DOT Standard Specification - Construction of
Transportation Systems, 2001 Edition, GDOT Bridge and Structures Design Manual (DPM), GDOT LRFD Bridge and Structure
Design Manual, and AASHTO Bridge Design Specifications. It is preferred that new bridges be designed using the latest AASHTO
LRFD Bridge Design Specifications but this will not be required in all cases.
JANUARY 2015 UPDATE

Page 43

The TIA Manual (Program Management Plan)

Blended projects must conform to FHWA requirements.
For 100% TIA funded projects, the following are the AASHTO Bridge Design Specifications to be used for bridge design:
•

Bridge Widening Projects: Latest version of AASHTO Bridge Specifications or the version of the specifications in place at
the time the bridge was originally designed with prior approval from GDOT Office of Bridges and Structures.

•

NEW Off-System Bridges: AASHTO Standard Specifications for Highway Bridges, 2002, 17th Edition (HS20 Loading) as a
minimum.

•

NEW On-System Bridges: AASHTO Standard Specifications for Highway Bridges, 2002, 17th Edition (HS20 Loading) as a
minimum. However, the latest AASHTO LRFD Bridge Design Specifications are acceptable.

•

NEW On-System Bridges (Interstate): Latest version of AASHTO LRFD Bridge Design Specifications (HL93 Loading) to
accommodate full FHWA oversight.

In the event of conflicting information or guidance, the Bridge DPM or Bridge LRFD DPM supersedes AASHTO guidelines.

12.4.6 Responsibilities
The roles and responsibilities of GDOT, PgM, EOR and Local Government related to bridge design of TIA projects are outlined in
the following sections.

Figure 12-2 TIA Bridge Project Design Guidance

12.4.6.1 GDOT Office of Bridge Design
For On-System bridges and bridges that are part of blended projects, the GDOT Office of Bridge Design will provide the necessary
submittal reviews, guidance and design acceptance. Blended projects will follow the PDP.
For all other bridges, the Office of Bridge Design will perform audits on projects for compliance with the TIA Manual.
For additional responsibilities related to Shop Drawings and Request for Information (RFI), see Section 12.6.10.

JANUARY 2015 UPDATE

Page 44

The TIA Manual (Program Management Plan)

12.4.6.2 Program Manager
For Off-System projects, the PgM may perform review of bridge submittals. The design and plan reviews will be “peer” review in
nature and will be conducted at the completion of the preliminary plan and final plan phases. The peer review will consist of the
design drawings for completeness and compliance with the TIA Manual, cost estimates, and constructability. It is expected that
bridge plans and designs will be prepared in a format typical to GDOT bridge plans in quality and presentation. Bridge review is not
a substitute for the EOR’s own quality control procedures. This review does not relieve the EOR of its overall responsibility for the
design.

12.4.6.3 Engineer-of-Record
The EOR is responsible for all aspects of design, plan development and specifications related to a bridge or structure design.
Bridge and structure designs and plans for On-System bridges shall follow the Bridge DPM or Bridge LRFD DPM. Every bridge
design must be certified by a licensed engineer registered in Georgia specializing in bridge design.
Engineering firms providing bridge and structure design work bridges are to be prequalified with GDOT in Area Classes 4.01, 4.02,
and/or 4.04 as necessary for the project.
The EOR is responsible for ensuring that bridge designs are complete, accurate and constructible. Construction plans should be of
sufficient quality to ensure that the contractor can easily understand the design and how the bridge is to be constructed. If errors
occur during construction due to errors on the bridge plans, the EOR is responsible to provide a remedy at no additional cost to the
project. The EOR may be held responsible for covering the additional contractor costs, liquidated damages or legal claims as a
result of errors and/or omissions in the plans.
For additional responsibilities related to Shop Drawings and Request for Information (RFI), see Section 12.6.10.

12.4.6.4 Local Government
For Off-System bridges, the Local Government and the Local Government’s EOR shall certify that:
•

The bridge configuration meets the drainage design and stream crossing requirements of the local jurisdiction and FEMA,
and creates no adverse effects to flood elevations or flood plain limits in the surrounding area.

•

The bridge is designed to resist the hydraulic forces determined by the applicable design guidelines and imposed on the
structure by the waterway.

