TOGAF Arch. Project Mgmt. Guide Architecture PM

User Manual:

Open the PDF directly: View PDF PDF.
Page Count: 88

DownloadTOGAF Arch. Project Mgmt. Guide Architecture PM
Open PDF In BrowserView PDF
TOGAF® Series Guide
Architecture Project Management
How to Manage an Architecture Project using
the TOGAF® Framework and Mainstream Project Management Methods

Prepared by The Open Group Architecture Forum

Copyright © 2018, The Open Group. All rights reserved.
No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means,
electronic, mechanical, photocopying, recording, or otherwise, without the prior permission of the copyright owner.
This Guide has not been verified for avoidance of possible third-party proprietary rights. In implementing this Guide,
usual procedures to ensure the respect of possible third-party intellectual property rights should be followed.
TOGAF® Series Guide
Architecture Project Management
ISBN:

1-947754-14-0

Document Number:

G188

Published by The Open Group, May 2018.
Comments relating to the material contained in this document may be submitted to:
The Open Group, Apex Plaza, Forbury Road, Reading, Berkshire, RG1 1AX, United Kingdom
or by electronic mail to:
ogspecs@opengroup.org

ii

TOGAF® Series Guide (2018)

Contents
1

Introduction ............................................................................................................... 1
1.1 Overview......................................................................................................... 1
1.2 Background ..................................................................................................... 1
1.3 Why do we need a Guide on Architecture Project Management? .................. 2
1.4 Document Scope and Structure....................................................................... 3
1.5 Constraints ...................................................................................................... 3

2

Managing Architecture Projects ................................................................................ 4
2.1 Architecture Project Definition ....................................................................... 4
2.2 Architecture Project Lifecycle ........................................................................ 7
2.3 Architecture Project Management Concepts ................................................ 10
2.4 Project Management Documentation............................................................ 14

3

Detailed Guidance ................................................................................................... 16
3.1 Architecture Project Start-Up ....................................................................... 17
3.1.1
Appoint the Executive ................................................................... 17
3.1.2
Appoint the Project Manager......................................................... 19
3.1.3
Capture Previous Lessons ............................................................. 20
3.1.4
Prepare Outline Business Case ...................................................... 21
3.1.5
Select the Project Approach .......................................................... 22
3.1.6
Design and Appoint the Project Management Team ..................... 24
3.1.7
Assemble the Project Brief ............................................................ 28
3.1.8
Define the Management Approach ................................................ 29
3.2 Architecture Project Planning ....................................................................... 32
3.2.1
Define the Architecture Project Scope .......................................... 33
3.2.2
Define the Final Product of the Architecture Project
and its Acceptance Criteria............................................................ 34
3.2.3
Define the Project Deliverables ..................................................... 35
3.2.4
Define the Project Exclusions, Constraints, and
Assumptions .................................................................................. 36
3.2.5
Detail the Architecture Project Scope ........................................... 37
3.2.6
Create the Work Breakdown Structure.......................................... 37
3.2.7
Develop the Architecture Project Plan and Schedule .................... 38
3.2.8
Consolidate the Statement of Architecture Work and
Secure Approval ............................................................................ 46
3.3 Planning a Stage............................................................................................ 47
3.3.1
What is a Stage? – Dividing an Architecture Project
into Stages ..................................................................................... 47
3.3.2
Planning a Stage ............................................................................ 48
3.3.3
Adjusting a Project Plan ................................................................ 50
3.4 Execute, Monitor, and Control a Stage ......................................................... 50
3.4.1
Authorize the Project Work Package ............................................ 51
3.4.2
Review Project Work Package Status ........................................... 51
3.4.3
Review Completed Project Work Package.................................... 52

Architecture Project Management

iii

3.5

3.6

iv

3.4.4
Review Stage Status ...................................................................... 52
3.4.5
Capture and Examine Issues and Risks ......................................... 52
3.4.6
Report Highlights .......................................................................... 53
3.4.7
Escalate Issues and Risks .............................................................. 54
3.4.8
Take Corrective Action ................................................................. 55
Ending a Stage .............................................................................................. 55
3.5.1
Stage Deliverables Hand-off and Approval .................................. 56
3.5.2
Managing a Stage Boundary ......................................................... 56
Architecture Project Closing ......................................................................... 57
3.6.1
Products Handover ........................................................................ 57
3.6.2
Prepare and Recommend Closure ................................................. 58
3.6.3
Evaluate the Project and Document Lessons Learned................... 59

4

PRINCE2 to ADM Mapping................................................................................... 61
4.1 High-Level Mapping Description ................................................................. 61
4.1.1
TOGAF ADM Phase A (Architecture Vision) .............................. 61
4.1.2
TOGAF ADM Phases B to F ........................................................ 62
4.2 Detailed Mapping Description ...................................................................... 64
4.2.1
TOGAF ADM Phase A (Architecture Vision) .............................. 64
4.2.2
TOGAF ADM Phases B to F ........................................................ 66

5

PMBOK to ADM Mapping..................................................................................... 68
5.1 Phase A: Architecture Project Initiation and Planning ................................. 70
5.1.1
Establish the Architecture Project ................................................. 70
5.1.2
Identify Stakeholders, Concerns, and Business
Requirements ................................................................................. 70
5.1.3
Confirm and Elaborate Business Goals, Business
Drivers, and Constraints ................................................................ 70
5.1.4
Evaluate Capabilities ..................................................................... 71
5.1.5
Assess Readiness for Business Transformation ............................ 71
5.1.6
Define Scope ................................................................................. 71
5.1.7
Confirm and Elaborate Architecture Principles,
including Business Principles ........................................................ 71
5.1.8
Develop Architecture Vision ......................................................... 71
5.1.9
Define the Target Architecture Value Propositions and
KPIs ............................................................................................... 71
5.1.10 Identify the Business Transformation Risks and
Mitigation Activities...................................................................... 72
5.1.11 Develop Statement of Architecture Work; Secure
Approval ........................................................................................ 72
5.2 Phases B to F: Architecture Project Execution and Monitoring ................... 72
5.3 Phase F: Architecture Project Closing .......................................................... 74

TOGAF® Series Guide (2018)

Preface
The Open Group

The Open Group is a global consortium that enables the achievement of business objectives
through technology standards. Our diverse membership of more than 600 organizations includes
customers, systems and solutions suppliers, tools vendors, integrators, academics, and
consultants across multiple industries.
The Open Group aims to:


Capture, understand, and address current and emerging requirements, establish policies,
and share best practices



Facilitate interoperability, develop consensus, and evolve and integrate specifications and
open source technologies



Operate the industry’s premier certification service

Further information on The Open Group is available at www.opengroup.org.
The Open Group publishes a wide range of technical documentation, most of which is focused
on development of Open Group Standards and Guides, but which also includes white papers,
technical studies, certification and testing documentation, and business titles. Full details and a
catalog are available at www.opengroup.org/library.
®

The TOGAF Standard, a Standard of The Open Group

The TOGAF standard is a proven enterprise methodology and framework used by the world’s
leading organizations to improve business efficiency.
This Document

This document is a TOGAF® Series Guide to Architecture Project Management. It has been
developed and approved by The Open Group.
The document supersedes Architecture Project Management, White Paper (W16B), August
2016, published by The Open Group.
More information is available, along with a number of tools, guides, and other resources, at
www.opengroup.org/architecture.
®

About the TOGAF Series Guides

The TOGAF® Series Guides contain guidance on how to use the TOGAF framework. They form
part of the TOGAF Body of Knowledge.
The TOGAF® Series Guides are expected to be the most rapidly developing part of the TOGAF
document set. While the TOGAF framework is expected to be long-lived and stable, guidance on
Architecture Project Management

v

the use of the TOGAF framework can be industry, architectural style, purpose, and problemspecific. For example, the stakeholders, concerns, views, and supporting models required to
support the transformation of an extended enterprise may be significantly different than those
used to support the transition of an in-house IT environment to the cloud; both will use the
Architecture Development Method (ADM), start with an Architecture Vision, and develop a
Target Architecture on the way to an Implementation and Migration Plan. The TOGAF
framework remains the essential scaffolding across industry, domain, and style.

vi

TOGAF® Series Guide (2018)

Trademarks
ArchiMate®, DirecNet®, Making Standards Work®, OpenPegasus®, Platform 3.0®, The Open
Group®, TOGAF®, UNIX®, UNIXWARE®, and the Open Brand X® logo are registered
trademarks and Boundaryless Information Flow™, Build with Integrity Buy with Confidence™,
Dependability Through Assuredness™, Digital Practitioner Body of Knowledge™, DPBoK™,
EMMM™, FACE™, the FACE™ logo, IT4IT™, the IT4IT™ logo, O-DEF™, O-PAS™, Open
FAIR™, Open O™ logo, Open Platform 3.0™, Open Process Automation™, Open Trusted
Technology Provider™, SOSA™, and The Open Group Certification logo (Open O and
check™) are trademarks of The Open Group.
Excel® and MS Project® are registered trademarks of Microsoft Corporation in the United States
and/or other countries.
PMBOK® is a registered trademark of the Project Management Institute, Inc. which is registered
in the United States and other nations.
PRINCE2® is a registered trademark of AXELOS Limited.
All other brands, company, and product names are used for identification purposes only and may
be trademarks that are the sole property of their respective owners.

Architecture Project Management

vii

About the Authors
The authors of this Guide have backgrounds in both Enterprise Architecture and Project
Management.
Jacek Presz

Jacek Presz (http://linkedin.com/in/jacekpresz) is an experienced Enterprise Architect focused on
planning and supporting technology-enabled business transformation. He has held Chief
Enterprise Architect positions in Banking, Technology, and Power & Utilities companies. While
working for one of the leading consulting firms, he delivered Architecture Projects on a strategic
and segment level for clients in different sectors. He is actively engaged in TOGAF standard
development.
Łukasz Wrześniewski, The Open Group Invited Expert

Łukasz Wrześniewski (http://linkedin.com/in/lukaszwrzesniewski) works as an Agile
Transformation and Enterprise Architecture Consultant. He specializes in Agile Enterprise
Architecture and Agile Program Management. He is also an active trainer who provides
TOGAF®, ArchiMate®, IT4IT™, and Scaled Agile training courses. He is participating in the
Agile Enterprise Architecture team and in the Architecture, IT4IT, ArchiMate Harmonization
Project as an invited expert.
Łukasz Drążek, PMP

Łukasz Drążek, PMP (http://linkedin.com/in/lukaszdrazek) is a manager with experience in
largescale IT projects for the banking, public, energy, power & utilities, and FMCG sectors. He
specializes in project and program management, program recovery, technology-enabled
transformation, and change management. He is responsible for the IT Delivery Management
practice in the Digital & Technology Enablement Advisory Group, EY Poland.
Maciej Iwaniuk, PMP

Maciej Iwaniuk, PMP (http://linkedin.com/in/maciekiwaniuk) is a certified Project Manager and
experienced Project Auditor with experience in local and international project planning,
execution, and management. He is involved in Project Management method design,
development, and implementation. He is an Integration Leader at EY EMEIA Advisory Center.
Bartłomiej Rafał, EY

Bartłomiej Rafał (http://linkedin.com/in/bartlomiejrafal) is a TOGAF Certified practitioner and a
Senior Analyst in the Digital & Technology Enablement Advisory Group, EY Poland. During
his career at EY, he has been involved in some of the largest architecture transformation
programs for leading organizations around the world. Currently, he is interested in improving his
Enterprise Architecture skill set (especially in data and application domains), and applying it to
support organizations intending to undergo Digital Transformation.

viii

TOGAF® Series Guide (2018)

Filip Szymański, EY

Filip Szymański (http://linkedin.com/in/szymanskifilip) is a TOGAF Certified practitioner and a
manager with experience in leading strategic and tactical change management projects focused
around Enterprise Architecture. He specializes in designing Enterprise Architecture, as well as
information systems architectures aimed at enabling value delivery to the business. He is
responsible for the IT Architecture practice in the Digital & Technology Enablement Advisory
Group, EY Poland.
Piotr Papros

Piotr Papros (http://linkedin.com/in/papros) is an IT Manager experienced in leading complex IT
projects, programs, and services for worldwide institutions. He is a Lean-Agile program
consultant, having served as a Lean-Agile coach in transformation efforts at an organization
level. He is an enthusiast of gamification, enterprise change management, and sport.

Architecture Project Management

ix

Acknowledgements
The Open Group gratefully acknowledges the authors and also past and present members of The
Open Group Architecture Forum for their contribution in the development of this Guide.
The authors would like to thank the following key contributors and reviewers, without whom the
original White Paper would not have been possible:

x



Atila Belloquim, Gnosis



Sonia Gonzalez, The Open Group



Kirk Hansen, Kirk Hansen Consulting

TOGAF® Series Guide (2018)

Referenced Documents
The following documents are referenced in this TOGAF® Series Guide.
(Please note that the links below are good at the time of writing but cannot be guaranteed for the
future.)


A Guide to the Project Management Body of Knowledge (PMBOK® Guide), 5th Edition,
Project Management Institute (PMI), 2013; refer to www.pmi.org



ArchiMate® 3.0.1 Specification, an Open Group Standard (C179), published by The Open
Group, August 2017; refer to: www.opengroup.org/library/c179



Managing Successful Projects with PRINCE2®, 2009 Edition, AXELOS, 2009



Practice Standard for Project Risk Management, Project Management Institute (PMI),
2009; refer to www.pmi.org



The PRINCE2® Foundation Training Manual, Frank Turley, 2013



The TOGAF® Standard, Version 9.2, a standard of The Open Group (C182), published by
The Open Group, April 2018; refer to: www.opengroup.org/library/c182

The following documents are not directly referenced in the text, but may be useful:


A Guide to the Project Management Body of Knowledge (PMBOK® Guide), 3rd Edition,
Project Management Institute (PMI), 2004



A Guide to the Project Management Body of Knowledge (PMBOK® Guide), 4th Edition,
Project Management Institute (PMI), 2009



Understanding PRINCE2®, Ken Bradley, 2002



Directing Successful Projects with PRINCE2®, AXELOS, 2009

Architecture Project Management

xi

xii

TOGAF® Series Guide (2018)

1

Introduction

1.1

Overview
Architecture Projects are typically complex in nature. They need proper Project Management to
stay on track and deliver on promise. This Guide is intended for people responsible for planning
and managing Architecture Projects. We explain how the TOGAF® Architecture Development
Method (ADM) can be supplemented with de facto methods and standards such as PRINCE2® or
PMBOK® to strengthen Project Management and improve the probability of success for
Architecture Projects.
This Guide provides Architecture Project Teams with an overall view and detailed guidance on
what processes, tools, and techniques of PRINCE2 or PMBOK can be applied alongside the
TOGAF ADM for project planning, monitoring, and control. Further, a detailed mapping of the
processes and deliverables of the TOGAF framework against PRINCE2 and PMBOK is
provided to visualize how those concepts come together.
This Guide is not intended to serve as a Project Management method guidance book. We explain
what Project Management tools and techniques should be applied to Architecture Projects, but
we rely on specific PRINCE2 and PMBOK publications for detailing those techniques or tools.
We hope that the introduction of Project Management techniques to Architecture Projects will
improve the chances for success of delivered value and solutions in a mature and professional
way, supporting The Open Group vision of Boundaryless Information Flow™.

1.2

Background
According to the TOGAF standard, Enterprise Architecture is the structure of enterprise
components, their inter-relationships, and the principles and guidelines governing their design
and evolution over time. Enterprise is the highest level of description of an organization and
typically covers all missions and functions; it can span multiple organizations.
The TOGAF standard includes the Architecture Development Method (ADM) that aims to be an
industry standard method for developing and implementing an Enterprise Architecture. This
method focuses on delivery of architecture products.
In the TOGAF standard, architecture products are delivered through execution of tasks described
in the ADM. These tasks are grouped into inter-related phases, each of which includes a number
of steps. Completing an ADM cycle can be a complex task. Therefore, architecture products
delivery is often executed as a project.
Architecture Project is not a term defined in the TOGAF standard; however, it is used often for a
project undertaken to define and describe an Enterprise Architecture to be implemented.
Therefore, in this Guide, the term “Architecture Project” encompasses all activities undertaken
within Phases A to F, and Requirements Management.

Architecture Project Management

1

Figure 1: Architecture Project Relationship to the TOGAF ADM (Adapted from the TOGAF
Standard)

A key result of Phases A to F is an Architecture Definition Document, which describes the
Enterprise Architecture to be implemented in Phase G and maintained in Phase H. Therefore, at
the end of Phase F the Enterprise Architecture to be implemented is defined and described – and
the Architecture Project, by our definition, is completed.
The Preliminary Phase, Phase G, and Phase H are out of scope for the Architecture Project. The
Preliminary Phase is concerned with ensuring an Enterprise Architecture capability of the
organization. The goal of Phase G is to govern implementation of the Enterprise Architecture.
Typically, it is run as a separate endeavor (a project or a set of projects). The goal of Phase H is
to maintain the Enterprise Architecture implemented – it is related to operational business (or
process) rather than project management.

1.3

Why do we need a Guide on Architecture Project Management?
The TOGAF ADM details objectives, approach, inputs, steps, and outputs of the Enterprise
Architecture development phases. However, it is not specific on how to manage an Architecture
Project and leaves that to methods that focus on Project Management.1
Project Management is the planning, delegating, monitoring, and control of all aspects of the
project, and the motivation of those involved, to achieve the project objectives within the

1

The TOGAF standard, Phase A (Establish the Architecture Project): “Each cycle of the ADM should normally be handled as a
project using the project management framework of the enterprise.”

2

TOGAF® Series Guide (2018)

expected performance targets for time, cost, quality, scope, benefits, and risks. 2 Market-leading
Project Management methods include PRINCE2 and PMBOK. They can be used to enhance an
Architecture Project’s chances of success.
Not all TOGAF practitioners are familiar with Project Management methods. Even for those
who are, there is no guidance on how to use and align the TOGAF framework with these
methods.
The intent of this Guide is to provide guidelines for TOGAF architects on how to manage an
Architecture Project. We suggest an approach that supplements the TOGAF ADM with selected
Project Management techniques. The goal of this approach is to enhance an Architecture
Project’s chances of success through better planning, monitoring, and communication.

1.4

Document Scope and Structure
This Guide is structured in the following sections, with a specific target audience in each case:


Managing Architecture Projects (Chapter 2) describes a high-level Project Management
approach for developing an Enterprise Architecture
The target audience for this section is Enterprise Architects, Project Management
professionals, and stakeholders of Architecture Projects who want to understand the key
relationships between the TOGAF standard and Project Management areas.



