Wolf_Research_Whirlwind_I_Checkout_Progress_Report_Jul63 Wolf Research Whirlwind I Checkout Progress Report Jul63
Wolf_Research_Whirlwind_I_Checkout_Progress_Report_Jul63 Wolf_Research_Whirlwind_I_Checkout_Progress_Report_Jul63
Wolf_Research_Whirlwind_I_Checkout_Progress_Report_Jul63 Wolf_Research_Whirlwind_I_Checkout_Progress_Report_Jul63
User Manual: Wolf_Research_Whirlwind_I_Checkout_Progress_Report_Jul63
Open the PDF directly: View PDF .
Page Count: 45
Download | |
Open PDF In Browser | View PDF |
WHIRLWIND I MOVING, REASSEMBLY ANI;? CHECKOUT PROGRESS REPORT JULY 1963 by Albert V. Shortell, Jr. WOLF RESEARCH AND DEVELOPMENT CORPORATIO\N, Baker Avenue and Route 2 West Concord, Massachusetts 'w 0,1' Research and Development Corporation P.O. Box 136; Baker Avenue, West Concord, Massachusetts EMerson 9-211 1 August 16, 1963 Mr. Alfred J. Wis e Special Representative Office of Naval Research Massachusetts Institute of Technology Cambridge 39, Mass achusetts Dear Mr. Wi~e: We are enclosing a report on the current st~tus' of the moving, reassembly and check-out of the Whirlwind I Computer. This report summarizes the activities and events compris'ing ·the moving and 1"eassemb,ly phase and the check-out phase. The activities and events of these two phases are also portrayed by means of two PERT networks. The PER T network descr-ibing the cheek-out phase presents' scheduled dates for completing the remaining events prerequisite to complete computer check-out. While these scheduled dates are based on our present best estimates, unforeseen problems may cause a further slippage in this s ched ule . Although this report provides considerable detail as to the present status of computer checkout, a visual demonstration of actual computer operation is more impress ive particularly now that we have a few, of the Whirlwind display demonstration programs operating. We would therefore like to extend an invitation to you, Mr. Healy, Professor Wilson and other ONR personnel to visit us again soon for the purpose of such a demonstration., ' Very truly yours~ ~${.4M. William M. President AVS/ csn Enc~osures wOlf-' TABLE OF CONTENTS I INTRODUCTION. II MOVING AND REASSEMBLY . . III . . . . 1 A. Rigging and Moving... B. C. D. Air Conditioning Installation Power Equipment ·2 . • t. 2 • 3 . . . . . . . . . . 3 Mechanical and Electrical Reassembly. 4 COMPUTER CHECKOUT . . A. Equipment Checked Out. 1. 13 13 . Power Equipment a. 13 Standby Alternator and Filament Power Distribution System . . . . . . . . b. DC Power Supplies. c. DC Power Distribution System v3. 4. 13 14 . 14 16 . . . . . 17 Arithmetic Element 18 Storage Element. 19 Cont ro1 Element. a. /b. c. 5. /' . . . . . . Marginal Checking System 2. , . Toggle Switch Storage and Parity Register . Flip Flop Storage . . .. 19 . . . .. 19 20 Core Memory . . . . 21 a. Control...... 21 b. Peripheral Equipment 21 Input -Output Element. 1) Flexowriter Keyboard Input, Reader/Printer, and Punch . . . . . . . . . . . 21 Photoelectric Tape Reader . . . 22 . 3) Real Time Clock. 22 /4) Test Control Display Scopes 22 Intervention: and Activate Registers 23 2) 5) . . . . . Table of Contents (Cont'd) ,Page B. 1. Power Equipment. /ct. b. 2. b. tiC. V . . . 23 . 400 Amp Alternator and Filament Power Distribution System . . . . . . .... DC Powe r Dist ribution System. Input -Output Equipment. \/a. IV· 23 Equipment to be Checked Out Display Consoles. c > 23 24 . 25 . 25 . Indicator Light Registers 25 Light Guns. 26 . . . . . d. Magnetic Tape Units 26 (e. IBM Card Machines 26 f. Anelex Alphanumeric Printer g. Test Control Camera . 27 h. Magnetic Drums . . 27 i. Teletype Input and Output .26 . 28 MAJOR PROBLEMS ENCOUNTERED TO DATE 33 A. B. Wire- Wound Resistors 33 400 Amp Standby Alternator Slip Rings . 35 C. Air Conditioning Equipment Trouble 36 D. Phenolic Breakdowns .. E. Power Failures SUMMARY . . .. ' . 38 40 42 LIST OF ILLUSTRATIONS Figure 2-1 Figure 3~1 PERT Network WWI Com.puter Moving and Reassembly 12 PERT Network '?fWI Com.puter Checkout. 32 . . . . . . LIST OF TABLES Table 2-1 Rigging and Moving (RM). 2-2 Air Conditioning Installation (AC) . 2-3 Power Equipment (PE)" 2-4 Mechanical and Electrical Reassembly (ME) . 3 -1 Check Out (CO) . "0 . • . . " • " . . . . . ,. . • . . 7 8 9 • . . . . . " " .. " " lq;i~l . " " 29-31 1 I INTRODUCTION This memorandum summarizes the present status of Whirlwind I I computer checkout and de sc ribes the wo rk ac complished to date in moving, reassembling and checking out the Whirlwind I computer in its new In addition, items of equipm~nt locat~on. yet to be checked out are desc ribed and scheduled. Section II describes the moving and reassembly phase which comm.enced on Decem.ber 6, 1961, and was com.pleted on Decem.ber 13, 1962. A PERT network showing the interrelationships and completion dates of the events comprising the m.oving and reas sem.bly phase is also presented. Section III describes the computer checkout phase which com.m.enced on Dec em.be r 19, 1962, and is scheduled for com.pletion on Novem.b e r 15, 1963. This section describes both work accomplished to date and work to be accom.plished by the scheduled date of Novem.ber 15, 1963. Section IV describes the major problems encountered'to date in checking out the com.puter. 