•

The foundations are designed to be installed below the anticipated scour depths, into competent bearing material, and in
accordance with the bridge foundation investigation.

•

The scour protection is designed to resist anticipated velocities at the crossing.

The Local Bridge Design Certification shall be submitted to the PgM before Final Acceptance of the project.

12.4.7 Bridge Details
The following sections outline guidelines for design and detailing of bridges that will improve safety and lower long term
maintenance costs for the owner.

12.4.7.1 Superstructure
Whenever possible, minimize the number of deck joints in bridge spans. Locate deck joints to provide access for future
maintenance and replacement.
JANUARY 2015 UPDATE

Page 45

The TIA Manual (Program Management Plan)

The use of fracture critical members (FCMs) is not permitted on highway bridges without written authorization from GDOT Office of
Bridge Design. Design and detail FCMs to allow full access for inspection. Provide a minimum inside depth of six (6) feet to
facilitate interior inspection of box girders. To allow free flow of air during inspections, include access openings of 3’-0” diameter
minimum into all cells, and between cells of the girders. Provide outside access opening covers in areas that can be accessed
without impacting traffic. Provide hinged access opening covers with hinges located on the inside of the box girder.
Timber bridges, masonry bridges and structural plate arches are not permitted for TIA projects. Intermediate hinges in bridge
girders or spans are not permitted for TIA projects.
Design bridge superstructures, joints and bearings to allow access for long-term inspection and maintenance.

12.4.7.2 Bridge Foundations
Design foundations for bridges over waterways to accommodate predicted scour depths. The EOR will determine the scour
potential of each bridge crossing using the Bridge Foundation Investigation and H&H Study.

12.4.7.3 Bridge Railing and Barriers
All barrier systems shall meet current crash test and other safety requirements as determined by GDOT. Table 14-6 lists current
approved GDOT Bridge Railing Standards, which GDOT will update upon request.
BRIDGE BARRIER, PARAPET AND RAIL
Description

Std Name

Rev Date

Std Name

Rev Date

3626

10-64

Chain Link Wire Fence for mounting on top of parapets

9031N

06-81

Pipe Handrail for mounting on top of parapets & modified barriers

9031R

10-88

Std Name

Rev Date

With Sidewalks
Concrete Parapet (42” tall – 13” wide)
Concrete Parapet (27” tall- 13” wide) w/Std 3626 (42” tall total)
Concrete Parapet (34” tall – 13” wide ) w/Std 9031N Chain Link Wire Fence for
urban area bridge over an Interstate or other limited access highway or a
railroad”
No Sidewalks
Concrete Jersey Barrier (32” tall) w/ 9” top (No Bicycle route)
Concrete Type “S” Barrier ( 42” tall)
COMBINATION RAILS/FENCES
Description

One-Pipe Aluminum Handrail for mounting on parapets (14.75” high rail)

ARCHITECTURAL RAILS
Description
Texas Rail (to be used only with GDOT Bridge Office approval)
Kansas Corral (to be used only with GDOT Bridge Office approval)
Table 14-6: GDOT Standard Bridge Railing
JANUARY 2015 UPDATE

Page 46

The TIA Manual (Program Management Plan)

12.4.8

Concept and Preliminary Plans

12.4.8.1 Concept
If required for approval of the Concept Report, provide concept layouts consisting of bridge plan view, elevation view and typical
section. Include a cost estimate, based on the concept layout, in the Concept Report.

12.4.8.2 Preliminary Plans
Preliminary Design Packages are required for all projects let to construction by GDOT.
Unless required by the Local Government, Local Let projects do not require submittal of Preliminary Design Packages. Submittal
of the bridge layout for review at an early phase of the project is recommended to minimize cost and schedule impacts.
Preliminary bridge layouts must show all required crossing information as outlined in the Bridge Design Policy Manual and the
GDOT Bridge Detailing Manual.