Detailed Guidance (Chapter 3) describes a detailed Project Management approach for
developing an Enterprise Architecture
It includes a step-by-step guide to Architecture Project initiating, planning, monitoring,
and closing. The target audience of this section is Enterprise Architects who are familiar
with the TOGAF standard and who lead Architecture Projects.



PRINCE2 to ADM Mapping (Chapter 4) and PMBOK to ADM Mapping (Chapter 5)
present detailed mappings between the phases of the TOGAF ADM and PRINCE2 and
PMBOK processes, respectively
These sections provide a foundation on which the guidance was built and are included for
reference.

1.5

Constraints
This Guide explores how Project Management methods can supplement the TOGAF ADM in
Architecture Project delivery. It focuses on PRINCE2 and PMBOK as proven practices in the
Project Management area.
Agile Project Management methods are out of scope for this Guide. In our experience, the
TOGAF framework can be tailored to use an agile approach. Such tailoring can provide
important benefits. However, it is not explored in this Guide.

2

This is a PRINCE2 definition. According to the more general PMBOK definition, Project Management is an application of
knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Architecture Project Management

3

2

Managing Architecture Projects
This section describes a general, high-level Project Management approach for developing an
Enterprise Architecture. The target audience for this section is Enterprise Architects, Project
Management professionals, and stakeholders of Architecture Projects who want to understand
the key relationships between the TOGAF standard and Project Management areas.

2.1

Architecture Project Definition
An Architecture Project is an endeavor undertaken to define and describe the Enterprise
Architecture to be implemented. In TOGAF terms, as shown in Figure 1, it encompasses all
activities undertaken within the Phases A to F and Requirements Management of the ADM.
Practically, it can be a stand-alone project or part of a larger effort (e.g., a program).
An Architecture Project does not include the Preliminary Phase, Phase G, or Phase H of the
ADM.
The Preliminary Phase focuses on establishing an Architecture Capability rather than delivery
of an Architecture Definition. It can initiate an Architecture Project when necessary (outputs
from the Preliminary Phase, especially Request for Architecture Work, are treated as an input
to the Architecture Project).


Phase G (Implementation Governance) is about implementing the architecture, not defining it.
It can be a separate project or a program (or even a part of the same program as the
Architecture Project), but it is not concerned with delivery of an architecture (outputs from
the Architecture Project are treated as inputs to Phase G).
Phase H (Change Management) is a continuous process concerned with maintaining the
architecture and initiating Architecture Projects when necessary and it should be treated as an
operational activity.

An Architecture Project starts with a Request for Architecture Work, which – according to the
TOGAF ADM – is an input initiating Phase A. It delivers an Architecture Definition, a
Roadmap, and an Implementation Plan. It is finished when these outputs are handed over for
implementation.
An Architecture Project can concern one or more architecture domains. The TOGAF standard
defines four architecture domains (Business, Data, Application, Technology) – an Architecture
Project typically covers a few or all of them.
An Architecture Project can concern different levels of architecture. The TOGAF standard
defines three levels of architecture – an Architecture Project typically covers exactly one of
these:

4



Strategic Level: covers the entire enterprise and defines the high-level vision, principles,
and strategic directions for the entire Enterprise Architecture



Segment Level: defines the Enterprise Architecture for a segment (business domain) of
the enterprise

TOGAF® Series Guide (2018)



Capability Level: defines the Enterprise Architecture for a single business capability
Enterprise Architecture at this level is the most detailed and leads directly to capability
implementation.

Figure 2: Levels of Enterprise Architecture (the TOGAF Standard: Summary Classification Model
for Architecture Landscapes)

Architecture developed by an Architecture Project on the strategic level typically is an input to a
segment-level Architecture Project. Similarly, segment-level Architecture Projects provide input
for capability-level Architecture Projects.
An Architecture Project can be executed as a stand-alone endeavor or as part of a larger effort:


A stand-alone Architecture Project is usually executed as a separate project (in line with
the Project Management regulations of the enterprise)
It has its own set of goals that can be achieved by the project itself (i.e., the Architecture
Definition not its implementation). Stand-alone Architecture Projects are often executed
on the strategic and segment architecture level.



Part of a larger effort means that the Architecture Project is a part of a project or program,
typically a work stream or a group of tasks
Its key goal is to develop the architecture for implementation within the larger effort.
Architecture Projects that are a part of a larger effort are usually executed on the
capability architecture level and sometimes on the strategic and segment levels.



An Architecture Project that is a part of a larger effort does not have to be recognized as a
project in terms of the Project Management regulations of the enterprise. More often, it can be
a work stream or simply a group of tasks. The approach recommended in this Guide can be
applied to both stand-alone Architecture Projects and architecture work that is part of a larger
effort.

Architecture Project Management

5

Table 1 presents a few examples of real-world Architecture Projects. These examples cover
different possible characteristics of an Architecture Project (e.g., level, domains, relationship to
other projects).
Table 1: Examples of Architecture Projects
Overall Goal

Architecture Project Overview

(A) Assess current
application portfolio
and recommend
improvement
options

Describe application landscape and identify IT improvement options.
There are about 50 applications of different scales (precise number to be
determined), mostly custom-built. Key concerns are:


Determining relationships and data flows between applications



Mapping application capabilities (overlaps and gaps)



Identification of key technological constraints for application development

Required views are to be determined. Improvement options should include
initiatives with assigned priorities. Timeframe is flexible within 22 weeks
maximum.
(B) Improve
logistics process
efficiency and
shorten time-toorder

Project scope is to model and plan target logistics process improvements to:


Provide current information on parcel location, resource use, and process
bottlenecks



Optimize resources usage through more accurate planning and use of the
above information



Shorten order-to-delivery through faster resource allocation and use of
preallocated resources

The logistics process is one of the core business processes of a transportation
company. Three large business units play key roles in the process, each of them
divided into about five subunits.
The team, apart from a business analyst and an Enterprise Architect, includes a
subject matter expert who already understands some parts of this process.
(C) Consolidate IT
environment of
recently merged
businesses

Define target IT architecture and a three-year roadmap to consolidate merged
businesses.
Power & Utilities holding includes eight recently merged business units, which
distribute and sell energy. These units operate in different areas geographically.
They are similar, but each of them has its own business processes and IT
applications. Nothing is shared between them.
The Architecture Project goal is to formulate a consolidation roadmap, which
would include common business services, IT applications, and infrastructure. The
approach includes three stages: as-is analysis, to-be modeling, and roadmapping.
The Architecture Project must meet defined budget and timeframe constraints.

6

TOGAF® Series Guide (2018)

Overall Goal

Architecture Project Overview

(D) Define a
solution architecture
for a Customer
Information System
supporting a new
operating model in a
retail sales area of a
P&U company

Analyze changes in an operating model in a retail sales area of a P&U company
and requirements for a solution architecture resulting from it.
Identify issues with current IT systems supporting this area that prevent the
implementation of a new operating model.
Develop a solution architecture for a Customer Information System that addresses
identified issues and supports the operating model along with a map of data
exchange between the system and other IT solutions located in its environment.
Develop a tender documentation for a Customer Information System containing
the description of the solution architecture.

(E) New
management
information system
to address
expanding bank
reporting needs

Define and implement new elastic management information system that will
address expanding bank reporting needs and shorten information delay. Project
scope includes:


Analyze current state – old data warehouse inbound and outbound interfaces,
data processing logic and report types



Define target architecture including moving deprecated functionality to other
solutions



Prepare High Level Design documentation

These examples were chosen to encompass different kinds of Architecture Projects. Generally,
they can be characterized by:


Levels of architecture3 covered: Strategic (A, C), Segment (B, D), Capability (E)



Architecture domains4 covered: Business (B, C, D, E), Data (B, C, D, E), Application (A,
B, C, D, E), Technology (C, D, E)



Relationship to other projects: stand-alone (A, B, D), part of a larger program (C, E)

These project examples are used throughout Detailed Guidance (Chapter 3) to enhance presented
guidance with a practical context. Examples that refer to these projects are denoted using gray
boxes.

2.2

Architecture Project Lifecycle
The Architecture Project can be executed as a single, preplanned stage, but usually it is divided
into a few stages. Use of stages allows for a more elastic approach, as each of the stages is
typically planned in detail just before it starts (rather than at the start of the whole project). The
TOGAF standard advocates iterative execution of Architecture Projects – in this case, each
iteration can be considered a separate stage.

3

For guidance on architecture levels, refer to the TOGAF standard, Part III: Applying the ADM Across the Architecture Landscape.

4

For guidance on architecture domains, refer to the TOGAF standard, Part I: Core Concepts (What Kind of Architecture Does the
TOGAF Standard Deal With?).

Architecture Project Management

7



Dividing the Architecture Project into stages is discussed in detail in this Guide. For more
information on the iterative approach, refer to architecture development in the TOGAF
standard, Part III: Applying Iteration to the ADM.

The Architecture Project encompasses management activities that can be grouped and sequenced
as follows:


Architecture Project start-up, which raises issues related to appointing the Executive and
Project Manager, as well as the Project Management team, capturing previous lessons,
selecting the project approach, assembling the project brief, and planning the following
stage



Architecture Project planning, which describes project scoping and planning activities
based on Project Management methods



Planning a stage, which describes how to split an Architecture Project into stages and plan
a stage in alignment with an overall Project Plan



Execute, monitor, and control a stage, which describes how to monitor and control
architecture development activities of the ADM Phases B to F using Project Management
methods



Ending a stage, which describes key steps performed at a stage end



Architecture Project closing (and handover of architecture deliverables for
implementation), which describes the project closing activities and handover of the
Architecture Project products to implementation programs and projects, and also the
approach for documenting lessons learned

The above sequence forms an Architecture Project lifecycle, which is used as the basic structure
to discuss Architecture Project Management in this Guide. This lifecycle maps into the TOGAF
ADM (which describes architecture development phases and steps). It can be represented by
Figure 3.

8

TOGAF® Series Guide (2018)

Figure 3: Architecture Project Lifecycle from the TOGAF ADM Perspective



Please note: to simplify Figure 3 it assumes Architecture Project is divided into stages that
resemble the ADM phases (each stage covers one ADM phase). Usually, this is not the case –
and in most cases should not be; the TOGAF standard recommends an iterative approach, in
which a stage can cover a few phases and can be executed repeatedly.
Dividing the Architecture Project into stages is discussed in detail in this Guide. For more
information on the iterative approach to architecture development, refer to the TOGAF
standard, Part III: Applying Iteration to the ADM.

The Architecture Project lifecycle also maps to Project Management methods. Generally, these
methods abstract from actual subject matter work in the project (i.e., architecture development),
as they focus on management processes and steps needed for successful project execution.


Detailed mapping of the TOGAF ADM and most popular Project Management methods is
presented in Chapter 4 and Chapter 5 of this Guide.

Architecture Project Management

9

High-level mapping of the Architecture Project lifecycle to the TOGAF ADM phases and
Project Management methods is presented in Table 2. Please note that the TOGAF standard
focuses on architecture development activities in the Architecture Project, and Project
Management methods focus on managing successful execution of this endeavor.
Table 2: Architecture Project Lifecycle Mapped to the TOGAF ADM and Project Management
Methods
Architecture Project
Lifecycle
Architecture Project
start-up

TOGAF ADM Phases

PRINCE2

Phase A (Architecture
Starting up the Project
Vision) – Establish an
Process – all steps
Architecture Project step

PMBOK
Initiation Process group:
4.1 Develop Project
Charter
13.1 Identify Stakeholders

Architecture Project
planning

Phase A (Architecture
Vision) – Develop a
Statement of
Architecture Work step
and previous steps

Initiation Process –
Create the Project Plan,
Assemble the Project
Initiation
Documentation

Planning a stage

No direct mapping, but
can be thought of as a
closing step of the
preceding phase

PRINCE2 highlights the concept of project stages
more than PMBOK. The concept described in this
Guide is mostly based on PRINCE2 processes, but it
is also consistent with PMBOK.

Execute, monitor, and
control a stage

Each of the Phases B to
F

The Execute, Monitor, and Control a Stage section
maps to the Execute and Monitor and Control
process groups defined in PMBOK.

Ending a stage

No direct mapping, but
can be thought of as a
closing step of the
preceding phase

Architecture hand-over Phase F (Migration
Closing the project
Planning) – closing steps process – hand over
products

Planning processes from
all process groups – create
and collect Project
Management plan

Closing the project section

(Source: Derived from the TOGAF standard, PRINCE2, and the PMBOK Guide, 5th Edition)
To sum up, the Architecture Project lifecycle consists of six types of activities, which can be
mapped to both the TOGAF ADM phases and Project Management method processes and steps.
It is used to structure the detail presented in Detailed Guidance (Chapter 3).

2.3

Architecture Project Management Concepts
Every method or framework defines its own set of core concepts and definitions. Sometimes
they overlap. Sometimes the meaning of overlapping concepts is similar, sometimes not – and
they can be considered “false friends” for people who go from one subject matter world to
another.

10

TOGAF® Series Guide (2018)

The TOGAF standard is more recent5 than the most popular Project Management methods and
uses some of the terms and concepts defined by them. In some cases, it gave these terms a new
life and there are significant differences in the meaning of some key definitions used throughout
the TOGAF standard and Project Management methods. They are discussed in detail throughout
this Guide.
Table 3 presents the TOGAF and Project Management concepts that are key from the
perspective of Architecture Project Management. It discusses definitions presented in the
TOGAF standard, PRINCE2, and PMBOK and presents how each term is used throughout this
Guide.
Table 3: Key Concepts of the TOGAF Standard, PRINCE2, and PMBOK for this Guide
Concept

Discussion and Definitions

Architecture
Project

As defined earlier in this Guide, an Architecture Project is an endeavor undertaken
to define and describe the Enterprise Architecture to be implemented. In TOGAF
terms, it encompasses all activities undertaken within the ADM Phases A to F, and
Requirements Management for these phases. Practically, it can be a stand-alone
project or part of a larger effort (e.g., a program).
It has not been defined explicitly in the TOGAF standard; however, it is used in the
framework on a few occasions.
There are no corresponding definitions for this concept in Project Management
methods.

Deliverables

Deliverables are unique and verifiable products, results, outputs that are required to
be prepared to complete the project or particular phase of the project. Deliverables
may be part of the final product, any auxiliary products, or Project Management
products. This term is similar in both the TOGAF standard (where it is more
specific, by defining more of the characteristics, acceptance process, etc.) and
Project Management methods (more generic), so the most appropriate is the
definition from the TOGAF standard; however, the definitions from Project
Management methods are also applicable.
TOGAF Standard: “An architectural work product that is contractually specified
and in turn formally reviewed, agreed, and signed off by the stakeholders.
Note: Deliverables represent the output of projects and those deliverables that are
in documentation form will typically be archived at completion of a project, or
transitioned into an Architecture Repository as a reference model, standard, or
snapshot of the Architecture Landscape at a point in time.”
PRINCE2: Synonymous with “Output”, which is defined as: “A specialist product
that is handed over to a user(s)”.
PMBOK Guide, 5th Edition: “Any unique and verifiable product, result, or
capability to perform a service that is required to be produced to complete a
process, phase, or project.”

5

This statement refers to Enterprise Editions of the TOGAF standard (Versions 8 and above), which became popular and are a de
facto standard for Enterprise Architecture. The TOGAF 8 standard was published in 2003 (with the latest revision of the TOGAF 9
standard published in 2018), PRINCE2 in 1996 (with a major refresh in 2009), and PMBOK in 1996 (with a major revision in 2004
which was the 3rd Edition; this Guide is based on the 5th Edition published in 2013).

Architecture Project Management

11

Concept

Discussion and Definitions

Executive

The Executive is the owner of the business goal, responsible for realization of
expected benefits, and ultimate success of the project. Its role is comparable with
the roles of Sponsor and Executive (which can be considered synonymous with
Architecture Sponsor from the Skills Framework) in PMBOK and the TOGAF
standard, respectively, though in the case of PMBOK the involvement of the
Sponsor versus Executive is more limited. For the sake of clarity, in this document
we will use “Executive” to define such enabling role, no matter what method we
refer to in a particular context.
TOGAF Standard: No explicitly stated definition, but has named key concerns as
“On-time, on-budget delivery of a change initiative that will realize expected
benefits for the organization”.
PRINCE2: “The single individual with overall responsibility for ensuring that a
project meets its objectives and delivers the projected benefits. This individual
should ensure that the project maintains its business focus, that it has clear
authority, and that the work, including risks, is actively managed.”
PMBOK Guide, 5th Edition: (Sponsor) “A person or group who provides
resources and support for the project, program, or portfolio and is accountable for
enabling success.”

Phase

In this Guide, we use the term “phase” for the TOGAF ADM phases. This is
different from the “project phase” term used throughout PMBOK – we use the
term “stage” for project phases (see Stage below).
TOGAF Standard: Used extensively to describe a collection of logically-related
work within the ADM, which is divided into specified phases; e.g., Phase A –
Architecture Vision.
PRINCE2: No special meaning.
PMBOK Guide, 5th Edition: “A project may be divided into any number of
phases. A project phase is a collection of logically-related project activities that
culminates in the completion of one or more deliverables.”

Project Manager

In this Guide, we use the term “Project Manager” to describe a person responsible
for ensuring that the project (in this case, Architecture Project) delivers the
required product that satisfies the stakeholders’ needs.
This constitutes the common part of the definitions from both Project Management
methods. The TOGAF standard does not explicitly define Project Manager, so use
of the term based on the Project Management methods was necessary.
Please note that the role of Project Manager can be appointed to an Enterprise
Architect or to a Project Management professional; refer to the Appoint the Project
Manager (Section 3.1.2) for details.
TOGAF Standard: No special meaning.
PRINCE2: “The person given the authority and responsibility to manage the
project on a day-to-day basis to deliver the required products within the constraints
agreed with the Project Board.”
PMBOK Guide, 5th Edition: “The person assigned by the performing
organization to lead the team that is responsible for achieving the project
objectives.”

12

TOGAF® Series Guide (2018)

Concept

Discussion and Definitions

Risk

Project risk management is an important aspect of Project Management. According
to the PRINCE2 and PMBOK, risk management is one of the key knowledge areas
in which a Project Manager must be competent.
Project risk is defined by PRINCE2 as “a set of events that, should they occur, will
have an effect on achieving the project objectives”,6 and by PMBOK as “an
uncertain event or condition that, if it occurs, has a positive or negative effect on a
project’s objectives”.7
It is important to note that risk impact on a project can be either negative (and
actions taken should be focused on minimizing the effect or probability of
occurrence) or positive, when we would like to increase the impact or probability
of occurrence of such an event.
Risk and compliance are an inherent part of any business activity or
transformation, thus the TOGAF standard requires proper consideration throughout
the ADM, as defined in the Architecture Capability Framework.
The key difference is that the TOGAF standard understands risk as a potential
threat of the transformation to the technical environment and compliance, while
PRINCE 2 and PMBOK are also considering risk as an event that can affect the
project itself (timeline, budget, quality, etc.).