2 II MOVING AND REASSEMBLY The moving and reassembly phase commenced on December 6, 1961, and was completed on December 13, 1962. Figure 2 -1 is a PERT network which depicts the interrelationships of events comprising this phase. Events are described by the circular. disks and the activities leading to these events are described by the printed paper tape whose length is proportional to the time required for the activity. Unprinted tape represents activities which require no time while unlabeled disks are merely connectors and do not represent events. Tables 2 -1 through 2 -4 inclusive identify each of the events in this network. The labeling of these events is similar to that used in our memorandum "Schedule for Moving and Reassembling the Whirlwind I Computer" dated October 6, 1960. Modification and additions to the tasks listed therein have been made where necessary. A. Rigging and Moving The events associated with rigging and moving are listed in Table 2-1. Moving of the air conditioning cooling towers (RMll) and ductwork (RM13) was accomplished on December 8, 1961, and the air handling units and associated controls (RM12A) were moved on January 16, 1962. Due to delays in building construction, the moving of the main computer racks (RM3, RM4, RM5 and RM7), which was originally scheduled for December, was delayed until February. Following this, the end wall of the computer section of the building was completed. The moving of rotating machinery and associated switch gear (RM14), DC power supplies (RM15), and air conditioning compressors (RMlO) had to be delayed until the completion of the mechanical room section of the building. These latter units were moved and set up in place by the latter part of March, 1962. Due to internal con- struction work such as electrical, plumbing and heating, and painting, the equipment racks could not be spread out and positioned until early April. This was done during the period April 5, 1962 through April 13, 1962, inclusive, and is described by events RM6, RM8 and RM17. listed under rigging an~ Other events moving in Table 2 -1 were accomplished at our con- venience as the equipment was needed but were scheduled so as' to vacate Navy Building 61 in South Boston before termination of our lease extension on June 30, 1962. 3 During the moving of additional equipment, it soon became obvious that additional storage space more convenient to Concord was a necessity. Consequently, 8400 square feet of warehouse space was leased in Maynard, Massachusetts. While not shown explicitly on the PERT network, the space at Building 61 in South Boston was vacated on or about May 29 J 1962. Events RMl and RM16 represent, respectively, the moving from Maynard to Concord of panels removed from the computer and the completion of the moving of additional equipment stored in our Boston office and in quarters adjac ent to our new building in Conc 0 rd. B. Air Conditioning Installation Table 2-2 describes the events associated with air conditioning equipment installation. The installation of the air conditioning equipment com- menced on May 23, 1962, with the installation of ductwork (AC3A) and electrical switchgear and control wiring (AC4A). Installation of refrigerant piping (ACl) was started early in June and was completed on July 31. Cornpletion of the rnajority of the ductwork (AC3C) and electrical wiring (AC4B) as well as pneumatic control installation (AC2B) was accomplished by August 2. Charging of the system with Freon and check out of the basic system (AC5B) was accomplished on August 4, 1962. Completion of remaining air conditioning work had to be delayed until receipt of a which provides room air cooling. n~w cooling coil for the air handler This coil was received during the latter part of September and completion of all air conditioning work (AC2C, AC3D, AC4C, AC4D, and AC5C) was accomplished on October 18, 1962. C. Power Equipment The tasks involved in installation of power equipment are listed in Table 2 -3. Two of the twelve events listed in this table were purpos ely ornitted from the reassembly phase of the project in order to perrnit an earlier start of the computer checkout phase. These two events, namely.. the wiring and checkout of the 400 amp alternator (PEl and PE5B) affect only the special