12.4.8.3 Hydraulic and Hydrological Studies
Bridge projects crossing or encroaching on FEMA studied waterways must be studied and designed to meet all FEMA
requirements.
For On-System bridges, GDOT requires an H&H Study and Preliminary Bridge Layout to be submitted and accepted prior to
advancing to the next phase, regardless of funding source. H&H Study Reports for these projects must follow the guidelines and
policies in the GDOT Drainage Manual and include the Preliminary Bridge Layout in the study appendices. The GDOT Drainage
Manual outlines the content and format of H&H Study Reports.
For Off-System bridges, an H&H Study Report shall be completed to determine bridge configuration, hydraulic opening, scour
depths and changes to existing flood elevations and floodplain limits. These bridges must (1) be designed to meet the drainage
design requirements of the local jurisdiction; (2) be designed to resist hydraulic forces imposed on the structure by the waterway;
(3) have foundations installed below the anticipated scour depths into competent bearing material; and (4) include scour protection
designed to accommodate anticipated stream velocities.
For Off-System bridges, the Local Government and the Local Government’s EOR or representative, shall provide a Local Bridge
Design Certification as per the TIA Manual.

12.4.8.4 Preliminary Cost Estimates
A concept level and preliminary cost estimate shall be prepared for the bridges using the latest cost data available from GDOT
including square foot cost provided in the Bridge DPM and the most recent GDOT Mean Item Summary Data. It is important that
the estimate developed at this stage of the project is as accurate as possible.

12.4.9

Final Plans

Final design of bridges will follow the requirements of the GDOT Bridge DPM and the applicable AASHTO Bridge Design
Specifications. For bridges designed using the AASHTO Standard Specifications, the EOR is encouraged to use the GDOT Bridge
design programs, which are available from GDOT at no cost. For Bridges that must be designed using the AASHTO LRFD Bridge
Design Specifications, it is necessary for the EOR to use software that is capable of designing the bridge using the LRFD
Specifications. Design calculations will be required for all portions of the bridge. Calculations should be checked for accuracy in
accordance with the EOR’s internal quality assurance policy.
Bridge plans and details shall follow the requirements of the latest GDOT Bridge Detailing Guide where applicable. Final plans will
be of sufficient detail and quality to let the project for construction.

JANUARY 2015 UPDATE

Page 47

The TIA Manual (Program Management Plan)

12.4.9.1 Final Cost Estimates
A final construction cost estimate for each bridge will be required prior to letting the project. The estimate should be developed
using estimated final quantities of materials and the most recent GDOT Item Mean Summary Data.

12.4.9.2 Foundation Investigations
A Bridge Foundation Investigation (BFI) will be required for all bridge projects regardless of the funding source. In cases where
they are available for use on bridge replacement projects, existing BFIs may be used in lieu of a new BFI Report. Prior to
undertaking a TIA project, an initial search shall be undertaken with GDOT’s Office of Materials and Testing to determine if
approved BFI Report(s) are available for use. The BFI will make all necessary recommendations for the project and will follow the
format required by GDOT’s Office of Materials and Testing. For On-System bridges, the BFI shall be submitted to GDOT for
review and approval.
Requirements and procedures for Wall Foundation Investigations (WFI) reports shall closely follow those specified for BFIs above.

12.4.10

Retaining Walls

Retaining walls will be designed according to the guidelines in the GDOT Bridge DPM. Wherever possible, the use of GDOT
standard walls and contractor designed walls is encouraged. A WFI will be required for walls as recommended by the GDOT
Bridge DPM.
For On-System and blended projects, wall layouts will be submitted with the preliminary design package for acceptance. For OffSystem projects, it is recommended that wall layouts be submitted with the preliminary design package for acceptance.

12.4.11

Bridge Condition Surveys

For On-system bridges to be widened and/or rehabilitated, the Office of Bridge Design - Bridge Maintenance Section shall
complete Bridge Condition Surveys in accordance with the PDP. The PgM will obtain Bridge Condition Surveys for these projects
from Office of Bridge Design - Bridge Maintenance Section. As determined eligible by the TIA Administrator, recommendations
from Bridge Condition Survey reports shall be incorporated into the final design of the bridge.

12.4.12

Bottomless Culverts

Bottomless or three-sided culverts may be used on projects. These culverts consist of precast concrete sections that are founded
on spread footings or pile supported foundations. Foundations for these structures must be designed and protected from
anticipated scour depths. Requirements for design capacity, H&H studies and foundations shall follow applicable sections of the
TIA Manual.