Scope

In this Guide, we use the term “scope: as defined in the Project Management
methods. This is a broader meaning than described in the Define Scope step of the
TOGAF ADM Phase A, and it means the scope of work that is to be performed in
order to achieve projects goals. In contrast, the TOGAF standard restricts use of
the term scope to the scope of the architecture to be defined.
TOGAF Standard: The Define Scope step of the ADM Phase A restricts the
scope definition to the scope of architecture: “what is inside and what is outside the
scope of the Baseline Architecture and Target Architecture efforts”.
PRINCE2: “The scope of a plan is the sum total of its products and the extent of
their requirements. It is described by the product breakdown structure for the plan
and associated product descriptions.”
PMBOK Guide, 5th Edition: “The sum of the products, services, and results to be
provided as a project.”

Stage

In this Guide, we use the term “stage” for stages (as defined in PRINCE2) or
project phases (as defined in PMBOK). We do not use the term “project phase” as
we reserve it for the TOGAF ADM phases (see Phase above).
TOGAF Standard: No defined meaning.
PRINCE2: “A section of a project.”
PMBOK Guide, 5th Edition: No defined meaning.

6

The PRINCE2 Foundation Training Manual, by Frank Turley.

7

Practice Standard for Project Risk Management, PMI.

Architecture Project Management

13

Concept

Discussion and Definitions

Stakeholder

The meaning of stakeholder in the TOGAF standard and Project Management
methods is generally the same. The TOGAF standard, as an architecture lifecycle
standard, highlights that the stakeholder focuses on the outcomes of the
architecture.
TOGAF Standard: “An individual, team, organization, or class thereof, having an
interest in a system.”8
PRINCE2: “Any individual, group, or organization that can affect, be affected by,
or perceive itself to be affected by, an initiative (program, project, activity, risk).” 9
PMBOK Guide, 5th Edition: “An individual, group, or organization who may
affect, be affected by, or perceive itself to be affected by a decision, activity, or
outcome of a project.”10

Work Package

The TOGAF standard uses the term work package to describe change initiatives
that will be implemented in the enterprise. These initiatives are typically large
groups of tasks (i.e., they may encompass a whole program).
Project Management methods use the term work package to describe a low-level
part of work to be performed – the most granular part of work that needs the
Project Manager’s authorization before it is started by the team.
The two meanings are vastly different. In this Guide, we use the term “Project
Work Package” for project tasks (in line with the PRINCE2 use of the term and the
PMBOK definition below) and “work package” for change initiatives identified by
Architecture Projects (in line with the TOGAF definition below).
TOGAF Standard: “A set of actions identified to achieve one or more objectives
for the business. A work package can be a part of a project, a complete project, or a
program.”
PRINCE2: “An input or output, whether tangible or intangible, that can be
described in advance, created, and tested.”
PMBOK Guide, 5th Edition: “The work defined at the lowest level of the work
breakdown structure for which cost and duration can be estimated and managed.”

(Source: Derived from the TOGAF standard, PRINCE2, PMBOK Guide, 5th Edition)
In this Guide we use concepts from both Enterprise Architecture (TOGAF) and Project
Management (PRINCE2, PMBOK) disciplines. As this Guide is addressed primarily to
architects, in case of conflicts, we usually stick to the TOGAF definitions. If you have a different
background, please keep Table 2 in mind.

2.4

Project Management Documentation
Project Management is about communication. The Project Manager is responsible for
communicating project plans, statuses, and risks to project stakeholders – the Project Sponsor,
Steering Committee, and other stakeholders. This can be effectively achieved formally or
informally, and in many forms – such as phone calls, meetings, presentations, or written reports.

8

The TOGAF standard, Part I: Definitions (Stakeholder).

9

Managing Successful Projects with PRINCE2, Glossary.

10

PMBOK Guide, 5th Edition, Glossary.

14

TOGAF® Series Guide (2018)

It depends on project size, organizational culture, and stakeholder requirements among other
things.
In this Guide, we often refer to plans, reports, and other artifacts that can or should be
documented. This does not mean every such artifact should be a separate document. In smaller
projects and more agile organizations, very little documentation may be required or necessary.
However, we do recommend that Project Management artifacts are documented in a written
form, even as simple as email. This allows for tracing back plans, important decisions, and
project milestones. In addition, documentation that is more formal can be prepared based on it, if
necessary.

Architecture Project Management

15

3

Detailed Guidance
This section describes a detailed Project Management approach to use when developing
Enterprise Architecture. The target audience of this section is Enterprise Architects who are
already familiar with the TOGAF standard and who lead Architecture Projects.
This section is organized into subsections which describe the approach to:


Architecture Project start-up, which includes the Project Management activities of the
ADM Phase A and the project start-up and “Initiation” activities of the Project
Management methods



Architecture Project planning, which includes project planning activities based on the
Project Management methods



Planning a stage, which describes how to apply the Project Management methods to plan
an Architecture Project stage



Execute, monitor, and control a stage, which describes how to monitor and control the
architecture development activities of the ADM Phases B to F using the Project
Management methods



Ending a stage, which describes how to apply the Project Management methods at the
end of an Architecture Project stage



Architecture Project closing, which includes project closing activities of the Project
Management methods and the ADM Phase F, including handover of architecture
deliverables for implementation

Architecture Project start-up
Architecture Project planning

Planning a stage
Execute, monitor, and control a stage

Architecture Project closing

n

Ending a stage

Figure 4: Structure of this Section and Architecture Project Flow (arrows)

Where appropriate, guidance refers to one or more real-world examples. These examples are
presented in gray boxes. They refer to selected projects from our examples list (see Table 1).

16

TOGAF® Series Guide (2018)



3.1

The approach in this Guide covers most of the Project Management responsibilities related to
an Architecture Project; however, some areas – such as schedule management, procurement
management, cost management, and others – are not covered. We assumed that the purpose of
this Guide is not to explain the Project Management methods in full detail, but to provide
guidance on how to apply them in the reality and characteristics of Architecture Projects.
Since areas related to procurement, cost, etc. are not different from other projects, they are not
detailed in this Guide.

Architecture Project Start-Up
The first step of Phase A of the ADM cycle is defined in the TOGAF standard, Phase A:
Establish the Architecture Project. The chapter is very concise and refers the reader to other
sources, by stating: “execution of ADM cycles should be conducted within the Project
Management framework of the enterprise”. It does not detail steps to be undertaken at the very
beginning of the Architecture Project, but leaves it to the Project Manager and other bodies
within the enterprise to decide on what has to be done based on their experience and a set of
organizational standards.
According to PRINCE2 to ADM Mapping (Chapter 4), the ADM step Establish the Architecture
Project can be mapped to the PRINCE2 Starting up a Project process. PMBOK, due to its
different nature, does not provide such elaborate systematic processes, nevertheless its Develop
Project Charter process can be mapped to this TOGAF step as well (see PMBOK to ADM
Mapping, Chapter 5). Therefore, the following activities are necessary for starting up a project:


Appoint the Executive and Project Manager



Capture Previous Lessons



Prepare Outline Business Case



Select the Project Approach



Design and Appoint the Project Management Team



Assemble the Project Brief



Define the Management Approach

The above-mentioned activities form a basis for the following subsections.

3.1.1

Appoint the Executive
The project should be a response to an identified business need, as its execution is connected
with tangible and usually quantifiable costs for the organization, in the form of, for example,
cash expenditure, man-hours of employees, and even disruptions in normal operations. The
project can only be executed when there are necessary resources provided, usually on the
assumption that they will achieve some business goal and provide sufficient return in some form
(like business benefits, ability to continue operations, etc.).

Architecture Project Management

17

There are multiple possible benefits of Architecture Projects; for example:


A more efficient operation



Better return on existing investment



Reduced risk for future investment



Faster, simpler, and cheaper procurement



Improved ability to respond to threats and opportunities identified from a context
analysis, as well as competitor pressure, through design of new business models and
identification of new business lines



Improved customer experience through different channels

Example

which all stem from having good, thoroughly planned Enterprise Architecture (or, at the very
least, are facilitated by it) or undertaking architectural efforts. In other cases, Architecture
Projects are enablers of other initiatives, projects, and programs, and do not deliver value on
their own, or are just necessarily grounded in external factors (like compliance with
regulatory requirements).

The Executive is the owner of the project’s business goal, and therefore an incarnation of
organizational support for the initiative at hand, responsible for realization of expected benefits.
Depending on the organization (especially its Project Management framework) and the project
itself (its type), the Executive can have different names and structures. The term was originally
taken from the PRINCE2 method, where it is the name of the role representing the “Customer”,
who is the ultimate resource provider for the project.11 A very similar role, though more limited,
is played by the “Sponsor” in PMBOK. The same is the case with the TOGAF standard, where
the Executive is responsible for ensuring “on-time, on-budget delivery of a change initiative that
will realize expected benefits for the organization”.12
The TOGAF standard does not elaborate on the Executive much. It is named as a stakeholder
organizational role, which can be played by, for example, a sponsor or program manager. It
defines the necessary skill set (see the TOGAF standard, Part VI: Architecture Skills Framework
(Goals/Rationale)) in its skills framework, provides information on the sponsorship of the initial
Enterprise Architecture effort (namely that it is usually a CIO or other Executive), names the
sponsor of the architecture (Architecture Board), as well as the “sponsor of sponsors” (Executive
sponsor from the highest level of the corporation).
As pointed out earlier, there can be no project without an Executive, who provides the necessary
resources for the project’s execution and represents the need to be addressed. The Executive is
the person that appoints the Project Manager and tasks them with Architecture Project execution
at the operational level.

11

The two can be, of course, the same person.

12

See the TOGAF standard, Part III: Stakeholder Management (Template Stakeholder Map).

18

TOGAF® Series Guide (2018)

Examples of Architecture Project Executives are:
Overall Goal

Example

CIO
(B) Improve logistics process Determine and design
efficiency and shorten time- possible improvements in
to-order
the business processes in the
area of logistics
(E) Implement new data
warehouse and management
information system to
address expanding bank
reporting needs

3.1.2

Architecture Project
Architecture Project Goal Executive

Enable efficient and
successful implementation
of the solution

Program Manager, responsible
for Management Information
System transformation program

Appoint the Project Manager
As stated in the Appoint the Executive step above, the Project Manager is appointed by the
Executive to lead the Architecture Project on the operational level.
A Project Manager is a person responsible for ensuring that the project delivers the required
product that satisfies the stakeholders’ needs. Therefore, a Project Manager must have strong
leadership, communication, and negotiation skills in order to lead the stakeholders to the
project’s successful outcome.



According to PRINCE2, the Project Manager is a person given the authority and
responsibility to manage the project on a day-to-day basis to deliver the required products
with the constraints agreed with the Project Board. The Project Manager’s prime
responsibility is to ensure that the project produces the required products within the specified
tolerances of time, cost, quality, scope, risk, and benefits. The Project Manager is also
responsible for the project delivering a result capable of achieving the benefits defined in the
business case.13
According to PMBOK, the Project Manager is a person assigned by the performing
organization to lead the team that is responsible for achieving the project objectives. In
general, Project Managers have the responsibility to satisfy the needs: task needs, team needs,
and individual needs.14

A common question is: who should be an Architecture Project Manager? Project Management
methods advocate assigning such a role to a Project Management professional.
The TOGAF standard does not answer this question, but its Architecture Skills Framework 15
provides an assessment of the skills required to deliver a successful Enterprise Architecture.
According to the framework, the Enterprise Architect is responsible for ensuring the
completeness (fitness-for-purpose) of the architecture, in terms of adequately addressing all the
pertinent concerns of its stakeholders; and the integrity of the architecture, in terms of
connecting all the various views to each other, satisfactorily reconciling the conflicting concerns
13

Managing Successful Projects with PRINCE2, Section C.5 (Project Manager).

14

Guide to the PMBOK, Section 1.7 (Role of the Project Manager).

15

The TOGAF standard, Part VI: Architecture Skills Framework.

Architecture Project Management

19

of different stakeholders, and showing the trade-offs made. Therefore, for most Architecture
Projects, the role of an Enterprise Architect satisfies the definition of the Project Manager. In
addition, excellent communication with stakeholders required from the Enterprise Architect
lowers the need to designate a dedicated Project Manager that is typical for IT projects.
However, in some cases there may be a need to delegate Architecture Project Management and
control to a dedicated Project Manager. The decision to include a dedicated Project Manager in
an Architecture Project will depend on the Project Management rules and principles adopted in
the organization, the scale of the Architecture Project, the number of internal entities and
external suppliers involved in the project, the number of project streams, its timeframe, etc. You
may find that the Architecture Project is so complex that combining an Enterprise Architect role
with the Project Manager role may not be effective because the workload connected with
managing and controlling the project according to the organization’s Project Management rules
and principles limits the Enterprise Architect to focus on core architecture work.
In Project B, an Enterprise Architect served as a Project Manager. This was possible due to
the low complexity of the project – it covered only one business domain, engaged people
from three business units, and five to ten IT systems. Moreover, the Project Management
rules and principles adopted in the organization were focused only on reporting issues and
risks associated with delivering the project within the specified tolerances of time and cost.
Example In Project D, there was a need to include a dedicated Project Manager due to the complexity
of the project – it consisted of five work streams (architecture was one of them) whose
products were inter-dependent, covered over 25 IT systems, and engaged over 50 people from
various business units. The Enterprise Architect was responsible for managing the work in the
architecture stream and reporting its status to the Project Manager who was, among others,
responsible for consolidating status reports from all streams and presenting an overall status
of the project to its stakeholders on a weekly basis.

In the rest of this Guide, we use “Project Manager” for a role responsible for the execution of the
Architecture Project. This role can be assigned to an Enterprise Architect or to a Project
Management professional, as discussed above.

3.1.3

Capture Previous Lessons
One of the first things the Project Manager is expected to do after being appointed, as per the
PRINCE2 method, is preparation of a Lessons Log.16 This document should function as an
informal repository of knowledge about the current project. At the very beginning, it should be
completed with all relevant information available about similar projects, including key
information from previous projects’ Lessons Logs (or Lessons Reports, if these exist) and other
relevant documentation, experiences of people involved in such endeavors, and all other
potential sources of knowledge (in case of Architecture Projects, the input should be obtained,
among other sources, from the lessons learned documented in Phase F.17) It enables the Project
Manager to gain better insight into the nature of the project and better prepare and execute the
project by avoiding mistakes made previously by others and using developed know-how.

16

In this Guide we refer to the Lessons Log as a repository filled continuously during the project, as opposed to Lessons Learned or a
Lessons Report, which are the documents concluding the project and containing only the most important information.
17

The TOGAF standard, Phase F (Complete the Architecture Development Cycle and Document Lessons Learned) and Phase H
(Drivers for Change).

20

TOGAF® Series Guide (2018)

The document should undergo regular updates when it should be filled in with additional
information acquired as well as developed good and best practices, which will support the
Project Manager in his duties on this and other projects.
The level of detail in this document should be adequate to the requirements of the project (its
scale and complexity) and compliant with the internal regulations of the particular organization.
There is no need to create sophisticated Lessons Logs for small projects. In some cases even a
bullet list, containing the most important observations, might be sufficient.
The Project Manager has been appointed to manage the project focusing on the architecture
design and implementation of a new Data Warehouse and Management Information System
(Project E). As a first step, the Project Manager gathered information about the project at
hand and interviewed the Sponsor.
In order to ensure integrity, completeness, and constant availability of potentially useful
information, he created the Lessons Log, where he intended to put all the information he
considered useful at the beginning, and where he will include all the insights gained during
Example the project execution. As it turned out, there was another project executed in the company,
which resembled the current project in scope and budget and ended in failure due to not being
completed in the estimated time. The documented reason for that was tasking the main
architect with Project Management duties, which proved to be too much to handle for one
person in this project type and set-up. The Project Manager included the note in the Lessons
Log: “In projects with such scope, the Project Management and Enterprise Architecture duties
should be separated; otherwise, there is a risk of neither of these functions being executed
properly due to the excessive workload.”

3.1.4

Prepare Outline Business Case
Simultaneously, the PRINCE2 method expects the preparation of an outline business case, which
will be an integral part of the Project Brief, providing information on expected costs, risks, and
benefits of the project. The outline business case is an attempt at providing quantitative and
qualitative assessment of the project, enabling the decision-makers (i.e., the Executive or similar
body) to make a more informed choice about whether the project is feasible and beneficial, and
whether it is the best project to undertake from the whole portfolio of project ideas.
The document is a responsibility of the Executive, though it does not mean that they prepare it.
This task might be delegated to, for example, business analysts or the Project Manager.
This document should become more detailed later on, as additional planning efforts are
conducted, and should be regularly verified and continuously maintained to provide the current
state of knowledge about all factors that might affect the outcome of the project. This constitutes
a basis for strategic decisions regarding the project, including a decision on whether the
continuing project is still beneficial, feasible, and needed (see Execute, Monitor, and Control a
Stage, Section 3.4). After the completion of the project, the business case should also be
confirmed, to see whether the forecasts regarding benefits were correct (see Architecture Project
Closing, Section 3.6).

Architecture Project Management

21

The Project Manager has been tasked with creating the business case for Project C
(Consolidate IT environment of recently merged businesses). The newly created IT
environment is largely redundant, allowing for a significant reduction of IT costs through
application and infrastructure consolidation. Possible savings are estimated at 20-50M EUR
yearly. The Architecture Project that will define the target model and consolidation roadmap
is estimated to involve four FTE of Enterprise Architects and eight FTE of other staff for six
Example months (total cost of 0.5M EUR including expected risk materialization costs). The resulting
roadmap implementation is estimated to cost between 40M and 100M EUR.
The Project Manager has documented these preliminary findings in an outline business case
and communicated them to the Executive, mentioning that these require further analysis, but
the project looks promising and should be, in his opinion, continued, at least until a more
precise cost benefit analysis can be prepared based on Architecture Project findings.