input-output equipment, particularly the magnetic drums and thus were not essential to the checkout of the main computer. These events are yet to be accomplished but are scheduled on the PERT network presented in 4 Section III. A third event listed in Table 2 -3 (PEB) has been completed but is shown on the PERT network of Section III since it is more properly considered as a checkout event rather than a reassembly event. The remaining events listed in Table 2 -3 are portrayed in the PERT network of Figure 2-1., These commenced during the latter part of March, 1962 and were completed on December 13, 1962. These tasks in- volved the setup and wiring of the 400 amp standby alternator, associated power control racks and contactors (PE2, PE3A, PE3B, PE4, and PE5A), installation and wiring of computer DC power supplies (PE6A, PE6B, PE7, and PE9) and wiring, checkout, and- distribution of laboratory DC power (PEIO and PE 11). D. Mechanical and Electrical Reassembly The events associated with mechanical and electrical reassembly of the computer are listed in Table 2 -4. All but the last four events in this table were completed during the moving and reassembly phase and are portrayed in the PERT network of Figure 2-1. on the PERT network of Figure 3 -1. The last four events are scheduled One of these events (ME23) has been completed and the remaining three (ME24, ME25 and ME26) are scheduled for completion within the next ten days. These four events were purposely eliminated-from the moving and reassembly phase since they could be con~ veniently postponed without delaying the start of the checkout phase of the, project. The remaining events associated with mechanical and electrical reassembly were started early in April, 1962 and were completed on November 15, 1962. It should be pointed out that one of these events (ME14) was intentionally deleted from the PERT chart, since after a few weeks of checking it was concluded that the error rate of Northeastern students in reconnecting cables was sufficiently low to make exhaustive checking of cables unnecessary. It was decided that if power connections were checked out in a fail-safe manner that signal cabling errors could be tolerated without damage to the computer. This decision to bypass checking of wire and cable reconnections in great detail saved considerable time and has been proven to be a correct decision 5 during the checkout phase which is described in Section III. While exact figures on the error rate in reconnecting cables have not been kept, our best estimate is that this error rate was not more than 50/0 and was probably_ as low as 2 to 30/0. Considering the semi-skilled personnel perform.ing' this task, the fact that two different groups disconnected and reconnected the cables, and inevitable human error in recording and interpreting cable termination data, we feel that this record is extremely good. While the mechanical and electrical reassembly phase consisted of about 25 different tasks, the major portion of the job involved reconnection of wires and cables (ME13). on April 30, was This task, which was started cOlTIpleted on October 29. It shoul? be pointed out here, that thfs reconnection included all the ca_ble s which were disconnected at Cambridge, not only in the main computer but in the input-output equipment area associated with drums, radar and teletype inputs, and digital outputs. Thus, this"task involved about twice as much work as that defined as MEl3 in our memorandum nSchedule for Moving and Reassembling the Whirlwind I Computer" dated October 6, 1960, wherein we had planned to reconnect only those cables associated with the central computer. Other factors tending to lengthen this task included the fabrication of new cables to replace ones which were badly frayed and tangled at Cambridge, extending or replacing cables which proved, in a few cases, to be too short due to our relocation of test control relative to the main computer, and time spent in pulse checking each video cable prior to reconnection. Pulse checking of video cables has proven valuable during the checkout phase since the only video cable failures found to date during checkout have been in cables which were disconnected only at one end and which could not be pulse checked since their destinations were not known without considerable checking of MIT records. All other events associated with mechanical and electrical reassembly required relatively short times for their completion. For example, events MEl through ME7 inclusive were completed during the month of April, 1962. Other events which appear later during the schedule shown in the PERT network of Figure 2 -1 involved effort of a few days to two weeks and were accomplished as required and as time permitted. The activity paths,to most of these events represent time delays primarily. For example, 6 about 22 weeks elapsed between the installation of computer wireways and ground busses (ME5) and the completion of reconnecting computer wires which we had cut in Cambridge (ME 11). This latte r event (ME 11) required about a week of effort for its accomplishment. but due to manpower limitations was not started until the ,middle of September, ,1962. This manpower limitation was dictated primarily by efficiency considerations, since the size of the work~ng crew was about optimum, an increase in its size ..would have resulted in decreased effectiveness of the group. 