12.4.13

Construction Phase

During construction, the EOR will provide shop drawing review and technical support consisting of addressing contractor RFI’s,
attending project status meetings and site visits as needed to resolve problems or issues in the field.

12.4.13.1 Shop Drawings
During construction, the EOR will provide shop drawing review. The Design Consultant or its designated EOR will review the shop
drawings for bridges and structures designed by the EOR. For On-System bridges, GDOT will process and return shop drawings
to the contractor following acceptance by the EOR. The PgM will coordinate processing of the shop drawings, RFIs and
construction correspondence. All submittal related correspondence will be submitted to the PgM for distribution to appropriate
review personnel. The PgM is to ensure that contractor submittals and RFI's are addressed and processed in a timely manner.
Review of Shop drawings will be performed and approved by the EOR. The PgM will keep a record of all shop drawing submittals
and approvals over the course of the project. This record will be turned over to the Local Government and/or GDOT at the

JANUARY 2015 UPDATE

Page 48

The TIA Manual (Program Management Plan)

conclusion of the project. The EOR will review shop drawings to ensure that fabrications are consistent with the designer’s intent.
A partial list will include, but not be limited to:
•

Structural steel framing

•

Precast, prestressed concrete beams

•

Precast segmental concrete units

•

Bearings

•

Expansion joints

•

SIP deck forms

•

Sound Barriers

•

Sign structures

•

Signal poles

•

Bridge appurtenances

•

High mast lighting

Shop drawing review may be required for major items of temporary works that might affect the public, impose significant loadings
on the permanent works, and/or require an engineered design. A partial list includes, but is not limited to:
•

Temporary structures

•

Cofferdams

•

False work, shoring and formwork

•

Superstructure erection

•

Construction staging and traffic control

•

Demolition plans

12.4.13.2 Requests for Information
Requests for Information (RFI) will be coordinated between the PgM, Local Government (if required) and the EOR. The PgM will
keep a record of all RFI submittals and outcomes over the course of the project. This record will be turned over to the Local
Government and/or GDOT at the conclusion of the project.

12.4.13.3 As-Built Plans
As-Built Plans will be prepared for all structures on the project. This will include the as-built foundation drawings as well as the
construction documents used for the structure, noting all field change corrections made to the drawings. The PgM will store Asbuilt drawings produced from construction and transfer the final drawings to the appropriate project sponsor upon project closeout.

12.4.14 Load Rating
The EOR will complete a load rating and develop a Load Rating Report for each bridge design which includes a statement
certifying that the bridge has the capacity to carry the minimum design loading specified in the TIA Manual and does not require
posting for current state legal loads. The Statement of Load Rating Certification will include the professional seal and signature of a
registered professional engineer in the state of Georgia.
Load rating procedures outline in AASHTO’s The Manual for Bridge Evaluation, current edition, shall be followed. Bridges
designed using the AASHTO Standard Specifications may be rated using either LFR or LRFR methodologies. Bridges designed
using the AASHTO LRFD Specifications must be rated using LRFR methodologies.
Load Rating Reports will be submitted to the PgM upon certification of final bridge plans. The PgM will submit the reports to the
Office of Bridge Design for verification of load capacity and acceptance prior to project letting. If changes occur between submittal
of final plans and construction of the bridge that affect the load capacity of the bridge, it is the responsibility of the EOR to submit
JANUARY 2015 UPDATE

Page 49

The TIA Manual (Program Management Plan)

revised Load Rating Reports to the PgM and GDOT for rerating. A certified copy of the Load Rating Report and Final Bridge Plans
will be submitted to Office of Bridge Maintenance for inclusion in the maintenance records for each bridge.
If an independent load rating, performed by GDOT, demonstrates that the capacity of the bridge design is less than 95% (<95%) of
the design load, the EOR will be responsible for any additional design and construction costs associated with correcting the
deficiency in a manner that increases the capacity to a level that meets the design load requirements.