3.1.5

Select the Project Approach
PRINCE2 expects the Project Manager to select the approach to project execution. Decisions to
be made mentioned by the PRINCE2 method are, among others: what resources to use (internal
or external), whether to build a solution from scratch or modify existing solutions, or whether to
base it on a Commercial Off-The-Shelf (COTS) solution, or create a tailor-made one.
In the case of Architecture Projects, only the first decision is relevant. However, from the
perspective of Architecture Project Management, the approach should be understood more
broadly: what methods and frameworks should be used to manage the Architecture Project and
how to plan the project.
The choice of methods and frameworks used in the Architecture Project Management should
stem from the characteristics of the problem the project aims to solve and be connected with the
adopted planning approach. Since the area of Architecture Project Management is a composite of
Project Management and Enterprise Architecture fields, decisions should be made regarding
tools used in each of these domains.
1. Choosing the Resources to Use

From our experience, the decision on whether to use internal or external resources should be
made taking into consideration at least the following:

22



Estimated complexity of the project and amount of work needed



Time and budget constraints



Necessary skills – note that knowledge of the existing architecture may be highly relevant;
cost of obtaining it (i.e., current state analysis) should be carefully considered for external
consultants



Available resources inside the organization



Previous experiences and organizational guidelines

TOGAF® Series Guide (2018)

The Project Manager tasked with managing Project E has concluded that due to broad
estimated scope, high complexity, and difficulty of the project, as well as strict time
constraints resulting from legal obligations of the bank, the project requires multiple
architects with high competency in the data domain. The resources at hand were assessed as
Example insufficient and there was neither possibility to recruit more people in time, nor to train the
available architects to the adequate skill level.
The Project Manager has decided to approach the project using external resources by
engaging a group of architects from the consulting firm, with which the bank has a
longstanding, positive relationship and has successfully completed other projects.

2. Choosing a Planning Approach

The decisions regarding planning approach and methods/frameworks are inter-dependent, as
each may influence the other. The TOGAF standard advocates an iterative approach with
iterations repeated until the product achieves the expected quality and consistency, which many
people equate with the agile approach and methods. This is not the case, and there is no
fundamental contradiction between the proposed approach and the waterfall methods.
Nevertheless, it might require tailoring of the TOGAF framework to fit within the constraints of
the Project Management methods and particular projects. For more information on how to plan
the project, with particular focus on dividing it into stages, refer to Architecture Project Planning
(Section 3.2) and Planning a Stage (Section 3.3).
3. Choosing a Method

Useful in the case of choosing the best approach (from the Project Management method
viewpoint) to the particular problem could be the Cynefin Framework. It divides the so-called
problem domain into four main categories: complex, complicated, obvious (simple), and
chaotic.18 Depending on the category of the problem, different methods are recommended, due
to them being best suited for different circumstances as they have different strengths and
weaknesses. In our experience, the following methods are recommended for particular problem
categories:


Complex – SCRUM method, specifically designed to deal with a high level of volatility
and uncertainty



Complicated – e.g., Kanban and SCRUM methods, as the category covers sophisticated
problems, requiring careful analysis, highly expert knowledge to solve, and some amount
of probing different solutions, as there is no one best solution



Obvious (simple) – all of the waterfall approaches, as the category covers known
problems and has best practices prepared, enabling use of a carefully preplanned approach



Chaotic –no method recommended, due to complete unpredictability of the systems’
behavior

Problems in the area of Enterprise Architecture tend to fulfill the criteria for simple and
complicated categories, especially when architecture is already present in the organization, as it
aims at increasing the level of order and predictability. The cause-and-effect relationships are
18

There is multitude of resources on this framework on the Internet, covering different applications. However, the clou is the same
everywhere. We would like to restrain from recommending any particular resource.

Architecture Project Management

23

present and possible to discern, and the only case in which the problems might become complex
or chaotic is high volatility of the environment (usually combined with lack of knowledge about
the organization at hand and its exterior). To which domain a particular problem belongs
depends, inter alia, on the expertise in the organization, its architecture maturity, scope of the
project, and additional constraints imposed. The task to classify the problem is up to the Project
Manager.
4. Choosing an Enterprise Architecture Framework

In the area of Enterprise Architecture, the choice to be made is between one of different
architecture frameworks. There are at least a few different major frameworks which provide
tools and resources for Enterprise Architects (including the Zachman Framework and the Federal
Enterprise Architecture (FEA)). However, not all of them are useful in the case of Architecture
Project Management. This is the consequence of the different focus of each of the frameworks.
As Architecture Project Management is, in fact, a process of creating an architecture, only the
frameworks which provide methods of creating architectures should be taken into consideration.
This is where the TOGAF framework, as compared to other frameworks, excels, thanks to its
detailed description of the ADM.
In Project A, the Project Manager has no clear understanding what views are necessary to
achieve the goals of the project, making it a complicated problem. He therefore has decided to
include on “overview” stage at the beginning, enabling him to determine scope, which will
allow completion of the project in the set timeframe and with set resources. After the
thorough analysis of two applications during this phase, he confirmed with the Executive
what is feasible to do in the following stages and will address the existing business need of
the Executive. Later on, the Project Manager has decided to adopt an iterative approach by
splitting the 50 applications used into groups of eight, which will be assessed in every twoweek iteration.
Example In Project E, the Project Manager has to deliver precisely described artifacts and products to a
set date, making the problem a simple one, assuming the presence of necessary resources.
Failure to do so will result in potentially costly delays in the project, including fines for not
complying with regulatory requirements, as the architecture stream is on the critical path.
Therefore, the Project Manager has adopted the preplanned approach with time-bound stages
with some buffer, focusing initially on the baseline (baseline first approach). This plan has
been assessed as feasible by the external consulting experts involved in the project, who have
participated in similar projects in the past. Nevertheless, the risk has been assessed and
communicated, and its significant part has been transferred to the consulting firm in the form
of additional provisions in the contract.

In this Guide we assume the Architecture Projects are conducted according to the TOGAF
framework, supplemented with practices stemming from the most popular Project Management
methods.

3.1.6

Design and Appoint the Project Management Team
Project Managers of Architecture Projects do not operate in a void and do not deliver products
singlehandedly. They use support provided by other institutions within an enterprise and are
regulated by them in order to ensure that the goals of the organization are met. They are part of
the team, working together to deliver the products and realize the benefits for the organization.
In PRINCE2, they are part of a Project Management Team, which provides them with oversight
and support. These Project Management Teams are the whole Project Management structure

24

TOGAF® Series Guide (2018)

comprising bodies responsible for governance,19 management, and support. There are also
Project Management Teams in PMBOK, but, in comparison to PRINCE2, they are limited to
Project Management and leadership activities, and do not include governance bodies (they only
cooperate with them).

Figure 5: Simplified Chart Representing Model Project Team Based on the PRINCE2 Method
1. Governance in Architecture Projects

The bodies which are responsible for successful delivery of the product should naturally be the
ones most interested in “ensuring that the business is conducted properly” (which is the most
general definition of governance, found also in the TOGAF standard). This is exactly the case:
the governing body in the case of PMBOK is the Sponsor, in PRINCE2 it is the Steering
Committee, led by an Executive (who is the ultimate decision-maker, only advised by optional
representatives of users and suppliers), and in the TOGAF standard it is the Architecture Board
(which is a sponsor of architecture in an enterprise).
It is necessary to bear in mind, though, that there is a difference in the type of governance
provided by the Architecture Board (i.e., Architecture Governance) and the other two bodies
mentioned (i.e., Project Governance). Architecture Governance is the practice and orientation by
which Enterprise Architectures and other architectures are managed and controlled at an
enterprise-wide level, while Project Governance (according to PMBOK) is an “oversight
function that is aligned with the organization’s governance model and that encompasses the
project lifecycle … providing a comprehensive, consistent method of controlling the project and
ensuring its success”. As a result, Architecture Projects should be subject to both types of
governance, first allowing to provide alignment with strategic architecture and sub-architectures,
second to ensure that the project delivers expected results in terms of quality, budget, and time.
Does this mean that the Project Manager on the Architecture Project should be overseen by two
different bodies? Often yes. However, it depends on the Project Management and Enterprise
Architecture organization. Is the architecture governance body (such as the Architecture Board)
19

Since we are discussing Architecture Project Management, the governance of the project is two-fold – both architecture governance
and project governance are applicable.

Architecture Project Management

25

already established in the organization? If it is, can the architecture governance body take the
role of project governance as well? If it is not and the project is the organization’s initial
Enterprise Architecture effort, can the Steering Committee transform into an Architecture Board
after the project is completed? There are many possibilities and the approach should be different
depending on project and organization characteristics.
The Project Manager has been tasked with managing Project B (improve logistics process).
The project is sponsored by the CIO of the company, who has been tasked by the business to
provide current information to allow for better planning and resource allocation, to shorten
order-to-delivery time as an end result. The CIO presides over the Architecture Board, which
also includes some leaders of business units involved in the company’s logistics process.
Example

The CIO decided there is no need to set up additional bodies to provide project governance,
as most of the key stakeholders are already part of the body providing architecture
governance. There are no inter-dependencies or planned follow-ups at the moment, and all
decisions will be made on the basis of its outcome.
As a result, the Project Manager turns to the Architecture Board and CIO in particular to
provide not only architecture governance, but also project governance as a Sponsor of the
project, and, if possible, to include the rest of the affected business leaders on the Board.

The Project Manager has been ordered to lead Project E, aiming to design the to-be
architecture in a bank, which includes new data warehouse and management information
systems. The Architecture Project is part of a larger program of new solution implementation,
making architecture effort only one of multiple streams, which are closely related and
dependent on each other. This is especially true for the Architecture Project, which functions
as an enabler for further work. The project has been initiated by the Program Management of
Example the whole information system transformation initiative, which is not in any way connected
with the Architecture Board. It is strictly bound by budget, timeframe, and scope, requiring
strict adherence to the plans and requirements.
The Project Manager is responsible in this case to the Program Management, while
simultaneously has to adhere to the rules and constraints imposed by the Architecture Board
in the organization. Depending on the type of issue, whether it is connected with architecture,
or Project Management and execution, he is obliged to follow different escalation routes.
2. Project Manager’s Support in Architecture Projects

Sometimes, Architecture Projects are too big and complex for a single Project Manager to
undertake and manage, even with support provided from the enterprise leadership. Furthermore,
some projects may require specific skills and competencies, which are not possessed by the
Project Manager designated to lead the project. This creates the need for additional people, other
than those in the Architecture Board or other governing body, who ultimately become the core of
the Project Management Team.
The TOGAF standard describes the roles that are usually part of an “architecture team” in Part
VI, Architecture Skills Framework: Enterprise Architecture Role and Skill Categories, and
Enterprise Architecture Role and Skill Definitions. These include both roles responsible for
governing the architecture and supporting the project and roles responsible for operational
management and delivery (architects for different domains and solution designers). These roles
are part of the Architecture Capability Framework and are separate from the structure of a
Project Management Team. The TOGAF standard does not describe how the Project

26

TOGAF® Series Guide (2018)

Management Team supporting the project should be staffed or organized. However, some hints
are provided in the Project Management methods.
PMBOK provides general information about Project Teams20 in Section 2.3 and hardly any
regarding Project Management Team (a subset of Project Team responsible for the Project
Management and leadership activities). It says that the only constant with regards to the Project
Team is Project Manager’s role as its leader, giving a lot of freedom to the Project Manager.
Among the factors which should be considered while devising the Project Team structure,
PMBOK mentions culture, scope, location, and organizational structure. It does not provide
guidelines on how it should be organized, other than giving information on some of possible
roles within the Project Team (for more information, see Section 2.3 of the PMBOK Guide) and
tools supporting the Project Manager’s decision-making and management processes (see Chapter
9 of the PMBOK Guide).
PRINCE2 is more specific and points out team managers, who are people responsible for
delivery of products assigned by the Project Manager, as defined in the Project Work Packages
later on (for more information on Project Work Packages and Work Packages see Architecture
Project Management Concepts, Section 2.3) and people being part of Project Support (usually as
part of the Project Management Office), whose duties are limited to support in administration
and operations and providing guidance regarding Project Management tools and techniques).
The decision on whether to appoint team managers, how to define their roles and duties, is
entirely up to the Project Manager (but this decision should be approved by the bodies providing
project governance), but shouldn't be made without serious consideration, as it impacts how the
work will be divided during the project. The factors, which should be considered are, among
others:


Estimated scope of the project, with regard to both domains and segments, that will be
affected by the project



Project constraints, especially with regard to timeframe



Size of the team involved

Based on what we know about Architecture Projects and having a general knowledge of Project
Management methods, it is possible to propose at least two ways of selecting team managers:


By architecture domain, where particular team managers are architects responsible for
either business, data, application, or technology architecture



By enterprise continuum level, where particular team managers are architects responsible
for different segments or solutions, which are affected by the project (however, we
recommend that the Architecture Project has a clear scope restricted to one of the levels:
strategic, segment, or capability)

20

This term is used in the PMBOK to describe the “Project Manager and the group of individuals who act together in performing the
work of the project to achieve its objectives”. As mentioned earlier, this term differs from the Project Management Team used in
PRINCE2, because it does not include the body providing oversight (herein called the Project Owner), as opposed to the Project
Management Team, but includes all the operational people – something which is not covered in the other method.

Architecture Project Management

27

In Project E, architecture is just one of work streams of a large project. The architecture work
stream can use a general Project Support team (PMO) for administrative tasks such as setting
Example
up meetings or managing the work stream repository. Therefore, the architecture work stream
leader decided he would not need any separate support staff.

The team structure is established in the Project Start-up stage. However, after the initial stages of
the project, the Project Team structure should be reviewed and may be adapted to changing
needs.
3. Delivery Team in Architecture Projects

The last group (but no less important than those mentioned earlier) are people engaged in
operational execution by working on project deliverables. They are organized in teams, managed
by the Project Manager directly or team-level managers, depending on the Project Management
structure in a particular project.
Selection of people to be involved in the project is critical to its success. It depends mainly on
the goals and scope of the Architecture Project, and the resources available. The TOGAF
Architecture Skills Framework can be helpful in planning and selecting delivery team members.
More general techniques in this area are described in the PMBOK Guide, Chapter 9.
In Project B, the delivery team was selected among available resources. The aim was to
ensure the team has skills strong enough to cover each of the business subunits with a single
workshop. This required careful planning and the right mix of skills and knowledge of current
information flows and systems within the team.
The delivery team consisted of:


Enterprise Architect – who was also the Project Manager; responsible for planning the
project, engaging stakeholders, preparing templates, reviewing work products, and
preparing final deliverables; would also take an active part in business workshops to
ensure they are fit-for-purpose



Business Process Analyst – who would facilitate business workshops and document their
results in line with the approach developed with the Enterprise Architect



Logistics Information Systems Architect – who would take an active part in business
workshops and provide knowledge on the current IT systems capabilities and their
development potential

Example

3.1.7

Assemble the Project Brief
According to PRINCE2 and PMBOK, the project becomes authorized when a document
summarizing the project’s assumptions is assembled and approved. At minimum, the document
should define the high-level boundaries of the project.

28

TOGAF® Series Guide (2018)

According to PRINCE2, the Project Brief is a statement that describes the purpose, cost, time,
and performance requirements, and constraints for a project.21


According to PMBOK, the project becomes authorized when the Project Charter is approved.
The Project Charter documents the business needs, assumptions, constraints, the
understanding of the customer’s needs and high-level requirements, and the new product,
service, or result that it is intended to satisfy.

The document is issued by the Executive that formally authorizes the existence of a project and
provides the Project Manager with the authority to apply organizational resources to project
activities. It is recommended that the Project Manager participates in the development of the
Project Charter to obtain a foundational understanding of the project requirements. This
understanding will better allow for efficient resources allocation to project activities.
The information from the document is relevant for the Project Manager to plan key milestones, a
detailed schedule, as well as key resources essential to perform particular tasks in the planning
phase. They are also important at the end of the project in order to verify whether the project
delivered the desired results within the specified tolerances of time, cost, quality, and scope. The
information included in the document may be updated along with the progress of work in the
planning phase.
The type and scope of the information needed at the beginning of an Architecture Project, as
well as documents that they will be included in, depends on the Project Management rules and
principles adopted in the organization conducting the project.
In Project D, the Project Manager utilized the information presented in the Project Brief to
develop a kick-off presentation and conduct a meeting informing key stakeholders of the
Example Architecture Project about its scope, business needs to be addressed, as well as imposed
constraints. Furthermore, the information was utilized by the Project Manager to plan key
milestones and develop a detailed schedule for the Architecture Project.

3.1.8

Define the Management Approach
After initial project start-up – selecting the project approach and appointing the Project
Management Team – the Project Manager determines how the project will be managed. In
PRINCE2, it is called preparing a Management Strategy. In PMBOK, it is a part of the Develop
Project Charter process.
The Define the Management Approach step includes determining an approach to:

21



Risk management



Quality management



Stakeholder and communication management



Project controls

See the PRINCE2 Glossary of Terms.

Architecture Project Management

29

1. Risk Management Approach

As part of project initiation, the Project Manager determines the risk management approach and
confirms it with the project governance body. Typically, an approach to risk management
includes the following steps:


Risk identification and classification



Risk analysis (qualitative and quantitative)



Risk mitigation and response strategy design



Risk monitoring

The Project Manager also performs an initial risk assessment, which includes risk identification,
classification, analysis, and design at the beginning of the project. The key result of this activity
is a risk log, which documents identified risks and their characteristics together with designed
responses. The risk log will be used throughout the project to monitor and manage risk; see
Execute, Monitor, and Control a Stage (Section 3.4) for details.
For more information on project risk management techniques, refer to the PMBOK Guide,
Chapter 11.
In Project E, initial risk assessment is performed first on a work stream level, then on the
project level (the project consists of a few work streams). In the architecture work stream,
initial risk assessment is performed on a deliverable level, then consolidated and extended on
Example the work stream level.
For a risk log example, refer to the example in Capture and Examine Issues and Risks, in
Section 3.4.5.



Risk management from the Project Management perspective is concerned with risks to
meeting projects goals. Please note that the Architecture Project has to deal with another key
type of risk – risk to the enterprise associated with the Architecture Vision and related to
implementing it. This type of risk – we can call it “architecture risk” – has to be managed and
mitigated. Techniques of managing architecture risk are similar to that applied to project risk;
they are described in the TOGAF standard, Part III: Risk Management.