7 TABLE 2-1 Rigging and Moving (RM) Event No. Desc ription Date Completed or Scheduled RM1 Removed Panels Moved July 21, 1962 RM2 Transformer Panels Moved April 15, 1962 RM3 Test Control, Core Banks and February 13, 1962 Drums Moved RM4 Computer Racks 0-7 Moved February 9, 1962 RM5 Computer Racks 8-15 Moved February 9, 1962 RM6 Computer Racks Positioned April 10, 1962 RM7 I/O 'Racks Moved February 9, 1962 RM8 I/O Racks Positioned April 13, 1962 RM9 Wire Boxes Moved April 15, 1962 RMIO Compressors Moved and Set Up March 26, 1962 RMll Evaporators Moved and Set :UP December 8,1961 RM12A Air Handling Units and Control January 16, 1962 Boards Moved RM12B Air Handling Units Set Up February 7, 1962 RM13 Ductwork Moved December 8, 1961 RM14 Rotating Mac;:hinery and Switch- March 26, 1962 gear Moved and Set Up RM15 DC Supplies Moved March 2'3, 1962 RM16 Remaining Equipment Moved June 12, 1962 RM17 TC Rack$ Positioned April 5, 1962 8 TABLE 2-2 Air Conditioning Installation (AC) Event No. ACI/ AC2A ~/ AC2B Description Date Completed or Scheduled Refrigerant Piping Com.pleted July 31, 1962 Sta rtConnecting Pneum.atic Controls August 1, 1962 ~\ Com.plete all Pneumatic Controls August 2, 1962 Except Room and Mechanical Room. AC2C Complete all Pneumatic Controls September 27, 1962 AC3A//, Start Ductwork Installation May_ 28, 1962 AC3B Complete Fresh Air And First JUly 6, 1962 J Section Supply Ducts AC3C Complete all Ductwork Except August 2, 1962 Room and Mechanical Room AC3D /' AC4A ,ft_/' Complete all Ductwork September 27, 1962 Start Electric Switchgear and May 28, 1962 Control Wiring AC4B Complete all Wiring Except Room July 29, 1962 and Mechanical Room Controls AC4C Start Remaining Wiring October 12, 1962 AC4D Complete all Wiring October 15, 1962 1/'- Start System Checkout August 3,' 1962 1- Complete Basic System. Checkout August 4, 1962 Complete System Checkout October 18, 1962 .AC5A AC5B AC5C 9 TABLE 2-3 Power Equipment (PE) Desc ription Event No. * PEll Date Completed or Scheduled 400A Alternator Wired August 14, 1963 400A Standby Alternator Wired June 22, 1962 PE3A I- Power Control Racks Set Up April 6, 1962 c/ Power Control Racks Wired October 15, 1962 Filament Contacto r s Wired to October 26, 1962 PE2 ;PE3B ~ PE4 Busses 1"/ PE5A * PE5B PE6A j--' PE6B /' PE7 //' ** PEB PE9 PEI0 y" v' Standby Alternator Checked Out December 13, 1962 400A Alternator Checked Out August 20, 1963 DC Supplies Installed in Racks June 9, 1962 DC Supplies Wired October 12, 1962 AC Inputs to DC Supplies Wired October 12, 1962 DC Supplies Checked Out January 17, 1963 DC Supplies Wired to Busses August 17, 1962 Lab. DC Supplies Wired and June 29, 1962 Checked Out PE11 Lab. DC Distribution Completed October 16, 1962 *Incomplete as of July 31, 1963. Desc ribed and scheduled in Section III. ** Des(f:ribed and scheduled in Section III. 10 TABLE 2-4 Mechanical and Electrical Reas sembly (ME) Event No. Dese ription Date Completed or Scheduled MEl v Floor Marked for Computer Racks April 6, 1962 MEl r Floor Marked for TC Racks April 2, 1962 Floor Marked for I/O Racks April 10, 1962 Junction Box Mount Completed April 18, 1962 Computer Wireway and Ground April 26, 1962 ME3 )// ME4 r ME5 j/' Bus Installed ME6A Start 'Test Control Wireways April 16, 1962 ME6B Test Control Wireways Installed April 27, 1962 ME7 I/O Wireways and Ground Bus April 27, 1962 Installed ME8 ' . Removed Panels Replaced JUly 26, 1962 ME9A ,!,.,.,.". Transformer Panels Replaced April 20, 1962 ME9B l:r Transformer Panels Rewired August 10, 1962 Filter Panels Replaced November 15, 1962 Bus Ba r s Installed July 18, 1962 Computer Cut Wires Reconnected September 26, 1962 I/O Cut Wires Reconnected September 27, 1962 Start Reconnection of Wires and April 30, 1962 ME9C':,MElO MEll v ","'" V MEl2 MEl3A t Cables MEl3B ME14 . ~. f-.