12.4.15 Final Acceptance
For On-System bridge projects, all project deliverables will be in accordance with GDOT PDP and Bridge DPM.
For Off-System bridge projects, the following will be required to be submitted to GDOT for Final Acceptance:
•

Design and As-built Plans

•

Load Rating Report

•

H&H Studies Reports including scour calculations

•

As-built Foundation Plans

•

BFI used for design

•

Shop Drawings

JANUARY 2015 UPDATE

Page 50

The TIA Manual (Program Management Plan)

JANUARY 2015 UPDATE

Page 51

The TIA Manual (Program Management Plan)

JANUARY 2015 UPDATE

Page 52

The TIA Manual (Program Management Plan)

12.5 Design Exceptions/Variances
For GDOT let and On-System projects , all Design Exceptions (DE) and Design Variances (DV) to be submitted and reviewed by
GDOT’s Office of Design Policy & Support (DP&S) regardless of funding source. It is highly encouraged that any DE/DV be
discovered and introduced at the concept stage or as early as possible. The Concept Report should identify these variations and
should include them in the report for review and approval. If a DE and/or DV are to be obtained, then the format and procedures
outlined in the GDOT PDP and in the GDOT DPM are to be followed.
GDOT’s Chief Engineer will approve all applicable DE and DV. These DE and DV reports will be submitted to the:
•

PgM for review and concurrence with copies sent to the RC and TIA Office

•

Chief Engineer for approval following the process outlined in the DPM with copies sent to the PgM, TRC, and TIA Office

12.6 Field Plan Review
The EOR is responsible for completing the Final plans and addressing all comments from the Field Plan Review. The Final Plans
are to be submitted to the PgM for review to ensure all comments have been addressed adequately and the plans are ready for
letting.
The PgM is responsible for facilitating plan reviews, preparing FPR reports, reviewing FPR responses, and distributing final FPR
reports. FPR comments and actions shall consider impacts to scope, schedule and budget prior to implementation on a project.
The Environmental commitments shall be known prior to the FPR. In addition, the soils report, if required, shall be complete prior to
the FPR.
Except with the approval of the PgM, a minimum of one FPR, conducted at the 80% to 85% plan completion level, is required for
100% TIA funded projects that are GDOT let or are On-System. At the request of the EOR and with approval from the PgM,
additional FPRs may be held for complex projects and projects that have a large number of right-of-way or utility impacts.
It is recommended that local delivered, off-system major projects conduct at least one FPR. The TIA office and appropriate GDOT
staff shall be invited to the FPR.
Minor projects are exempt from this requirement.

12.7 Airport Projects
The work and materials for airport projects shall be in strict and entire conformity with:
•

Laws of the State of Georgia,

•

GDOT’s Standard Specifications, 2001 Edition, and the Supplemental Specifications,

•

Federal Aviation Administration’s Standards for Specifying Construction of Airports, dated February 17, 1989,

•

GDOT’s Special Provision 107-1-01-SP (Legal Regulations and Responsibility to the Public),

•

GDOT’s Special Provision 108-1-01-SP (Prosecution and Progress),

•

GDOT’s Special Provision 109-1-01-SP (Measurement and Payment), and

•

“TERMS AND CONDITIONS OF ACCEPTING AIRPORT IMPROVEMENT PROGRAM GRANTS,” dated April 13, 2012.

JANUARY 2015 UPDATE

Page 53

The TIA Manual (Program Management Plan)

Copies of any of these compliance documents are available from GDOT’s Aviation Programs office or the Atlanta Airports District
Office of the Federal Aviation Administration.

12.8 ADA Compliance
The TIA Program requires all compliance with ADA Regulations as set forth in the current GDOT Design Policy Manual.

12.9 Lighting
The Program Manager will prepare lighting agreements for execution with local governments. In addition, the Program Manager
will perform all reviews, approvals, and coordination with the Office of Design Policy and Support in relation to retention of records.
Design must be in compliance with the GDOT Design Policy Manual, Chapter 14, Lighting.

JANUARY 2015 UPDATE

Page 54

The TIA Manual (Program Management Plan)

13 Construction Administration
13.1 Preconstruction Conference
For GDOT let projects, the PgM is responsible for coordinating a Preconstruction Conference with the Contractor, CEI provider,
District / Area Office, utilities, etc. after project award, but prior to beginning of construction activities. The format of the PreConstruction Conference will follow GDOT standards as outlined on The Source.
For local let projects, the PgM should be invited to all preconstruction conferences. The PgM reserves the right to attend or
decline.