2. Quality Management Approach

As part of project initiation, the Project Manager determines the quality management approach
and confirms it with the project governance body. The quality management approach should be
compatible with the organization’s quality management system. Typically, it should establish:

30



Key quality characteristics of the project deliverables – conditions that would be used to
assess conformance when the deliverable is handed over



Documentation requirements – how these quality characteristics would be documented to
allow for conformance checks



Quality assurance processes – how these quality characteristics would be checked for
conformance (before and on deliverable handover)

TOGAF® Series Guide (2018)

The quality management approach will be used throughout the project. Established criteria are
key for stage and project closing activities (see Ending a Stage, Section 3.5, and Architecture
Project Closing, Section 3.6).
For more information on project quality management techniques, refer to the PMBOK Guide,
Chapter 8.
In Project E, each of the project deliverables is described with a Deliverable Charter. The
Deliverable Charter defines the deliverable name, its scope, required inputs, acceptance
criteria, and acceptance process. Two types of acceptance processes are designed – one for
documentation deliverables (analysis, architecture, etc.) and one for software deliverables
which includes the system testing approach.
Example The document acceptance process consists of five steps: initial hand over of the deliverable,
initial deliverable review (two weeks), review meeting (one day), deliverable revision (two
weeks), final deliverable review (one week). It is assumed that the final deliverable review
confirms the deliverable’s conformance to quality requirements.
Acceptance processes and Deliverable Charters are discussed and accepted by the project
governing body.

3. Stakeholder and Communication Management Approach

TOGAF ADM Phase A includes stakeholder identification and determining an approach to
stakeholder communication. It is one of the core activities that the Project Manager has to assure
during the Architecture Project initiation.
Specifically, the Project Manager should:


Identify all stakeholders and their concerns about the resulting Enterprise Architecture



Determine the stakeholder communication management approach



Determine the stakeholder engagement deliverables



Document all the above information in a form of stakeholder map and communication
plan

The TOGAF stakeholder management technique fulfils needs related to the proper stakeholder
management approach. This technique is described in the TOGAF standard, Part III: Stakeholder
Management. PMBOK uses a similar approach, which is described in Project Stakeholder
Management (Chapter 13).
In Project A, during initiation of the project and Phase A of the ADM, the Project Manager
uses the approach described in the TOGAF standard to manage stakeholders. At first he
identified the stakeholders, then he grouped the stakeholders with common concerns into
stakeholder groups (e.g., C-level management, IT operations), then he defined the stakeholder
communication approach using the power-interest matrix. He defined for each of four groups
Example
how and how often the Project Team would communicate with each of the four groups. (e.g.,
the stakeholders with low level of interest and low power receive only the weakly project
brief on their emails). At the end, the Project Manager defined the stakeholder engagement
deliverables and created the stakeholder map matrix. He added this matrix to the project
communication plan.

Architecture Project Management

31

The output deliverables stakeholder maps and communication plans are used by the Project
Manager during project execution and control. The stakeholder map is also the important source
of knowledge about engagement deliverables (catalogs, matrices diagrams) for Enterprise
Architects that participate in the project.
4. Project Controls Approach

Project controls define the level of control that is demanded to ensure proper project execution
and the effectiveness of Project Management. Project controls should be defined during
initiation of the project.
PRINCE2 defines the project controls as:22


The frequency and format of communication between the Project Management levels



The number of stages and hence end stage assessments



Mechanisms to capture and analyze issues and changes



Mechanisms to escalate exceptions



Tolerances for delegated authority



How delegated authority from one level of management to another will be monitored

Project controls should be defined as part of the management approach. They are executed
throughout the project (see Execute, Monitor, and Control a Stage, Section 3.4).
During the initiation of Project A, the Project Manager defined several project controls:


He set up weakly status report meetings for the Architecture Project Team.



He decided to divide the analyzed applications to tree packages and assign the
responsible application architect for each package.



He stated that all issues will be registered in a shared issue log and all changes will be
registered in a shared change log in the form of Excel® spreadsheets in the project
intranet repository.

Example

3.2

Architecture Project Planning
Project planning is about defining and splitting the project’s scope into manageable tasks with a
defined schedule and quality criteria. Arguably, it is the most important task of the Project
Manager at the project start. According to PRINCE2, a plan is necessary to control anything –
and we agree with regard to Architecture Projects.
TOGAF ADM Phase A ends with development and approval of the Statement of Architecture
Work, which includes a “project plan and schedule”. It does not go into detail and omits a
planning techniques description. In this Guide, we recommend a sequence of activities that
allows creation of a schedule and includes it in the Statement of Architecture Work.

22

Managing Successful Projects with PRINCE2.

32

TOGAF® Series Guide (2018)

We recommend the following sequence of activities to develop the Architecture Project schedule
and Statement of Architecture Work:


Define the Architecture Project Scope



Define the Final Product of the Architecture Project and its Acceptance Criteria



Define the Project Deliverables



Define the Project Exclusions, Constraints, and Assumptions



Detail the Architecture Project Scope



Create the Work Breakdown Structure



Develop the Architecture Project Plan and Schedule (sequence activities, estimate activity
resources and durations, develop schedule)



Consolidate the Statement of Architecture Work and Secure Approval

These activities are described in the following subsections.
In the TOGAF standard, there are quite a few essential (non-management) work products
delivered throughout Phase A. These work products can have a great impact on the Architecture
Project Scope and should be completed before working on the Work Breakdown Structure and
Project Plan. They include:


Evaluate Capabilities and Assess Readiness for Business Transformation – project
planning should be based on this preliminary assessment of change complexity and
readiness for change



Confirm and Elaborate Architecture Principles, including Business Principles – project
planning should take into account Architecture Principles



Develop Architecture Vision – project planning should be based on baseline and target
architectures outlined in the Architecture Vision



Define the Target Architecture Value Propositions and KPIs and Identify the Business
Transformation Risks and Mitigation Activities – while not directly related to Project
Scope, some of the value propositions and business transformation risk mitigation
activities may impact the Project Scope and should be taken into account in project
planning

The above work products can have a great impact on the Architecture Project Scope and should
be completed before working on the Work Breakdown Structure and Project Plan. These work
products are wide in scope, but they are usually produced at a very high level, to allow just
enough information to plan further work and get to a more detailed level.

3.2.1

Define the Architecture Project Scope
Defining the Architecture Project and its scope is the most important activity which should be
performed with great care and awareness. The output of this activity will have significant impact
on the understanding and achievement of the project’s goals.

Architecture Project Management

33



Note that the definition of an Architecture Project Scope is broader than described in the
Define Scope step of the TOGAF ADM Phase A. The Define Scope ADM step describes what
is in the scope of the Baseline Architecture and Target Architecture efforts. The Architecture
Project Scope, in line with the Project Management methods, means the scope of work which
is to be performed in order to achieve the project’s goals. Of course, performing the Define
Scope ADM step is a critical initial task to understand and define the Architecture Project
Scope.

The scope of the Architecture Project should be defined using the ADM scope definition
activities and other essential Phase A outputs, such as the Architecture Vision (see the list in
Architecture Project Planning, Section 3.2). According to the TOGAF standard, it is critical to
define what level of the Architecture Landscape, breadth and time will be covered (as shown in
Figure 2).23
The Project Management methods provide tools and techniques which too can be used during
definition of the detailed Project Scope and Project Plan; the most important of them are
presented in the following subsections.
As part of the scope definition, a summary Architecture Project Description should be created.
The Architecture Project Description is a short summary of the work that will be performed
under the project along with the project’s goals. All outputs from the above ADM tasks should
be gathered and analyzed together in order to prepare the Project Scope Statement that is the
description of the scope, major deliverables, assumptions, and constraints.
In Project A, after completion of the essential tasks from the ADM Phase A, the Project
Manager had enough knowledge to prepare a description of the Architecture Project. He
decided to start by defining the main goal of the project and came up with the following:
Assess current application portfolio and recommend improvement options.
After that, he defined the main goal, he prepared a more detailed description of the
Architecture Project:
Describe the application landscape and identify IT improvement options. There are about 50
Example applications of different scales (precise number to be determined during project execution),
mostly custom-built. Key concerns are:


Determining relationships and data flows between applications



Mapping application capabilities (overlaps and gaps)



Identification of key technological constraints for application development

Required views are to be determined. Improvement options should include initiatives with
assigned priorities.

3.2.2

Define the Final Product of the Architecture Project and its Acceptance
Criteria
The final product of the Architecture Project is the main output resulting from all work that will
be performed during the project realization. Depending on the project goal it may be a document
or a set of related documents that describes the current situation of, for example, the corporate
architecture, results of analysis, recommendations, description of target architecture and
roadmap, etc.

23

The TOGAF standard, Phase A (Define Scope) and Part III: Applying the ADM Across the Architecture Landscape.

34

TOGAF® Series Guide (2018)

In Project A, the Project Manager decided that the final product of the Architecture Project he
Example is managing is: Report summarizing current application portfolio analysis along with key
observations and improvement recommendations.

The acceptance criteria are a set of conditions that must to be met before the final product of the
Architecture Project will be accepted. It is important to involve all projects stakeholders in the
definition of project acceptance criteria in order to avoid any unexpected, mismanaged
expectations at the end of the project.
In Project A, after reviewing all documentation, and after consultation with the Project
Sponsor and other stakeholders, the Project Manager prepared a list of conditions that the
final product should meet in order to gain acceptance. He decided to include both essential
criteria of the final product content as well as technical details of the report itself.
The main final product acceptance criteria are as follows:


The report should be written in Polish and should be prepared in accordance with
company templates.



The precise number of applications that are going to be analyzed is to be determined
during project execution (initially it is 50), but it may not be less than 45.



Relationships and data flows between applications should be prepared in common
notation; e.g., using the ArchiMate® modeling language.

Example

Recommendations for improvement should include a roadmap with all initiatives along with
assigned priorities, estimated cost, and timeframe.

3.2.3

Define the Project Deliverables
Deliverables are unique and verifiable products, results,24 and outputs that are required to be
prepared to complete a project or particular phase of the project. Deliverables may be part of the
final product, any auxiliary products, or Project Management products. The aim of defining the
list of deliverables is to better plan the work and gain their acceptance right after they are
completed rather than at the end of the project. This approach (acceptance of smaller
deliverables) is the best way to reduce the risk of not meeting the expectations at the end of the
project. During this activity it should be defined which of the TOGAF documents should be also
delivered; e.g., Architecture Definition Document, Architecture Requirements Specification,
Implementation and Migration Plan, Architecture Roadmap, etc.

24

PMBOK Guide, 5th Edition.

Architecture Project Management

35

In Project A, the Project Manager prepared a list of deliverables that will be prepared during
execution of the project. He decided to divide the final product into smaller deliverables and
also included additional deliverables that are important to be agreed during the execution of
the project. Moreover, he included management deliverables such as status reports.
Project essential deliverables:

Example



Agreed list of applications that will be subject of the analysis



Agreed list of required views that will be prepared



Relationships and data flows between applications



Mapping application capabilities (overlaps and gaps)



Identification of key technological constraints for application development



Key observations from analysis



Improvement recommendations

Project management products:


Report highlights



End stage report



Risk log



Issue log



Change log

Project final report

3.2.4

Define the Project Exclusions, Constraints, and Assumptions
Project exclusion is a statement saying what is out of scope for the project and it is used to
acknowledge and make stakeholders aware of what is excluded from the project.
Constraint is a statement about the limitations of the project that affect its execution.
Assumption is a statement about facts that are considered to be true.

36

TOGAF® Series Guide (2018)

In Project A, the Project Manager prepared a list of exclusions, constraints, and assumptions
based on the results from previous analysis. Examples are listed below.
Exclusions:


Recommendations for improvement will contain initiatives along with only estimated cost
There will be no RFI process in order to gain more reliable cost data.



The goal of the project is to analyze the current application portfolio along with key
observations and improvement recommendations
The Target IT Architecture is excluded from the Project Scope.



Identification of key constraints for application development will be performed from a
technological perspective
Other perspectives – e.g., knowledge capabilities, human resources, organizational
constraints – are excluded from the Project Scope.

Example

Constraints:


The project is being performed mostly by internal resources, but the maximum five FTEs
can be dedicated to this project



Due to limited budget there is no possibility to subcontract work outside the organization



The final work product should be completed within 22 weeks

Assumptions:

3.2.5



Deliverables will be accepted within five working days after completion



Any change requests affecting Project Scope, budget, or resources will be approved by
the Steering Committee of the project



Management and employees, with the appropriate knowledge, will devote sufficient time
in order to collect the appropriate information and make the necessary decisions

Detail the Architecture Project Scope
The Project Management methods provide tools and techniques which can be used during
definition of the detailed Project Scope and Project Plan.

3.2.6

Create the Work Breakdown Structure
This is the process of subdividing project deliverables and project work into smaller, more
manageable components.25
It should be determined which architecture domains should be developed, to what level of detail,
and which architecture views should be built prior to creating the Work Breakdown Structure,
and the result of this task should be an input to the Work Breakdown Structure.
During this task, the following TOGAF ADM activities should be also performed:


25

Assess work products that are required to be produced against the set of business
performance requirements, ensuring performance metrics are built into the work products,
and specific performance-related work products are available

PMBOK Guide, 5th Edition.

Architecture Project Management

37



Identify new work products that will need to be changed



Provide direction on which existing work products will need to be changed

There are two common tools used to create the Work Breakdown Structure:


Decomposition is a technique used for dividing and subdividing the Project Scope and
project deliverables into smaller, more manageable parts26



Expert Judgment is often used to analyze the information needed to decompose the project
deliverables down into smaller component parts in order to create an effective Work
Breakdown Structure.27

The Work Breakdown Structure is often presented as a diagram that graphically presents the
decomposition of work products.
In Project A, the Project Manager prepared the Work Breakdown Structure of his project
using decomposition techniques. As he had already prepared a detailed list of project
deliverables, he decided to use it as an input. The Work Breakdown Structure diagram
prepared by the Project Manager is presented below:
Assessment of current
application portfolio and
recommend improvement
options

Example

3.2.7

Project management

Relationships and data
flows between
applications

Mapping application
capabilities

Key observations

Improvement
recommendations

Planning

Agree list of
applications

Identification of
overlaps between
aplications

Identification of key
technological
constraints

Identification of
improvement
recommendations

Monitoring &
controlling

Analysis of
relationships
between applications

Identification of
application gaps

Observations from
application
relationship

Identification of
initiatives along with
prioritization

Reporting &
Administration

Analysis of data flow
between applications

Observations from
mapping application
capabilities

Preparation of
initiatives roadmap

Develop the Architecture Project Plan and Schedule
After the detailed scope is defined, the following Project Management tools and techniques can
be used in order to define the Project Plan. During this phase it is recommended to prepare a
schedule; a detailed schedule for each phase should be prepared during the Planning a Stage
activity (see Planning a Stage, Section 3.3).

26

PMBOK Guide, 5th Edition.

27

PMBOK Guide, 5th Edition.

38

TOGAF® Series Guide (2018)

1. Define Activities

This activity is used to identify any specific tasks that need to be executed in order to produce
deliverables.
The key benefit of this process is to break down work packages into activities that provide a
basis for estimating, scheduling, executing, monitoring, and controlling the project work.28
In this process the Project Manager should use the prepared Work Breakdown Structure that
divides deliverables to the lower level; i.e., work packages. In this process work packages are
decomposed into smaller components called activities, that will be later sequenced and
estimated.
It should be clarified that in terms of the Project Management methods, the definition of “work
packages” has a different meaning to the TOGAF standard (e.g., in the ADM Phase E). In order
to avoid ambiguity, later in this chapter we will use term “work packages” defined as in the
previous paragraph.

28

PMBOK Guide, 5th Edition.

Architecture Project Management

39

In Project A, the Project Manager used defined work packages from the Work Breakdown
Structure and decomposed them into activities. The results for relationships and data flows
between application deliverables is presented below.
ID

Activity Name

1

Start of the project

2

Relationships and data flows between applications

2.1

Agree list of applications

2.1.1

Workshop with architecture team to get initial list

2.1.2

Summary of the workshop with architecture team (initial application list)

2.1.3

Workshop with stakeholders to discuss list of applications

2.1.4

Prepare final list of applications

2.1.5

Secure approval of list

2.2

Analysis of relationships between applications

Example 2.2.1

40

Overall analysis of relationships

2.2.2

Detailed analysis of applications

2.2.2.1

1st package of applications

2.2.2.2

2nd package of applications

2.2.2.3

3rd package of applications

2.3

Analysis of data flow between applications

2.3.1

Overall analysis of data flow

2.3.2

Detailed analysis of applications

2.3.2.1

1st package of applications

2.3.2.2

2nd package of applications

2.3.2.3

3rd package of applications

2.4

Prepare final report from analysis

2.5

Approval of analysis results

TOGAF® Series Guide (2018)

2. Sequence Activities

This activity is used to define all relationships between project activities.
The key benefit of this process is that it defines the logical sequence of work to obtain the
greatest efficiency given all project constraints.29
Please refer to the Project Evaluation and Review Technique (PERT) method which is a
commonly used, network diagram-based technique supporting the process of sequencing tasks.

29

PMBOK Guide, 5th Edition.

Architecture Project Management

41

In Project A, the Project Manager sequenced all defined activities using the Precedence
Diagramming Method. To do this, the Project Manager used a scheduling tool that enabled
him to do it easily. For each activity on the lowest level the Project Manager defined the
preceding activity, so that all of the tasks had defined dependencies which will allow him to
build the schedule. The Results for relationships and data flows between application
deliverables is presented below.

Example

42

ID

Activity Name

Predecessors

1

Start of the project

2

Relationships and data flows between applications

2.1

Agree list of applications

2.1.1

Workshop with architecture team to get initial list

1

2.1.2

Summary of the workshop with architecture team
(initial application list)

2.1.1

2.1.3

Workshop with stakeholders to discuss list of applications

2.1.2

2.1.4

Prepare final list of applications

2.1.3

2.1.5

Secure approval of list

2.1.4

2.2

Analysis of relationships between applications

2.2.1

Overall analysis of relationships

2.2.2

Detailed analysis of applications

2.2.2.1

1st package of applications

2.2.1

2.2.2.2

2nd package of applications

2.2.1

2.2.2.3

3rd package of applications

2.2.1

2.3

Analysis of data flow between applications

2.3.1

Overall analysis of data flow

2.3.2

Detailed analysis of applications

2.3.2.1

1st package of applications

2.3.1;2.2.2.1

2.3.2.2

2nd package of applications

2.3.1;2.2.2.2

2.3.2.3

3rd package of applications

2.3.1;2.2.2.3

2.4

Prepare final report from analysis

2.2[FF];2.3[FF]

2.5

Approval of analysis results

2.4

2.1.5

2.2.1

TOGAF® Series Guide (2018)

3. Estimate Activity Resources and Duration

Each identified activity should be estimated in the context of needed resources (e.g., human
resources, equipment) and duration (time needed to complete the individual activity with
estimated resources).
Refer to PMBOK to gain further information about the following commonly used duration
estimation techniques:30

30



Expert judgment



Analogous estimating



Parametric estimating



Three-point estimating



Group decision-making techniques



Reserve analysis

PMBOK Guide, 5th Edition.