-/ Reconnection of Cables Completed October 29, 1962 Reconnectionof Cables Checked Deleted Out ME15 Interco;rn Reconnected and Checked Out September 14, 1962 11 TABLE 2-4 Mechanical and Electrical Reassembly (ME) (Cont'd) Event No. ME16 Date Completed or Scheduled Description j,-/ Transformers in Banks A and B October 25, 1962 Replaced ME17 ME18 p/ j/ Core Stacks A, Band C Installed October 29, 1962 Drum Bearings Checked and September 24, 1962 Replaced if Required ME19 ["./ ME20 Drums Installed September 28, 1962 AC and DC Power for TC October 3, 1962 Installed ME2l v ME22 J unction Boxed Repo s itioned October 5, 1962 Test Bench for Drum Chassis September 24, 1962 Installed ** ME23 1-/ I Construct Anelex Transition Panel April 11, 1963 * ME24 y/ Install Anelex Cabling " August 9, 1963 * ME25 y August 9, 1963 Repair Brush Box,es on 400A Alternator * ME26 / ' Recable 3 Display Consoles *Incomplete ; as of July 31, 1963. August 2, 1963 De,scribed and scheduled in Section III. >:C*Described and scheduled'in Section III., I I., 13 III COMPUTER CHECKOUT The checkout phase commenced on December 19, 1962 with the completion of checking the standby alternator cycling system from the alternator output to the computer busses and thence to the computer racks. That is, filament power was applied to all of the main computer racks. Checkout ,is scheduled to be completed on Novembe r 15, 1963 with the com -:. pletion of checkout of the teletype input subsystem. '. Presented in Figure 3-i is a PERT network which describes the activities and events comprising this phase of the project. listed in Table 3 -1. All but seven of the events in this network are As mentioned in Section II, the remaining seven event's, (PEl, PE5B, PEB, ME23, ME24, ME25, and ME26) have been carried over from the moving and reassembly phase as their accomplishment was not essential to the start of the checkout phase and it was more convenient to defer action on these tasks. 2 -4 of Section II. These tasks are described in Tables 2-3 and Two of these seven events (PEB and ME23) have already been accomplished; the remaining five are scheduled to be completed within the next three weeks. It should be noted that our October, ~960 moving schedule memorandum has no counterpart of Table 3 -1, since the 1960 memorandum scheduled only the moving and reas~embly ! I but not the checkout of the computer. Section A below describes equipment already checked out during the checkout phase, while Section B describes tasks involving equipment yet to be checked' out. A. Equipment Checked Out 1. Power Equipment a. Standby Alternator and Filament Power Distribution System) As mentioned above, the checkout phase began on December 19, 1962 with the success~ul completion of checking of cycling of the standby alternator to the computer busses (COl) and thence to the computer racks (C02). These two events were completed with very little difficulty. Power was cycled on to groups of eight racks at a time with several personnel 14 st~nding by to warn of trouble so that power could be reITloved immediately, thereby minimizing damage to the computer panels. As power was applied succes sfully to each group of eight racks, the filament voltage was then cycled down, eight more racks were turned on and observed for signs of trouble as the filaments were cycled back on. This procedure of adding modules of eight racks to previously checked racks with alternate cycling on and off of the filament power was repeated until filament power was successfully applied to all the racks in the main computer including the core memories. The success of this operation is indicated by the fact that the entire process was completed in a period of about four hours. Other than a difficulty due to voltage breakdown in the standby alternator slip rings, which occurred on April 12 a.nd which is described in Section IV -B,asic input-output devices. More detailed checking of the multiply, divide and shift operations was again undertaken on July 15 and was completed on July 30, 1963. D':lring the initial check 19 of Arith:metic Element operation (CO 17 A) most of the troubles were corrected .by replacing all the 2000 ohm ten watt wire -wound resistors with 2000 ohm twelve watt wire-woundresistors and replacing several of the matched pairs of flip-flop tubes. The few remaining troubl~s were corrected by replacing a small quantity of gate tubes and rectifying a few video cabling errors. During the recent final check of the Arithmetic Element (C017B) troubles with the multiply, divide, and shift instructions were found to be caused by pulse repetition frequency sensitivity when shifting alternate l's and a's through the flip-flops of the B-Register and Accumulator. Further investigation revealed that this sensitivity could be eliminated by replacing the 1600 ohl;'n I ten watt resistors in the flip-flop circuits with 1600 ohm twelve watt resistors. Since multiplication is basically an add and shift operation, and since divid,e is basically a subtract and shift ope ration, elimination of the shifting probl'erns. also cured the multiply and divide problems. 