13.2 Construction Engineering and Inspection
For blended projects, CEI shall be performed in accordance with all GDOT manuals, specifications, plans, and testing
requirements. GDOT Manuals include but are not limited to the GDOT Construction Manual, GDOT Bridge Manual, and GDOT
Sampling, Testing and Inspection Manual.
For GDOT let 100% TIA projects, the scope of work for inspection will be determined by the PgM and submitted to the TIA
Administrator for concurrence.
For locally let projects, the scope of work for inspection will be the responsibility of the Local Government, unless determined
otherwise by the PgM.

13.3 Construction Audits
For blended projects the standard GDOT procedures will apply.
For 100% TIA projects, the PgM is responsible for conducting audits on both On-System and Off-System projects. GDOT may
conduct random audits for validation.

13.4 Site Manager
On GDOT let projects, Site Manager will be the software used for all daily reporting, submittals, submittal tracking, materials
certifications, testing reporting, and payment estimates.

13.5 Materials
All construction materials shall comply with current Qualified Product List requirements, GDOT Standard Specifications for the
Construction of Transportation Systems, as supplemented by the Supplemental Specification Book, Special Provisions,
Supplemental Specifications, Standards, and Details. Products and suppliers are defined on the Qualified Products list and they
have a defined inspection frequency.
For GDOT Let Projects, GDOT’s Office of Materials and Testing will provide all required testing in accordance with all applicable
GDOT Manuals, which include but are not limited to: the GDOT Construction Manual, GDOT Bridge Manual, and GDOT Sampling,
Testing and Inspection Manual.

JANUARY 2015 UPDATE

Page 55

The TIA Manual (Program Management Plan)

The CM or designated CEI provider will complete all required material certification documentation to ensure all sampling and
testing is completed as required for the project. For GDOT let, On-System projects Material Certifications are to be submitted and
tracked through Site Manager. Material Certification ensures all materials used in the Work are acceptable.
For material quality assurance on Local Let, Off-System Projects a Material Certification Statement must be provided in support of
the reimbursement of costs. See sample form included at the end of this chapter.
For material quality assurance on Local Let, On-System Projects see section 13.5.1 of the TIA Manual

13.5.1 Local Let Responsibilities for Material Quality Assurance of On-System Projects
For Local Let, On-System, the Local Government shall provide a consultant prequalified in Area Classes 6.04a and 6.04b to
perform the Materials Testing. Local Governments shall adhere to the following process:
•

Submit a Local Let Material Quality Assurance form to the PgM to obtain approval of materials testers (see form below)

•

Ensure QPL sources are utilized and that only testing personnel with GDOT certifications perform testing on the project,
All testing must be in accordance with GDOT’s Sampling Testing and Inspection Manual

•

Complete a quarterly Materials Certificate (MC) Checklist and submit to the PgM as required in GDOT Construction
Manual. Contact PgM to obtain a Checklist prior to starting work on the project

•

Provide test results to the GDOT OMT and via hardcopy to the TIA CM or CEI designee.

•

Complete required MC Checklists and submit to the PgM as required in GDOT Construction Manual, unless otherwise
determined by the PgM.

•

13.6 Project Closeout
13.6.1 Final Inspection
For blended projects, all GDOT let projects and Local Let, On-System projects, final inspection follows the requirements as
outlined in The Source and Standard Specifications as may be modified from time to time by TIA specific policies. The PgM will
perform a Final Audit on these projects.
For Local Let, Off-System projects, final acceptance of work is the responsibility of the local sponsor. The local government will
provide a final acceptance letter to GDOT for the project. The PgM will perform a Final Audit on these projects.

13.6.2 Final Audit
For GDOT Let or On-system projects, the CM or designated CEI provider is responsible for completing the TIA Construction
Manager’s Closeout Checklist (Prior to Requesting Final Audit) form (Sample provided at the end of this section). If any of the
checklist items have discrepancies, they must be resolved or be in the process of being resolved before requesting a Final Audit.
The CM or designated CEI provider will compile a list of all discrepancies and completion status. This list should be attached to the
front of the Final Package and checked off by the CM as each item on the list is resolved. Once all the items have been resolved,
the PgM or designee will complete the Final Audit. The Final Audit can be completed without the Materials Certificate being
received, but the lack of the Materials Certificate shall be noted on the Final Audit. The project cannot be closed out until the
Materials Certificate is received.