Architecture Project Management

43

In Project A, the Project Manager estimated the necessary resources and duration of each
activity. He also used a common method to make the milestones stand out – they are marked
as 0 days duration.

Example

44

ID

Activity Name

Resource Names Duration

1

Start of the project

PM

2

Relationships and data flows between applications

25 days

2.1

Agree list of applications

10 days

2.1.1

Workshop with architecture team to get initial list

PM IT Architect

1 day

2.1.2

Summary of the workshop with architecture team
(initial application list)

PM; IT Architect

4 days

2.1.3

Workshop with stakeholders to discuss list of applications

PM; Stakeholders 2 days

2.1.4

Prepare final list of applications

PM; IT Architect

2.1.5

Approval of list

PM; Stakeholders 0 days

2.2

Analysis of relationships between applications

2.2.1

Overall analysis of relationships

2.2.2

Detailed analysis of applications

0 days

3 days

10 days
IT Architect

5 days
5 days

2.2.2.1 1st package of applications

IT Architect

5 days

2.2.2.2 2nd package of applications

IT Architect

5 days

2.2.2.3 3rd package of applications

IT Architect

5 days

2.3

Analysis of data flow between applications

2.3.1

Overall analysis of data flow

2.3.2

Detailed analysis of applications

10 days
IT Architect

5 days
5 days

2.3.2.1 1st package of applications

IT Architect

5 days

2.3.2.2 2nd package of applications

IT Architect

5 days

2.3.2.3 3rd package of applications

IT Architect

5 days

2.4

Prepare final report from analysis

IT Architect

5 days

2.5

Approval of analysis results

PM; Stakeholders 0 days

TOGAF® Series Guide (2018)

4. Develop Schedule

This activity is the process of analyzing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule model.31 For this task it is recommended
to use one of the available scheduling tools that enable a schedule to be built easily.
Please refer to the Critical Path Method (CPM) which is a commonly used technique supporting
the process of scheduling tasks.

31

PMBOK Guide, 5th Edition.

Architecture Project Management

45

In Project A, the Project Manager developed a schedule using a scheduling tool. He agreed
with the Project Sponsors that it would start at 2016-01-04. He set the start date for start of
the project activity and set the scheduling tool property to automatically schedule all tasks
based on needed resources and duration of all activities. The results of developing the
schedule is presented below:
Resource
Names

Duration Start

PM

0 days

2016-01-04 2016-01-04

Relationships and data flows
between applications

25 days

2016-01-04 2016-02-05

2.1

Agree list of applications

10 days

2016-01-04 2016-01-15

2.1.1

Workshop with architecture team to 1
get initial list

PM;
IT Architect

1 day

2016-01-04 2016-01-04

2.1.2

2.1.1
Summary of the workshop with
architecture team (initial application
list)

PM;
IT Architect

4 days

2016-01-05 2016-01-08

2.1.3

Workshop with stakeholders to
discuss list of applications

2.1.2

PM;
Stakeholders

2 days

2016-01-11 2016-01-12

2.1.4

Prepare final list of applications

2.1.3

PM;
IT Architect

3 days

2016-01-13 2016-01-15

Approval of list

2.1.4

PM;
Stakeholders

0 days

2016-01-15 2016-01-15

10 days

2016-01-18 2016-01-29

5 days

2016-01-18 2016-01-22

ID

Activity Name

1

Start of the project

2

Example 2.1.5

3.2.8

2.2

Analysis of relationships between
applications

2.2.1

Overall analysis of relationships

2.2.2

Detailed analysis of applications

2.2.2.1

WBS
Predecessors

Finish

2.1.5

IT Architect

5 days

2016-01-25 2016-01-29

1st package of applications

2.2.1

IT Architect

5 days

2016-01-25 2016-01-29

2.2.2.2

2nd package of applications

2.2.1

IT Architect

5 days

2016-01-25 2016-01-29

2.2.2.3

3rd package of applications

2.2.1

IT Architect

5 days

2016-01-25 2016-01-29

2.3

Analysis of data flow between
applications

10 days

2016-01-25 2016-02-05

2.3.1

Overall analysis of data flow

5 days

2016-01-25 2016-01-29

2.3.2

Detailed analysis of applications

5 days

2016-02-01 2016-02-05

2.3.2.1

1st package of applications

2.3.1;2.2.2.1

IT Architect

5 days

2016-02-01 2016-02-05

2.3.2.2

2nd package of applications

2.3.1;2.2.2.2

IT Architect

5 days

2016-02-01 2016-02-05

2.3.2.3

3rd package of applications

2.3.1;2.2.2.3

IT Architect

5 days

2016-02-01 2016-02-05

2.4

Prepare final report from analysis

2.2[FF];2.3[FF] IT Architect

5 days

2016-02-01 2016-02-05

2.5

Approval of analysis results

2.4

0 days

2016-02-05 2016-02-05

2.2.1

IT Architect

PM;
Stakeholders

Consolidate the Statement of Architecture Work and Secure Approval
The schedule resulting from the above activities, together with elements developed in the steps
of the ADM Phase A, should be included in the Statement of Architecture Work. To complete
ADM Phase A, the Project Manager obtains the sponsor’s approval of the Statement. For details
refer to the TOGAF standard, Phase A (Develop Statement of Architecture Work; Secure
Approval), and Part IV: Architecture Deliverables (Statement of Architecture Work).

46

TOGAF® Series Guide (2018)

3.3

Planning a Stage

3.3.1

What is a Stage? – Dividing an Architecture Project into Stages
PRINCE2 advocates dividing a project into manageable and controllable stages. PMBOK says
that stages32 can be broken down “by functional or partial objectives, intermediate results or
deliverables, specific milestones within the overall scope of work, or financial availability”.
Stages are generally time-bound, with a start and ending or control point.
What stages should the Architecture Project be split into? The TOGAF standard recommends an
iterative approach in the ADM.33 It suggests use of architecture development iterations that cycle
through Phases B to F to deliver architecture. In such a case, each architecture development
iteration would be executed as a separate stage.
In general, a few options for how to split an Architecture Project into stages can be considered,
depending on the project goal. Here are a few frequently used approaches:


Splitting the baseline architecture definition, target architecture definition, and transition
planning into separate stages (note that the TOGAF standard advocates both baseline-first
and target-first approaches, depending on context34)



Splitting into iterations based on a level of detail (e.g., the first iteration delivers a highlevel outline that is detailed in the next iterations)



Splitting into iterations based on a level of consultation (e.g., the first iteration delivers an
internal Enterprise Architecture draft, refined in the next iterations through consultation
with groups of stakeholders)



Using a sequence of ADM phases, where each stage includes a single phase, or a number
of phases (e.g., Architecture Vision, Business/IS/Technology Architecture, Opportunities
& Solution/Migration Planning)



Single stage approach; i.e., the whole Architecture Project is executed as a single stage



A mix of these

The approach should be chosen carefully to ensure it meets the Architecture Project goal and
constraints such as time and budget. The TOGAF advice on choosing the right approach can be
found in the TOGAF standard, Part III: Applying Iteration to the ADM.

32

The PMBOK uses the word “phase”. In this Guide, we use the word “stage” when referring to PRINCE2 “stages” and PMBOK
“phases”. We use the word “phase” according to its TOGAF definition (the ADM consists of phases, which do not necessarily equal
Architecture Project stages).
33

Refer to the TOGAF standard, Part III: Applying Iteration to the ADM (Iteration Considerations) for more information on applying
iteration to the ADM.
34

Refer to the TOGAF standard, Part III: Applying Iteration to the ADM (Approaches to Architecture Development) for more
information on approaches to architecture development.

Architecture Project Management

47

In Project B, a complex business process is to be analyzed and optimized. The process scope
is not fully understood, but it is known that three business units play key roles in the process,
each of them divided into five subunits on average. After the process is analyzed, the team is
going to model to be state for the process. Then, it is going to define and prioritize initiatives
that will move the company to the target state.
The architect leading the project decides on an approach based on splitting the baseline
architecture definition, target architecture definition, and transition planning. He also decides
to work on the baseline iteratively, with the first iteration goal to understand the whole
process and plan detailed work. His plan includes the following stages:
1.

Process Overview (2 weeks) – preliminary analysis and general business process views
definition, based on existing documentation and meetings with business unit leaders;
approach and schedule confirmation based on process overview.

2.

Process Analysis (5 weeks) – thorough workshops with each of the subunits to define
detailed process views including collaboration with other departments and external
organizations, and IT systems support (15 workshops; 5 workshops per week); summary
meetings with business unit leaders; process models review with subunits.

3.

Process Modeling (4 weeks) – target process modeling; new and changed logical IT
components definition; target model review with subunits and business unit leaders.

4.

Transition Planning (3 weeks) – initiatives definition, prioritization, and roadmap
preparation.

Example

Note that Stage 1 can be mapped to the ADM Phase A, Stages 2 and 3 cover activities from
the ADM Phases B and C, and Stage 4 includes activities from the ADM Phases E and F.

3.3.2

Planning a Stage
According to PRINCE2, a stage should be planned before it starts; i.e., at the end of the previous
stage. This enables use of earlier project results, risks, and lessons learned in stage planning. It
also allows for task execution and monitoring from the beginning. Typically, stage boundaries
are already set in the Project Plan (refer to Architecture Project Start-Up, Section 3.1), so when
planning a stage, we already know:


What products are to be delivered by the stage; i.e., what views



What level of detail is expected



What architecture elements are in scope; e.g., processes and/or applications list for
segment architecture



What the timeframe is



What the key tasks to be completed are



What resources are allocated

If the above are unclear, use techniques described in Architecture Project Planning (Section 3.2)
to determine them.
Depending on the overall Project Plan level of detail, the stage plan can already be a part of it
(i.e., the level of detail is sufficient to proceed with the work) or it may be needed to create a
more detailed plan for the stage.

48

TOGAF® Series Guide (2018)

PRINCE2 recommends planning the work stage by stage (see PRINCE2, Section 2.4). This
approach is suitable in most Architecture Project cases, in our view. It is practical to have a
general Project Plan that clearly defines stages and their boundaries, but does not go too deep – it
should only outline the major activities and their timeframes within each stage. Therefore, a
detailed stage plan has to be prepared before each of the stages.
To create a stage plan, you can follow the guidelines on the Project Plan presented in
Architecture Project Planning (Section 3.2). The approach is the same – defining activities,
sequencing them, estimating efforts, and scheduling. However, effort and schedule should stay
within the stage boundaries set by the Project Plan.
In Project B, after the Process Overview stage, the Project Manager prepared the next stage
(Process Analysis) plan.
The Project Manager’s work was based on an earlier prepared Project Plan, which outlined
the stage schedule:


3 weeks for workshops with the subunits



1 week for analysis consolidation and internal review



1 week for analysis review by the subunits



1 week for addressing issues identified through reviews

Additional information was collected in the previous stage (Process Overview), including:


There are 13 subunits that take an important part in the logistics process execution;
3 others have a supporting role



Contact persons were established for each of the subunits. Based on this input, the
Project Manager detailed the stage plan with a daily granularity



There will be 13 workshops, one for each of the subunits that take part in the process,
with supporting units included in 3 of the workshops

Example 

One full day was allocated for each of the workshops (13 days overall); workshops are
led by a business analyst with a logistics systems architect support (16 hours effort per
workshop); the product of each workshop day is a BPMN process model agreed at the
meeting and a worksheet with a process description including the IT systems role in the
process steps



2 days were allocated for workshops scheduling, templates, and other materials
preparation



2 days were allocated for business analyst to consolidate the whole material and 3 days
for the leading architect to review. The product of these activities are refined process
model and descriptions



1 week was allocated for subunit reviews that would be conducted in parallel (16 hours
effort of the Project Team for subunits support during the review period)



4 days were allocated for addressing issues



1 day was allocated for a workshop with subunits to discuss how the issues were
addressed and communicate plans for the next stage (Process Modeling)

This stage plan was documented in a dedicated worksheet, listing the activities, resources
performing these activities, timeframes, and work products. It was later supplemented with
workshop details – dates, locations, and subunit representatives.

Architecture Project Management

49

3.3.3

Adjusting a Project Plan
Ideally, there would be no changes to the Project Plan after planning a stage – i.e., the stage plan
would match the schedule, scope, and budget restrictions implied by the Project Plan. However,
if needed, the Project Plan should be updated to reflect the stage plan.
The project still has to meet its time/budget/scope boundaries – or the change has to be handled
as an exception. Please refer to Execute, Monitor, and Control a Stage (Section 3.4) for how to
manage such exceptions.
In Project B, after the Process Overview stage it was identified that there is another business
unit engaged in the logistics process execution. The Project Manager assessed that an extra
week will be needed for additional workshops in the Process Analysis stage. The Project
Manager also noted that the Process Modeling stage schedule was very tight and additional
reviews could make it impossible to close the stage in four weeks.
Project B was governed by an Architecture Board. Its Sponsor was the CIO. After completing
the Process Overview stage, the Project Manager reported the stage end to the Sponsor and
Example
the Architecture Board, presented its results, and requested a change in the project schedule
(plus two weeks) and budget (plus 120 hours) to reflect the extra effort needed.
After discussion, the governing body agreed for an extra one week (and 60 hours) in the
Process Analysis stage. A risk of insufficient time to complete the Process Modeling stage
was registered. It would be reassessed after the Process Analysis stage. Also, it was agreed
that each of the subunits would select a single representative for reviews in the Process
Modeling stage to reduce the above risk.

Stage planning activities are described as part of the Managing Stage Boundaries process in
PRINCE2. PMBOK recommends performing its Initiating processes at the start of each stage
when using a staged approach. Refer to the mappings presented in PRINCE2 to ADM Mapping
(Chapter 4) and PMBOK to ADM Mapping (Chapter 5) and the Project Management methods
themselves for further information.

3.4

Execute, Monitor, and Control a Stage



Both PRINCE2 and PMBOK distinguish between monitoring and controlling the stage and
directing or executing the work. These groups of processes serve a different purpose and
focus on different individual processes; however, from daily Project Management routines
they are executed in parallel. For practical reasons in this Guide we decided to present both
groups – directing (PRINCE2) or executing (PMBOK) and monitoring and control – as a one
chapter covering both areas.
For more details, please refer to the PRINCE2 and PMBOK methods.

Execution, monitoring, and controlling a stage is a core activity of the Project Manager within
every stage of the project. This means making sure that the work is being properly assigned,
tracking work progress, and reacting to unforeseen situations, as well as making sure that the
proper information is being distributed to the required parties.
There are few activities assigned to this process by the PRINCE2 method. From the PMBOK
perspective, these activities are a part of Monitor & Control, just narrowed down to the specific
phase of the project. Since most of the actions are ongoing throughout the stage it is difficult to
set the sequence or describe the order.

50

TOGAF® Series Guide (2018)

3.4.1

Authorize the Project Work Package
According to the key rule, no Project Work Package should be worked on unless clear
authorization is given by the Project Manager. The purpose is to prevent the project going off
track by working on some deliverables or tasks until all prerequisites are completed and properly
processed through approval. Otherwise, the risk of rework or delivery of a product that does not
comply with quality requirements is high.
The authorization to start the work should be explicitly received from the Project Manager along
with the following information:


What should be delivered, the scope, and expected product of the Project Work Package



The cost and time of work on the delivery of the product and its tolerances that often come
from the free-float of the schedule or other constraints that need to be identified and
communicated by the Project Manager



Specific information about quality requirements and configuration management required
for this process



Specific information about required reporting and distribution of information that would
support the control and monitoring of progress

It should also by clearly communicated to the team that authorization is required before they can
start any activity related to the Project Work Package. Even if the team feels like all
prerequisites are completed, there might be – and often are – situations where there are
additional questions that need to be addressed before the work can continue and all details
related to the product are properly defined.

3.4.2

Review Project Work Package Status
As defined in the Project Plan and Project Work Package authorization step, the team that is
carrying out the work should submit the reports (checkpoint reports) to the Project Manager at
regular, agreed intervals to allow for continuous control of progress and to identify risks related
to timely completion of the Project Work Package.
The input received from teams is the base for the Project Manager to report the progress to
stakeholders and make decisions for required adjustments for schedule, budget, and other
relevant forecasts. This is also a key point for identification of risks and problems that may
impact assumed deadlines, quality, or cost baseline.
In practice, the review of the Project Work Package status is carried out in a form of status
meetings with the Project Management team and Project Work Package team working on the
particular package. It is highly recommended to perform the status review in meeting form in
addition to written form, since more information and details can be obtained and any unclear
points can be discussed.
Reviewing the status of the Project Work Packages also allows identification of the areas of the
project or products where work is not being progressed as originally planned. This may happen
due to multiple internal and external factors. It might be a case of underestimation of the time
and effort needed to complete the work, or any other change in the Project Scope, schedule, or
effort (budget). Any change should be subject to the formal change control procedure.

Architecture Project Management

51

The change control procedure is extremely important from a Project Management perspective. It
is to ensure that whatever was agreed to be delivered as project products, schedule, or cost
baseline is under control, and can be changed only in a formal way. The procedure varies
between projects and organizations: sometimes the Project Manager has certain authority to
make decisions for changes in the project (for example, not exceeding a certain cost threshold),
and in some cases only the Steering Committee of the project can approve the change requested.
It is very important that the change is not incorporated in the project until it is approved.

3.4.3

Review Completed Project Work Package
Once the work on the Project Work Package is completed and the final product of the package is
ready and approved, the Project Work Package is marked complete by the Project Manager, and
related successor Project Work Packages can be authorized as described in the Authorizing
Project Work Package task.

3.4.4

Review Stage Status
The Project Manager must review the overall status of the stage in order to ensure control over
the progress being made. To effectively do that, the Project Manager should review all
management products such as checkpoint reports, the current stage plan, the various registers
and logs (quality register, issue register, risk register, and daily log), also including the benefits
review plan. Based on these inputs, the overall project status is estimated and recorded (for
example, using the MS Project® tool). This should present the overall stage or project status to
stakeholders.