4. Storage Element a. Toggle Switch Storage and Parity Register Checkout of Toggle Switch Storage and the Parity Register (GalS) as well as the Storage Switch was performed concurrently with the initial check of the Arithmetic Element and the checkout of FlipFlop Storage. This event was accomplished on April 22, 1963. Troubles with the Toggle Switch Storage Registers and the Storage Switch were corrected by replacing ten watt resistors with twelve watt resistors, replacing several defective 6Y6 tubes, and by replacing several wires which had been cut when the computer was moved and which had been poorly butt connected. Troubles with the Parity Register were cleared up mainly by replacing flipflop tubes and/or flip-flop plug-in units., b. Flip-Flop Storage Checkout of Flip-Flop Storage (CO 16) also proceeded concurrently with the initial check of the Arithmetic ·Element. As with the Arithmetic Element, most of the troubles with Flip-Flop Storage were corrected by replacing 2000 ohm ten watt resistors with twelve watt resistors and replacing several matched pairs of 6145 flip-flop tubes. A few other troubles were corrected by replacing defective crystal diodes and correcting two wiring errors in the Flip-Flop Storage reset switches. 20 c. Core Memory AC and DC power were initially applied to core memory Banks A and B on May 15 and to core memory Bank C two days later. After correcting two video cabling errors and replacing a defective video cable, proper operation of the Memory Address R~gisters was accomplished. At this point it was then possible to attempt writing into and reading from registers in each core bank. Parity errors were encountered in Banks A and B but a check of a few registers in each of the four core fields in Bank C seemed to indicate that this bank was working perfectly. The initial success of operation of Bank C and initial failure of Banks A and B was due, in pa rt, to adjustment of read and write currents. Read and write current controls in Banks A and B had been misadjusted during the move) whereas the controls in Bank Care locked and had not been disturbed by the moving process. The current controls in Banks A and B had been roughly reset in accordance with some photographs we had taken in Cambridge prior to computer disassembly. More precise adjustment of the read and write current controls in Banks A and B with an oscilloscope made some improvement in operation of these cores but did not entirely correct the problems. It was then discovered that most of the remaining troubles in Banks A and B were due to faulty operation of digit plane driver plug-in units which were failing to provide proper inhibit currents and \ were causing parity alarms. Troubles with these plug -in unit digit plane drivers were found to be due to open ten watt non-inductively wound resistors. Since we had good operation from the 4000 core registers in Bank C at that point, it was decided to reduce our efforts on checking core memory so that checkout of the input-output system, the Flexowriter and photoelectric tape reader could be expedited. Further checking of Bank B suddenly revealed that the parity error problems were not entirely due to faulty digit plane driver operation when it was discovered that the cables from the digit plane drivers to the core. planes had been completely reversed. Correcting this cabling error and repairing the digit plane drivers seemed to clear up all core memory troubles for a period of ahout two weeks. However, with the onset of very hot weather toward the latter part of June, troubles developed in all 21 core banks and we were suddenly forced to concentrate all our efforts on checking core memory again. Some of the troubles were evidenced by blown fuses, probably due to overheating, which resulted from a lack of Freon in the air conditioning system. The system, as described in Section IVe, had been found to have lost all Freon during the latter part of May. Over- heating problems during the hot weather at the end of June subsequently revealed that we had underestimated the Freon capacity of the system and had replaced only about half of the required amount of Freon. During the first week of July, a more exhaustive check of all core banks was made. Troubles with Bank C were cleared up by replacing two broken tubes, two blown fuses, correcting an open circuit in a common ground line on a selection plane driver due to a poor solder joint, and replacement of a burned out 5998 tube in a selection plane driver panel. 