13.6.3 Final Payment
For GDOT let projects, the designated CEI provider will submit the Final Package to the PgM prior to completion of the Punch List
by the Contractor.
JANUARY 2015 UPDATE

Page 56

The TIA Manual (Program Management Plan)

The CM will notify the PgM and GDOT that the project is ready for Final Audit. This request comes only after the CM has
thoroughly reviewed the project records using the Project Checklist for Requesting a Final Audit as a guideline. Immediately on
completion of the Final Acceptance, the CM or designated CEI provider will transmit final quantities to the Contractor.
This process will follow the TIA Contract Close out Standard.

13.6.4 As-Built Plans
For GDOT let projects, the CM or designated CEI provider will coordinate with the project designer (EOR) throughout construction
to determine if field changes can be completed as a redline change or if revisions to the plans by the EOR are needed. The CM will
coordinate and distribute plan revisions as required and ensure the Contractor has the most current set of plans. Redlined Final
As-Built plans should be compiled by the CM or designated CEI provider as directed and submitted to the PgM for review and
processing.
For Local Let, On-System projects, the local sponsor shall provide As-Built plans to the Department prior to Final Acceptance.
For Local Let, non-bridge Off-system projects, local sponsors are responsible for obtaining As-Built plans. For bridge projects see
requirements set out in Chapter 12.

13.6.5 Final Acceptance
For GDOT Let projects, the TIA Office will follow GDOT procedures.
For local let, off system projects, the Local Government shall provide written notification to the TIA Office of certification of work
and final acceptance.

JANUARY 2015 UPDATE

Page 57

The TIA Manual (Program Management Plan)

TIA Program - Local Let Project - Materials Quality Assurance
SELECT ONE:

 Request GDOT to perform Materials Testing (Complete Section 1)
 Request Approval for Consultant Quality Assurance Materials Testing (Complete Sections 1 and 2)
Section 1
Project Number/County: ________________________________________________________________________
GDOT Contract ID Number/Proposed Let Date: ______________________________________________________
Project Description: ____________________________________________________________________________
____________________________________________________________________________________________
Local Govt. Responsible for Letting Project: ____________________________________________________________________
Local Govt. Project Manager Contact Name & Number: ___________________________________________________________

Section 2

GDOT Certified Technicians to be responsible for testing on the project:
1) Roadway Testing Technicians (RTT) are required to perform field density testing on embankment, pipe backfill, subgrade and all
asphalt layers, along with sampling misc. materials
List GDOT Certified Roadway Testing technician(s) who will be performing testing:
GDOT RTT Certification Number

Name/ Employer

2) Concrete **– GDOT Certified Concrete technician(s) are required to perform all field concrete testing (slump, air, cylinders)
List who will be performing concrete testing & GDOT certification number:
GDOT Concrete Certification Number

Name/ Employer

Attach additional sheets as necessary.
**Please note if a Bridge or other major structure is involved:
NOTE: Labs performing any testing shall be accredited in the testing to be performed (i.e. AASHTO T-22 or ASTM C-39 for concrete cylinders)
by the AASHTO Accreditation Program (AMRL and/or CCRL).
3) Hot Mix Asphalt
GDOT specifications require the Contractor to perform mixture Acceptance testing at the plant. GDOT will perform Verification Testing at
the asphalt plant as a part of the existing QPL process. The Local Government is responsible for notifying GDOT’s Testing Management
Operations Supervisor (TMOS) at least one week prior to start of work.
*send completed form to TIA Office.
APPROVED: _____________________________________________________________________________________
TIA Program Manager
Date
JANUARY 2015 UPDATE

Page 58

The TIA Manual (Program Management Plan)

JANUARY 2015 UPDATE

Page 59

The TIA Manual (Program Management Plan)

Similar to this:

APPENDIX E
CERTIFICATION OF WORK AND FINAL ACCEPTANCE
**For execution after Project completion.
PROJECT NAME:___________________________________
PROJECT NUMBER:___________________________________
LOCAL GOVERNMENT:___________________________________

This is to certify that all work for the above referenced Project has been completed in accordance with this Agreement
and in accordance with the scope as defined in the Approved Investment List(s). A final inspection of the Project has
been made. All punch list work has been completed and accepted.