3.4.5

Capture and Examine Issues and Risks
Risk management becomes even more critical during the project execution and control phase. It
is important for the Project Manager to regularly conduct risk assessments. Particular attention
should be paid to risks prior to production cutover.
Following the strategy, processes, and procedures established during project start-up, the Project
Manager must make sure that all project issues are carefully and accurately logged, prioritized,
and assigned for closure. Moreover, it is the Project Manager’s responsibility to drive open
issues to a closure that fulfills the requirements.
On a regular basis, the Project Manager should perform risk assessments. The following steps
should be performed:

52



Revisit risks defined in the risk log and include new risks as appropriate



Categorize, assess, and analyze the probability and severity of each risk



Determine symptoms that would indicate that risks may be occurring



Prepare a mitigation and response plan for each risk



Report results of risk assessment

TOGAF® Series Guide (2018)

The Project Manager decides to hold a weekly status meeting to keep track of the stage
progress and control the process. Since the project timeline extends over a few months, he
decides that a weekly meeting is sufficient. In case of more aggressive schedules more
frequent meetings may be better to allow for faster information flow and shorter reaction time
to any unplanned situations. A weekly meeting does not replace a daily routine for
communication and information exchange, but is the best tool to ensure unified
communication to the team and collecting feedback.
The Project Manager prepares the agenda for the meetings around a common schema:


Review of progress to date – this allows the Project Manager to collect and discuss
information about the status of the stage, some details on Project Work Packages
completion, and to identify and discuss risks that may impact the assumed work plan
At the same time, completed Project Work Packages are confirmed and the Project
Manager makes sure that the final versions of the Project Work Packages are delivered
for the approval process.



Confirm the plan for next period of time (usually a week) – this is part of the status
control in terms of confirmation of tasks to be worked on during the following week.
In case of tasks that are a continuation of current Project Work Packages, this serves as
information about what progress is expected to be achieved over the period. If the Project
Plan defines a new Project Work Package to start in the next period, this needs to be
clearly communicated to the team; if there is a “green light” to start the work, or what
needs to happen before the green light is given.

Example


Identify and examine risks and issues – most risks and issues come from team members.

3

4



3.4.6

Risk Description

04.03.2014

There is a risk that billing capabilites of the target
solution will be defined in a way that no existing
COTS solution can support. Architecture Project 3
team has no knowledge of such solutions
available on the market.

2

05.03.2014

Architecture Project has the resposibility for
solution performance, but it is the Infrastructure
who decides on the hardware technology and
sizing. Therefore, Architecture Project may be
unable to ensure performance of the solution.

2

2

Severity

Date Raised

Impact

ID

Likelihood

They can identify most potential situations (missing input data, additional work,
misunderstandings and mismanaged expectations, etc.) that may impact the project, but
also information from project surroundings that is shared by the Project Manager based
on his sources of information is discussed as a potential risk or issue. Once identified,
risks or issues (issue is a materialized risk) are documented in a simple spreadsheet by
the Project Manager for further tracking.
Mitigation Plan

...
Hire an external consultancy with knowledge on
billing capabilities of market available solutions.
5 OR:
Extend the project plan with an RFI to gain
knowledge of solutions available on the market.
1. Perfom performance tests on development
environment and extrapolate results to estimate
performance. Development environment has to be
filled with test data.
4
2. Expected infrastructure needs will be passed to
the Infrastructure team.
3. Consult solution provider on the recommended
hardware after the performance tests.
...

Owner

Status

CRM solution
architect

Identified mitigation plan
to be agreed

Architecture
Project manager

Managed mitigation plan
agreed

Date Closed

The Project Manager decides what needs to be done next – usually he holds a quick
meeting with all parties that are affected by the risk or issue to examine it further and
plan for mitigation

Report Highlights
Based on collected information, the Project Manager should build the proper and tailored
message that should be communicated to the project stakeholders. This involves creating the
time-driven Highlight Report, which presents the current achievements and actual progress of
the project, and also describes any corrective actions that the Project Manager may intend to
carry out, as well as forecasts for the remainder of the stage and the project.

Architecture Project Management

53

The level of detail that should be provided to stakeholders varies between projects and each
particular stakeholder. It should be defined per particular situation taking into account the actual
requirements and particular preferences of each and every stakeholder. In practice, the minimum
set of details should be:


Achievements and tasks completed over the last reporting period to explain what was
done and how it related to the original project schedule and plan



Key activities planned for the next period – it is important, and helps to keep track of
progress made, to keep both points integral by showing the same list of achievements that
was presented in the last period as the planned tasks



Key risks and problems identified, especially these that require the attention of the
stakeholders or escalation



Quite often the report contains also some tracking for changes unapproved and approved
that were introduced to the project (using the formal change control process), open issues,
or decisions that need to be made by stakeholders
Based on the information collected during the weekly status meeting, the Project Manager
prepares the status report for management and stakeholders, as defined in the communication
plan. The form and content of the report depends on the expectations and preferences of the
report audience. Some prefer a simple one-page summary of progress to date, key activities
for the next period of time, key risks, and issues; while other stakeholders expect detailed
presentations with a deep-dive on risks and content of the delivered Project Work Packages.

For this project, the Project Manager discussed the expectations with key stakeholders, and he
is expected to prepare a one-page weekly report, highlighting the key activities and risks, and
to discuss it with stakeholders on the weekly briefing within 15 minutes. The Project Manager
Example
decides to present three bullets per area: achievements to date, plans for the next period, three
or four of the most important risks and issues, and also the most important decisions to be
made by the stakeholders.
Once per month a more detailed report is prepared and presented to the Steering Committee
of the project during a 45-minute meeting. More discussion and details are presented,
including a plan for team interaction meetings with other employees of the company for the
next period of time (1 month in this case), to confirm the schedule with decision-makers and
ensure their awareness and support, and more details on risks and issues especially if
escalation is required.

3.4.7

Escalate Issues and Risks
In cases where handling a risk or problem exceeds the authority of the Project Manager, it is
necessary to escalate to the Project Board/Steering Committee. This must be done especially
when a risk or problem exceeds the tolerance assigned to it. PRINCE2 defines this as an
exception and triggers an Exception Report, which is written by the Project Manager and
submitted to the Steering Committee for further action.

54

TOGAF® Series Guide (2018)

The 15-minute status meetings with key stakeholders and the Steering Committee are the
perfect occasion to escalate risks or issues that need to be taken up in the chain of command.
Of course most of these issues are discussed by the Project Manager with stakeholders before
the meeting, once risks are identified, but these meetings present a good opportunity to
discuss them further and perhaps get the involvement and support of someone else from the
management team or Steering Committee. For risks and issues that were not identified as
exceeding the authority of the Project Manager, but may still impact the project heavily, the
Project Manager decides to share his mitigation plan as well to communicate such a situation,
Example but also – quite often – he is given support by Steering Committee board that makes the
mitigation process easier.
In Project E, the architect identifies that some of the data warehouse calculations should be
done in a COTS calculation engine solution possessed by the bank. However, the business
analyst team does not have any knowledge of this solution. There is a risk that they would be
unable to model the calculations process adequately to the calculation engine capabilities.
Therefore, the architect collaborates with the Project Manager to describe the risk. It is
recorded in the risk log.

3.4.8

Take Corrective Action
During this stage, the Project Work Package is revised in comparison with the existing plan.
Evaluation of risks, problems, and discrepancies between the plan and the Project Work Package
are done as part of this review. The stage status often ends with a conclusion that certain actions
need to be taken to bring the project back on track. These are corrective actions and they should
become the integral part of the Project Plan and schedule. The goal is to address all situations
that already did or are expected to impact the plan and schedule in negative form.
Based on risk or issue evaluation and discussion with the Steering Committee or stakeholders,
a plan is created to make sure the risk or issue has a minimal negative (or maximum positive)
impact on the project. The Project Manager adds these tasks to the Project Plan in the Project
Work Package that is affected by the risk or issue. Tasks are also put on the timeline and the
task owner is assigned as for every other task of the project. Corrective action becomes an
integral part of the project and from here on is being tracked, reported, and controlled in the
same way as any other task in the plan.
Example

In reference to the previous example, the Project E Project Manager collaborates with the
architect and the business analysis leader to design a risk mitigation. They recommend that
two of the business analysts would be trained on the calculation engine solution capabilities.
Then, they will use this knowledge to guide the calculations process analysis to make use of
the calculation engine capabilities.
Later on, the Project Manager collaborates with the management team to formally accept this
mitigation and proceed with it.

3.5

Ending a Stage
A stage ends when stage deliverables are done and, typically, handed off and approved.
According to PMBOK, stage end is a natural milestone that allows reassessment of the work
being done and necessary changes to be made, or even termination of the project if needed. 35
PRINCE2 is much more specific on the topic – it defines the Managing a Stage Boundary

35

PMBOK Guide, 5th Edition, Section 2.4.2.

Architecture Project Management

55

process whose purpose is to review the finished stage and approve next stage plan, making sure
the project is still justifiable and viable.36

3.5.1

Stage Deliverables Hand-off and Approval
At the stage end, the Project Manager makes sure all of the stage deliverables are handed off and
approved appropriately. This may include internal Project Team reviews (for example, those
who will use the deliverables as inputs in further project execution), external parties’ reviews
(such as business users), and stakeholders’ approval (for example, Project Sponsor or Steering
Committee members).
Stage hand-off and approval activities may be very limited, if each of the deliverables was
separately approved earlier.
In Project B, after completing workshops and internal reviews of the Process Analysis
deliverables (process models and descriptions), the Project Manager sent these deliverables to
business units for review. A one-week deadline was set for comments and change
Example
suggestions. After that, the Project Team assessed and addressed the reviews received. A
meeting was held to discuss major issues. Then, the deliverables were presented to the Project
Sponsor for final approval (see next example).

3.5.2

Managing a Stage Boundary
When stage exit criteria are met, the stage end should be reported by the Project Manager to the
Architecture Project Oversight (i.e., Architecture Board or Project Sponsor; see Architecture
Project Start-Up, Section 3.1). Typically, the report should include:


A summary of the completed stage – it should show how all stage products were delivered
and how the stage has performed against targets for time, cost, quality, scope, risk, and
benefit



Impact on the project – if the Project Plan needs to be updated



Plan of the next stage – refer to Architecture Project Planning (Section 3.2) for stage
planning

In Project B, after completing reviews with the business units and addressing their comments,
the deliverables were presented to the Project Sponsor for final approval. The meeting was
Example also meant to close the Process Analysis stage. Therefore, the Project Manager reported ontime delivery of the stage, presented the Process Modeling stage plan, and recommended its
execution, which was approved by the Project Sponsor.

Any issues identified should be handled according to the description in Escalate Issues and Risks
(Section 3.4.7).
The Architecture Project Oversight decides on further execution of the project – its continuation,
change, or termination. It can take into account factors that are internal (such as timeliness and
costs) and external (such as enterprise goals and priorities change) to the project.

36

PRINCE2, Chapter 17.

56

TOGAF® Series Guide (2018)

In Project E, after the High-Level Architecture stage, the deliverables were presented to the
Project Sponsor for final approval. However, the Project Manager noted that the detailed
business analysis stream identified gaps that needed a lot of extra work and may impact the
Example High-Level Architecture. He presented associated risks for the project and recommended an
adjusted Project Plan that included revisiting the High-Level Architecture stage after the
detailed business analysis is fully completed two months later. The Steering Committee
accepted the proposed resolution.

3.6

Architecture Project Closing
Architecture Project closure includes all activities that formally close the project. The Project
Manager starts closing the project when all iterations or stages are finished and all project
products or Project Work Packages are finished and approved by the Executive. It can also be
started if the project’s business case is no longer valid and project governance decides to close
the project.
Architecture Project closing includes the following activities:

3.6.1



Products handover



Prepare and recommend closure



Evaluate the project and document lessons learned

Products Handover
The Architecture Project delivers a definition of an architecture to be implemented. The final
step leading to this architecture implementation is handing the deliverables over to the body
responsible for implementation.
At the end of Phase F, the Architecture Project delivers several deliverables that together form
the final product. These deliverables, including the Architecture Definition Document,
Implementation and Migration Plan, and Architecture Roadmap, should be used as inputs to the
program and Project Management activities that are typically executed by another organizational
unit (and governed by the ADM Phase G).
Project deliverables should be transferred to the organizational unit that will implement the
architecture (e.g., PMO or business owner of the implementation). From our experience, it is
crucial to ensure that these deliverables are sufficient to start the implementation project (or
program) right away. It is a common issue to have the architecture finished, but the
implementation start is delayed due to some additional documentation needed, especially for
strategic and segment-level projects.
This issue can be mitigated with careful quality management based on quality criteria agreed
with the organizational unit that will implement the architecture (see the Define the Management
Approach step in Architecture Project Start-Up (Section 3.1) for quality management planning).
The TOGAF standard also highlights the need to coordinate the Implementation and Migration
Plan with the management frameworks within the organization.37

37

The TOGAF standard, Phase F (Steps).

Architecture Project Management

57

Architecture Project deliverables can also include new Requests for Architecture Work (that will
start a new Architecture Project) and/or change requests for architecture capability.
The detailed mapping of Architecture Project products is presented in Figure 6.

Figure 6: Architecture Project Final Deliverables

3.6.2

Prepare and Recommend Closure
To close the project formally, the Project Manager has to prepare a closing report and
recommend project closure to the project governance.
The project closing report should contain information collected throughout all stages of the
project. The report should summarize:38


38

Products that were delivered by the Architecture Project

PMBOK Guide, 5th Edition.

58

TOGAF® Series Guide (2018)



Work performance – how did the project perform against targets for time, cost, quality,
scope, and benefit



Risks and issues summary, and how were they mitigated



Architecture capability performance information

The report should be presented to the project governance.
Closing the project needs formal acceptance of the Executive. This is typically obtained after
presenting the project closing report. The Project Manager should also confirm with the
Executive and stakeholders that all Architecture Project deliverables are reviewed and accepted
by them.

3.6.3

Evaluate the Project and Document Lessons Learned
The final step of an Architecture Project should be its evaluation. The team should document the
lessons learned for further Architecture Projects and recommend architecture capability
improvements.
This step is very important from the perspective of knowledge management and continuous
improvement of architectural practice. Lessons learned documentation should always be
considered as an input to further Architecture Projects.
Lessons learned should document project assumptions about product quality, project
performance data (e.g., time and costs), and comparison with project results. If there are any
deviations, lessons learned should contain the analysis of factors that impacted these deviations
and deduction of how to improve the Architecture Project management practice.
Based on lessons learned, the Project Team can define recommendations for architecture
capability improvement. According to the TOGAF standard, these recommendations should
include change requests that will be handled in the ADM Phase H (Architecture Change
Management).

Architecture Project Management

59

In Project A, the Project Manager established a project evaluation meeting with his team.
During this meeting he recommend an After Action Review (AAR) approach to evaluate the
project. During this meeting all project performance-related information was gathered.
The meeting had a structured agenda – after the Project Manager introduction that explained
the meeting goals, the team discussed and answered the following questions:


What were we supposed to achieve at the end of the project?



What did we achieve?



Why is there a difference?



What did we learn and what can we improve in our future projects?

They documented the meeting results using the following lessons learned template:
No.

Example

60

Issue Name

Issue Description

Impact on Project

Recommendation

Agreement of
application list
takes more time
than planned.

We had a problem
with agreement on
the list of
applications with
stakeholders. It took
1 month instead of
10 days. We found
that there was a lack
of formalized and
systematic approach
to this task.

We have to provide
the changes in
schedule and assign
extra resources to
meet the project
deadline.

We need to prepare
a set of common
templates for our
stakeholders that
will improve the
efficiency of their
work.

The CFO stated
that his concerns
about the costs of
applications were
not addressed
properly.

The CFO stated that
he would like to
know potential
financial savings on
application portfolio
optimization as a
decision factor.

We have to modify
some views affected
by CFO concerns.

We recommend
adding the cost of
the application
license and
maintenance cost
to the application
function matrix.

TOGAF® Series Guide (2018)

4

PRINCE2 to ADM Mapping
The aim of this section is to a present mapping of the TOGAF ADM to PRINCE2. This section
is assumed to provide general information about the mapping, not detailed information about the
TOGAF ADM phases and PRINCE2 processes; therefore, the standard terms are used without
description. For more detailed information, please refer to the TOGAF standard and Managing
Successful Projects with PRINCE2.
In general, the TOGAF ADM Phase A (Architecture Vision) can be mapped to the PRINCE2
processes “Starting up the project” and “Initiation”. The TOGAF ADM Phase B (Business
Architecture), Phase C (Information Systems Architectures), Phase D (Technology
Architecture), Phase E (Opportunities and Solutions), and Phase F (Migration Planning) can be
grouped together and considered substantive Architecture Project phases, which – according to
PRINCE2 – should be considered work delivery stages.
Division of the TOGAF ADM Phase B to F into PRINCE2 work delivery stages depends on the
scale and constraints of the Architecture Project.

4.1

High-Level Mapping Description
Figure 7 presents the results of the TOGAF ADM mapping into PRINCE2 Project Management
processes at a high level. In order to ensure clear understanding of the mapping, some tasks and
processes were aggregated and simplified. Furthermore, only the main deliverables are
presented.

4.1.1

TOGAF ADM Phase A (Architecture Vision)
Figure 7 should be read from top to bottom starting from the first task of the ADM in Phase A:
Establish the Architecture Project. In this TOGAF task architecture activities should be planned
and managed using accepted practices for the enterprise.
In order to manage the Architecture Project using the PRINCE2 method during “Establish the
Architecture Project” it is recommended to execute following tasks from the PRINCE2 “Starting
up the project” stage:


Appoint Project Executives and Project Manager



Design a Project Management Team



Prepare Outline Business Case



Select Project Approach & Assemble



Plan the Initiation Stage

Architecture Project Management

61

The Stage Plan (initiation) is the result of the “Starting up the project” stage and is considered an
input to the next TOGAF ADM Phase A tasks and PRINCE2 “Initiation” stage, which should be
performed in parallel. The following ADM Phase A tasks:


Identify Stakeholders, Concerns, and Business Requirements



Confirm and Elaborate Business Goals, Business Drivers, and Constraints



Evaluate Capabilities



Assess Readiness for Business Transformation



Define Scope



Confirm and Elaborate Architecture Principles, including Business Principles



Develop Architecture Vision



Define the Target Architecture Value Propositions and KPIs



Identify the Business Transformation Risks and Mitigation Activities



Develop Statement of Architecture Work

should be performed in parallel with the following PRINCE2 “Initiation” stage tasks:


Prepare Management Strategy, Business Case, and Project Controls



Create Project Plan



Refine the Business Case

Be aware that some of the TOGAF ADM Phase A tasks produce Project Management
deliverables which are used in PRINCE2 processes as shown in Figure 7 with a dotted line. The
final task in ADM Phase A is the Statement of Architecture Work Definition and Approval,
which along with deliverables should be included in the Project Initiation Document, which is
the main deliverable from the PRINCE2 “Initiation” stage assembled in the last process
(Assemble the Project Initiation Document).