5. Input -Output EleITlent a. Control Checkout of the In -Out Element (CO 19) was accomplished with very little difficulty by June 5, 1963. The only difficulty encountered with the In-Out Register was the failure of one flip-flop which was corrected by replacing the flip-flop tubes with a new matched pair of 6145 IS. Troubles with the In-Out Delay Counter were corrected by replacing a missing gate tube and two defective video cables which were responsible for failure to terITlinate block transfer. instructions. Difficulties with the In-Out Switch were corrected by replacing a missing 6Y6 tube which drives the clear line to the flip-flops of the In-Out Switch and by replacing an open 22, 000 ohm twelve watt wirewound resistor in a cathode follower. This cathode follower was failing to shut off a gate tube in the clear line to the In-Out Switch flip-flops and was thus permitting spurious clear In-Out Switch. puls~s to interfere with proper operation of the Operation of the In-Out Element to date has been excellent and no failures have been encountered since the above troubles were corrected. b. Peripheral Equipment 1) Flexowriter Keyboard Input, Reader/Printer, and Punch Checkout of the Flexowriter direct keyboard input, direct printer and 'punch output and mechanical paper tape reader input (C022) was accomplished on June 5, 1963. The only difficulties encounteredhere were caused by two wires which were incorrectly connected. 22 2) Photoelectric Tape Reader Checkout of the Ferranti Photoelectric Tape Reader (C023) was also accomplished with very little difficulty. Three troubles were encountered here, two due to missing DC voltages, the third due to failure of one of the digits to read to the In-Out Register. One of the missing voltages was due to a wiring error, the other was due to a broken wire. The failure to read one of the digits to the In-Out Register was corrected by tightening a tube which was loose in its socket in an In-Out Register Input Mixer panel. 3) Real Time Clock Checkout of the Real Time Clock (C032) was com- pleted on June 13, 1963. Trouble with the clock was corrected by rectifying one video cabling error and replacing an indicator light bracket. 4) Test Control Display Scopes Successful completion of event C027 A was accom- plished on June 19, 1963. This task included checkout of all the control elements o.f the display subsystem as well as the two display scopes in Test Control. Troubles encountered in this area included failure of the vertical deflection signal which was caused by a bad 5651 voltage regulator tube in the Vertical Decoder, failure of vertical deflection on one scope due to a loose wire on a binding post, and a cabling error which caused the horizontal and vertical deflection signals on one scope to be interchanged. Troubles with the .individual scopes were encountered in the Dumont high voltage power supplies and in the deflection amplifiers. Troubles with the Dumont high voltage supplies were corrected by replacing a broken high voltage coil and two open wire -wound potentiometers. were corr~cted Malfunctions in one of the horizontal deflection amplifiers by replacing defective tubes. After correcting these dif- ficulties, prope r operation of point displays, characte r displays, and vector displays was accomplished by aligning the deflection decoders, the decoder output amplifier, and the scope deflection amplifiers in accordance with procedures established at MIT. 23 5) Intervention and Activate Registers The Intervention and Activate Registers (C02S) were also checked out on June 19. The only difficulties encounte'red with these subsystems were caused by missing voltages on the switches in, Test Control, two video cabling errors, and a fuse blowing problem associated with the cathode followers which enable the read-out gates of the individual Intervention Registers. The fuse involved kept blowing repeatedly and the trouble was finally cleared up by replacing it with a larger size fuse after determining that the fuse rating was too low for the amount of current being drawn by these cathode followers. B. Equipment to be Checked Out Several more units of input -output equipment remaiI). to be checked before the computer can be considered to be completely checked out. These include principally the magnetic tape units, the IBM card machines, the 'Anelex printer, three additional display consoles, and the two magnetic drums. In addition, the 400 amp alternator which provides filament power to the magnetic drums and associated input -output equipment requires some repair and must be rewired. Also, the power distribution system, both AC and DC, for the magnetic drums and associated equipment must be checked out. Some checkout work has been done in each of these areas with the exception of ,the drums. Many of these jobs are scheduled to be completed within the next few weeks and present indications are that all work should be completed on or about November 15, 1963. 