DATE:

______________________________________
Signature of Authorized Local Government Representative
USE NEW FORM (ADD MATERIALS CERT?)

JANUARY 2015 UPDATE

Page 60

The TIA Manual (Program Management Plan)

14 Quality Management
14.1 Introduction
Quality management includes all the activities that are used to direct, control, and coordinate quality. These activities include
formulating a quality policy and setting quality objectives and procedures. They also include quality planning, quality control, quality
assurance, and quality improvement.
Each consultant and contractor is responsible for quality management on their respective contract. The PgM may request to review
consultant or contractor quality management plans.

14.1.1 Quality Assurance Elements
The basic quality assurance elements include but are not limited to the following:
•

Development and implementation of quality plans, procedures and instructions

•

Quality management organization and personnel qualifications

•

Design and management control

•

Review and control of contract drawings and text documents

•

Procurement control, Quality records and electronic data file control

•

Indoctrination, training, and certification

•

Verification of all quality requirements (to include reviews, audits, and surveillance)

14.1.2 Quality Control Elements
The basic quality control elements will include execution of any (or all) of the following, as applicable:
•

Inspections of works

•

Tests of materials and equipment

•

Control of calibration of measuring and test equipment

•

Audit of processes and systems

14.1.3 Design
The GDOT Quality Control and Quality Assurance (QC/QA) Program has been developed by the Engineering Division of the
Georgia Department of Transportation to ensure the engineering, design, plans and quantities developed by our design offices are
supported by comprehensive studies and sound engineering judgment; comply with established policies, guidelines and standards;
and contain appropriate design flexibility and cost saving measures. This program shall be the basis for QC/QA on the TIA
program.
The document can be found at:
http://www.dot.ga.gov/doingbusiness/PoliciesManuals/roads/OtherResources/GDOT_QCQA_Program.pdf

JANUARY 2015 UPDATE

Page 61

The TIA Manual (Program Management Plan)

14.1.4 Construction
14.1.4.1 Requirements
At a minimum, QC/QA shall be performed in accordance with GDOT’s Sampling, Testing, and Inspection Manual, standard
specifications, supplemental specifications, special provisions or any other sampling or testing requirements such as material
provider’s recommendations.
For detailed instructions refer to The Source: http://www.dot.ga.gov/doingbusiness/TheSource/Pages/home.aspx

JANUARY 2015 UPDATE

Page 62

The TIA Manual (Program Management Plan)

15 Safety
This section defines the responsibility for safety for the PgM and each participant involved in the Program including GDOT,
contractors, consultants, designers, and inspectors. The contracts assign the responsibility of safety risks on the program to the
party most able to control and mitigate those risks.
In addition, the PgM recommends and encourage a "safety culture" on the program which makes it clear that all participants are
expected to report known hazards to the appropriate individual or entity responsible for the involved work, as well as perform their
own activities in full compliance with applicable laws and regulations.
The PgM is not contracted to provide comprehensive safety services to GDOT. The PgM is required to have a safety program in
place for its employees developed in accordance with the local laws and regulations. The PgM safety program includes as a
minimum, education and training for the PgM staff commensurate with company policy and the hazards expected to be
encountered during the program. The PgM is ultimately only responsible for the safety of its employees.
The PgM is not responsible for job site safety, construction means and methods, or the safety for the owner, contractors,
consultants, designers, and inspectors. On TIA construction projects, the contractor is solely responsible for the safety and welfare
of his employees and for the protection of property, other program stakeholders and the general public. The contractor has to
comply with all federal, state, local and county safety regulations, applicable to his work site.
IMPORTANT: All program participants have a duty to call attention to observed unsafe conditions as a key step in preventing
injuries to themselves or others. In addition to this basic ethical requirement, other responsibilities for job site safety derive from
statutes, regulations, case law and contracts.

JANUARY 2015 UPDATE

Page 63



Source Exif Data:
File Type                       : PDF
File Type Extension             : pdf
MIME Type                       : application/pdf
PDF Version                     : 1.4
Linearized                      : No
Warning                         : Invalid secondary xref table
Tagged PDF                      : Yes
Page Layout                     : OneColumn
EXIF Metadata provided by EXIF.tools

Navigation menu