4.1.2

TOGAF ADM Phases B to F
The TOGAF ADM Phase B (Business Architecture), Phase C (Information Systems
Architectures), Phase D (Technology Architecture), Phase E (Opportunities and Solutions), and
Phase F (Migration Planning) are considered as PRINCE2 work delivery stages and should be
planned under the PRINCE2 Managing Stage Boundary, controlled under PRINCE2
“Controlling the Stage” and delivered under PRINCE2 “Managing Product Delivery”.

62

TOGAF® Series Guide (2018)

Figure 7: TOGAF ADM and PRINCE2 Mapping (High-Level) (Derived from the TOGAF Standard
and PRINCE2)

Architecture Project Management

63

4.2

Detailed Mapping Description
Figure 8 presents the results of the TOGAF ADM mapping into PRINCE2 Project Management
processes on a detailed level. The aim of this diagram is to present a detailed mapping, including
all tasks from the TOGAF ADM Phase A (Architecture Vision) and the PRINCE2 “Starting up
the project” and “Initiation” stages, along with deliverables. This section describes additional
elements or changes to the high-level mapping that were included in the detailed mapping and
therefore should be read along with the description of the high-level mapping.

4.2.1

TOGAF ADM Phase A (Architecture Vision)
The following processes/stages were detailed to exactly reflect the TOGAF ADM and
PRINCE2.
All of the ADM Phase A tasks were included in the detailed mapping, along with the main
deliverables:
Establish the Architecture Project, which is input to the PRINCE2 “Starting up the project” stage
Identify Stakeholders, Concerns, and Business Requirements – results from this task should be
used during PRINCE2 “Set up the project controls” process


Confirm and Elaborate Business Goals, Business Drivers, and Constraints – resulting in
refined statements of business principles, goals, and drivers



Evaluate Capabilities



Assess Readiness for Business Transformation – resulting in a Capability Assessment



Define Scope, which has an impact on the PRINCE2 “Refine the Business Case” process



Confirm and Elaborate Architecture Principles, including Business Principles – resulting
in Architecture Principles



Develop Architecture Vision – resulting in a Draft Architecture Definition Document and
Architecture Vision which are inputs to the PRINCE2 “Create the Project Plan” process



Define the Target Architecture Value Propositions and KPIs



Identify the Business Transformation Risks and Mitigation Activities – resulting in a
Communications Plan



Develop Statement of Architecture Work; Secure Approval – resulting in an Approved
Statement of Architecture Work, which should be part of the PRINCE2 Project Initiation
Documentation that is to be completed during the PRINCE2 “Assemble the Project
Initiation Documentation” process

All of the PRINCE2 “Starting up the project” processes were included in the detailed mapping,
along with all deliverables:


64

Appoint the Executive & Project Manager, which should be started after the “Establish the
Architecture Project” task from the ADM, resulting in the Project Management team role
descriptions (part of the Project Brief)

TOGAF® Series Guide (2018)



Capture previous lessons – resulting in a Lessons Log



Prepare the outline Business Case – resulting in the Outline Business Case and Project
Product Description (both part of the Project Brief)



Design and appoint the Project Management team – resulting in the Project Management
team structure and updated Project Management team role descriptions (both part of the
Project Brief)



Select the project approach & assemble the Project Brief – resulting in the Project
Approach (part of the Project Brief)



Plan the initiation stage – resulting in the Initiation stage plan

All of the PRINCE2 “Initiation” processes were included in the detailed mapping, along with all
deliverables.
Development of Project Management Strategies, that can be executed in parallel:


Prepare the Risk Management Strategy – resulting in the Risk Management Strategy (part
of the Project Initiation Documentation) and Risk Register



Prepare the Quality Management Strategy – resulting in the Quality Management Strategy
(part of the Project Initiation Documentation) and Quality Register



Prepare Configuration Management Strategy – resulting in the Configuration Management
Strategy (part of the Project Initiation Documentation), Configuration Item Records, and
Issue Register



Prepare the Communication Management Strategy – resulting in the Communication
Management Strategy (part of the Project Initiation Documentation)

Development of Project Plan and project controls, that can be executed in parallel after
completion of the Project Management Strategies:


Set up the project controls – resulting in the Project Controls (part of the Project Initiation
Documentation)
Results from the ADM step Identify Stakeholders, Concerns, and Business Requirements
should be used during this process to ensure the integrity of the project control
mechanisms.



Create the Project Plan – resulting in the Project Plan (part of the Project Initiation
Documentation)
The Draft Architecture Definition Document prepared during Develop Architecture
Vision should be considered as input to planning all activities during the Architecture
Project.

The following tasks should be executed sequentially after completion of the previous “Initiation”
stage processes:


Refine the Business Case – resulting in the Detailed Business Case (part of the Project
Initiation Documentation) and Benefits Review Plan
Results from the ADM step Define Scope should be considered during this process.

Architecture Project Management

65



Assemble the Project Initiation Documentation – resulting in the Project Initiation
Documentation
The approved Statement of Architecture Work (resulting from the ADM step Develop
Statement of Architecture Work; Secure Approval) should be included in the Project
Initiation Document.

4.2.2

TOGAF ADM Phases B to F
As described in Architecture Project Management Concepts (Section 2.3), the TOGAF ADM
Phases B to F are considered as PRINCE2 work delivery stages and should be planned under the
PRINCE2 Managing Stage Boundary, controlled under the PRINCE2 “Controlling the stage”,
and delivered under the PRINCE2 Managing Product Delivery. Phases B to F do not specify any
Project Management activities; therefore, should be managed according to the PRINCE2
method.

66

TOGAF® Series Guide (2018)

Figure 8: TOGAF ADM and PRINCE2 Mapping (Detailed) (Derived from the TOGAF Standard
and PRINCE2)

Architecture Project Management

67

5

PMBOK to ADM Mapping
The aim of this section is to present the TOGAF ADM mapping to PMBOK processes. This
section is intended to provide general information about the mapping, not detailed information
about the TOGAF ADM phases and PMBOK processes; therefore, the standard terms are used
without description. A detailed description can be seen in the TOGAF standard and the PMBOK
Guide, 5th Edition.
In general, the TOGAF ADM Phase A (Architecture Vision) can be mapped to the PMBOK
initiation and planning process groups. The TOGAF ADM Phase B (Business Architecture),
Phase C (Information Systems Architectures), Phase D (Technology Architecture), Phase E
(Opportunities and Solutions), and Phase F (Migration Planning) can be grouped together and
considered delivery stages. Project closing should be considered as the last step of Phase F.
The TOGAF standard provides the ADM that defines the Enterprise Architecture lifecycle. In
this ADM there are distinct phases that are divided into steps that describe the processes related
to architecture planning, development, implementation, and architecture change management.
PMBOK describes the processes divided into knowledge areas and process groups. The
knowledge areas contain: integration management, scope management, time management, cost
management, quality management, human resource management, communication management,
risk management, procurement management, and stakeholder management. The process groups
are divided into: initiating, planning, executing, monitoring, and closing.
The TOGAF standard recommends managing the ADM cycle as a project and using for this
purpose the Project Management framework that is implemented in the enterprise.39 Based on
the ADM phases and Project Management process groups we could initially map the PMBOK
Project Management processes into the TOGAF ADM.
A detailed description of the mapping of the Project Management processes to the ADM steps
follows. Process activities are covered fully or partially in the TOGAF ADM steps. Some
processes are not covered in the TOGAF standard so we discuss them as additional Project
Management processes.
Figure 9 presents the high-level mapping between the TOGAF ADM and PMBOK processes. In
order to ensure clear understanding of mapping, some tasks and processes were aggregated and
simplified.

39

The TOGAF standard, Preliminary Phase, Approach (Management Frameworks, and Relating the Management Frameworks).

68

TOGAF® Series Guide (2018)

Figure 9: TOGAF ADM and PMBOK Mapping (High-Level) (Derived from the TOGAF Standard
and the PMBOK Guide)

Architecture Project Management

69

The following part of this section presents the detailed description of the PMBOK processes
mapping to the TOGAF ADM cycle. First, Phase A is being assessed. In this section each step is
mapped to the PMBOK processes. Then, Phases B to F are assessed. The last part presents the
closing part of the Architecture Project. The mapping covers an explanation of why and how
specific processes are mapped to each of the steps.

5.1

Phase A: Architecture Project Initiation and Planning

5.1.1

Establish the Architecture Project
In this step we should consider the use of the following PMBOK process:


Develop Project Charter

According the TOGAF standard, we have to apply the Project Management framework to the
execution of the ADM. We have to select the Project Manager that could be an external Project
Manager from the PMO or a Lead Architect responsible for execution of the ADM cycle.
Then we have to determine the company culture and existing processes and procedures. And
understand the business case for the project. In this step we should develop the Project Charter
that will address the stakeholder concerns expressed in the Request for Architecture Work.

5.1.2

Identify Stakeholders, Concerns, and Business Requirements
In this step we should consider the use of the following PMBOK processes:


Identify Stakeholders



Collect Requirements



Plan Communication Management



Plan Stakeholder Management

According PMBOK, we have to identify stakeholders and develop a stakeholder management
strategy. This approach is also covered in the TOGAF standard as a stakeholder management
technique. The TOGAF stakeholder management technique defines how to identify, classify, and
categorize the stakeholders according to communication needs in the form of a Stakeholder Map
that should be developed in this step.
The TOGAF approach fulfils all the needs related to stakeholder management here. The
Stakeholder Map should also be an input to the Communication Plan.
The TOGAF standard also recommend the business scenario technique to gather the stakeholder
requirements.

5.1.3

Confirm and Elaborate Business Goals, Business Drivers, and Constraints
In this step we should consider the use of the following PMBOK process:


Define the Scope

This step will have an impact on the vision of the project scope.

70

TOGAF® Series Guide (2018)

5.1.4

Evaluate Capabilities
In this step we should consider the use of the following PMBOK process:


Define the Scope

This step will have an impact on the vision of the project product scope. The identification of
current and demanded business capabilities will help the architects to develop the Architecture
Vision.
The Architecture Vision defines the target architecture that could be considered as a project
product scope.

5.1.5

Assess Readiness for Business Transformation
Business transformation readiness assessment is not covered by the PMBOK processes, but this
technique is useful to identify the project risks.

5.1.6

Define Scope
In this step we should consider the use of the following PMBOK process:


Plan Scope Management

The TOGAF standard recommends determining the scope in terms of breadth of coverage of the
enterprise, level of detail, covered architectural domains, and time period. In PMBOK, such
activities are covered in the scope management plan.

5.1.7

Confirm and Elaborate Architecture Principles, including Business
Principles
This step is not related directly to Project Management processes, but principles will have an
impact on the scope of the Architecture Project. Principles should be taken into account when
defining the target architecture in the Architecture Vision document.

5.1.8

Develop Architecture Vision
In this step we should consider the use of the following PMBOK process:


Define the Scope

The Architecture Vision describes the high-level target state of the architecture so we could treat
it as a project product scope.

5.1.9

Define the Target Architecture Value Propositions and KPIs
In this step we should consider the use of the following PMBOK process:


Define the Scope

In this step we define the quality measures of the project product.

Architecture Project Management

71

5.1.10

Identify the Business Transformation Risks and Mitigation Activities
In this step we should consider the use of the following PMBOK processes:


Plan Risk Management



Identify Risks



Perform Qualitative Risk Analysis



Perform Quantitative



Plan Risk Responses

The risk management approach in the TOGAF standard is similar to the approach recommended
by PMBOK.

5.1.11

Develop Statement of Architecture Work; Secure Approval
In this step we should consider the use of the following PMBOK processes:


Develop Project Management Plan



Create Work Breakdown Structure



Plan Schedule



Define Activities



Sequence Activities



Sequence Activity Resources



Estimate Activity Durations



Develop Schedule



Plan Costs Management



Estimate Costs



Determine Budget

The Statement of Architecture Work is a plan for architecture work that is accepted by the
stakeholders. An integral part of this document is a work plan. To develop this document, we
should perform processes from the Project Time Management knowledge area that will help us
to perform the important planning activities.
The TOGAF standard does not say anything about cost management, so after project planning
we should estimate the costs and determine the budget.

5.2

Phases B to F: Architecture Project Execution and Monitoring
In general, the main goal of the TOGAF ADM Phases B, C, D, E, and F is to prepare complete
work packages with a migration plan of how the target architecture can be achieved. The first

72

TOGAF® Series Guide (2018)

three – Phases B, C, and D – are assigned to the decomposition solution by looking into the
business, application, and technology layer and detailing both the baseline and target architecture
solution. Phase E concentrates on how to deliver the architecture. It takes into account the
complete set of gaps between the baseline and target architectures in all architecture domains,
and logically groups changes into work packages within the enterprise’s portfolios. Phase F
brings finalization of the Architecture Roadmap and the supporting Implementation and
Migration Plan. At the beginning of each phase, there is a reassessment and revalidation of
whether they are properly planned. When needed, the Project Management Plan is amended.
Planning of the next phase should be prepared in great detail, especially in terms of activities and
risk assessment. The following phases can be kept more general. Detailed planning of the closest
phase only ensures that the business value, cost of work packages, and transition architectures
are both optimal and understood by key stakeholders.
From the project point of view, we can assume that actions from Phases B to F are the next
phases of the project and the end of each phase can be understood as a milestone which delivers
an important functionality. The following PMBOK processes should be considered:


Direct and Manage Project Work



Perform Integrated Change Control



Close Project or Phase



Validate Scope



Control Scope



Control Quality



Perform Quality Assurance



Manage Communication



Manage Stakeholder Engagement

In order to better understand this, we should look at the entire knowledge area of Execution and
Monitoring and controlling where we can find processes from all areas.
Integration Management (4.3, 4.4, and 4.5):


Direct and manage project execution is a process of performing specific work by the
Project Manager (or leader of the work) with an intention to reach intended project goals.

Scope Management (5.4 and 5.5)
Time Management (6.4):


Keep the plan in sync with intended milestones

Cost Management (7.3):


The TOGAF standard does not provide a way to control costs, but it is an essential part of
each project.

Architecture Project Management

73

Quality Management (8.1, 8.2, and 8.3):


Set and control quality standards but also ensure that the intended work with appropriate
level of detail has been performed.

HR Management (9.2, 9.3, and 9.4):


Working with the team is critical when approaching a topic as broad as Enterprise
Architecture. It is very possible that in each phase the team would be changed as the each
phase requires a different set of competencies.

Communication Management (10.3, 10.4, and 10.5):


With the various stakeholders and their concerns, we will not only need to know who and
when to inform, but also to identify the information level that needs to be maintained
through to project resolution.

Risk Management (11.5):


As risk is something which can seriously damage an Architecture Project, the Project
Manager should have a way to identify and mitigate risk. Risk monitoring and controlling
management processes can help.

Stakeholder Management:

5.3



Managing stakeholder expectations is a process of communication and cooperation with
stakeholders in order to meet their needs and manage their future concerns.



These activities are strongly related to the ADM step Conduct Formal Stakeholder
Review.

Phase F: Architecture Project Closing
Complete the Architecture Development Cycle and Document Lessons Learned
Close Project or Phase (4.6)
This last step of Phase F is related to the PMBOK process closing project or phase. The use of
the PMBOK approach is recommended.

74

TOGAF® Series Guide (2018)

Glossary
See also Architecture Project Management Concepts (Section 2.3) for Architecture Project
Management concepts that are key to understanding this Guide.
Architecture

The structure of components, their inter-relationships, and the principles and guidelines
governing their design and evolution over time. [Source: the TOGAF Standard; one of two
definitions provided]
Enterprise

The highest level (typically) of description of an organization and typically covers all missions
and functions. An enterprise will often span multiple organizations. [Source: the TOGAF
Standard]
Project

A temporary endeavor undertaken to create a unique product, service, or result. [Source:
PMBOK Guide]
Project Management

Application of knowledge, skills, tools, and techniques to project activities to meet the project
requirements. [Source: PMBOK Guide]

Architecture Project Management

75

Index
agile approach................................. 23
Architecture Board ......................... 26
Architecture Definition..................... 4
Architecture Definition Document ... 2
Architecture Development Method
(ADM).......................................... 1
architecture domain ........................ 27
Architecture Governance ................ 25
Architecture Project .......................... 1
Architecture Project lifecycle ........... 8
Architecture Skills Framework....... 19
architecture team ............................ 26
Assumption..................................... 36
Capability Level ............................... 5
communication ............................... 14
Constraint ....................................... 36
Critical Path Method (CPM) .......... 45
Customer ........................................ 18
Cynefin Framework ........................ 23
Decomposition................................ 38
Deliverables .................................... 11
documentation ................................ 15
Enterprise ......................................... 1
Enterprise Architecture..................... 1
enterprise continuum level ............. 27
evaluation ....................................... 59
Executive .................................. 12, 18
Expert Judgment ............................. 38
governance...................................... 25
Highlight Report ............................. 53
Implementation Plan......................... 4
initial risk assessment ..................... 30
iterative approach ........................... 23
Kanban method............................... 23
Lessons Log.................................... 20

76

Phase .............................................. 12
Project Charter ............................... 29
project controls ............................... 32
Project Evaluation and Review
Technique (PERT) method ........ 41
Project exclusion ............................ 36
Project Governance ........................ 25
Project Management......................... 3
Project Management methods .......... 9
Project Management Team ............ 27
Project Manager ....................... 12, 19
Project Teams ................................. 27
Project Work Package .................... 51
quality management approach........ 30
Request for Architecture Work ........ 4
Resources ....................................... 22
Risk ................................................ 13
risk log............................................ 30
Roadmap .......................................... 4
Scope .............................................. 13
SCRUM method ............................. 23
Segment Level.................................. 5
Sponsor........................................... 18
Stage ............................................... 13
stage plan........................................ 49
Stakeholder..................................... 14
stakeholder communication ........... 31
stakeholder identification ............... 31
stakeholder map ............................. 32
Steering Committee........................ 26
Strategic Level ................................. 4
team managers ................................ 27
waterfall approaches....................... 23
Work Breakdown Structure............ 38
Work Package ................................ 14

TOGAF® Series Guide (2018)



Source Exif Data:
File Type                       : PDF
File Type Extension             : pdf
MIME Type                       : application/pdf
PDF Version                     : 1.5
Linearized                      : No
Page Count                      : 88
Language                        : en-GB
Tagged PDF                      : Yes
Title                           : TOGAF Arch. Project Mgmt. Guide
Author                          : The Open Group
Subject                         : The Open Group
Creator                         : Microsoft® Office Word 2007
Create Date                     : 2018:05:08 13:51:07+01:00