1. Powe'r Equipment a. 400 Amp Alternator and Filament Power Distribution System Work on repairing the brush boxes on the 400 amp Alternator (ME25) is scheduled to start the latter part of this week. Prelim- inary investigation into this problem indicates that replacing of the slip ring~ may be a more desirabl,e long-term solution. We are awaiting information from the manufacturer, which will determine just how much wear on the , rings has occurred. sl~p \ After talking with the manufacturer's local representativ.~, 24 there isa slight possibility that the solution to the problem may be merely the use of a different type of brush than that used by MIT. Data from the factory giving original dimensions of the slip rings will be the deciding factor on whether or not these will be replaced. If it is necessary to replace the slip rings, there is a good pos sibility that a new pair may be available from stock. ~ If the slip rings are not available from stock, then a two week delivery period is quoted. In this latter event, it would be necessary to postpone further work on the slip rings for two weeks. However, other tasks as sociated with the alternator could be performed sooner so that the two week delivery delay .will not impose any slippage on the existing schedule. Reconnecting the cables from this 400 amp alternator (PE I) has been planned and presently is scheduled to be accomplished after the slip ring problem is corrected.. However, if it is necessary to wait the two weeks for slip ring delivery, the wiring of the alternator can be done first. Checkout of the 400 amp alternator (PE5B) is presently scheduled to be completed by August 20. No difficulty is ant,icipated in accomplishing this task as scheduled, even if it is necessary to wait two weeks for delivery of slip rings. After checking out the operation of the 400 amp alternator, the next tasks will be to check the 400 amp alternator cycling system and connections to the in-out filament busses (C034) and the filament connections to the individual in-out equipment racks and to the drum bays (C035). With the exception of the feeder cables from the 400 amp alternator, all the necessary filament power cycling and distribution wiring was completed during the moving and reassembly phase last year. Thus, little difficulty is foreseen in completing these two tasks by the end of August. b. DC Power Distribution System After checking filament power connections to the in-out equipment racks and drums, it will be necessary to check the DC connections to these equipments. Two tasks are involved-the first, checking of the DC supplies to the in-out equipme~t busses (C036) and the second, checking the 25 DC power distribution to the individual racks and drum bays (C037). The only difficulties anticipated in connection with these two tasks are in checking DC power connections to the drum bays and the connection 9f rack DC switches which control the outputs of the power distribution panels to the associated racks and drum bays. Connection of the outputs of the power distribution panels to the individual racks should give no trouble, since unlike the racks in the main computer, most of this DC wiring did not have tobe disconnected. The scheduled date of September 20 for completion of DC checking should be accomplished without difficulty. 2. Input -Output Equipment With the exception of the Anelex printer, magnetic drums, teletype input, and teletype output on which no checking has yet been done, checkout of remaining input-output units has been done to some degree. a. Display Consoles Three display consoles, in addition to the two in Test Control already checked out, are planned. and checkout is nearly completed. just been started. Two of these have been recabled The third display console recabling has When cabling of this scope is completed, event ME26 will have been accomplished. Completion of this event is scheduled for August 2, but may slip one or two days. Complete checkout of these three display consoles will accomplish event C03l 'on or about August 7. The only diffi- culties anticipated in checking these three displays are troubles with the Dumont high voltage power supplies, alignment problems in the deflection amplifiers, and a few minor wiring errors. b. . Indicator Light Registers Completio~ of checkout of all Indicator Light Registers required at present (C030) is expected to occur concurrently with the completion of the checkout of three display consoles mentioned in a. above. Most of these registers have been checked and it is felt that remaining troubles are due to defective thyratrons in these registers or to one or two· wiring errors. 26 c. Light Guns Three light guns are being checked out for use with the three display consoles mentioned in a. above. Two light guns have been reconnected and one of these has been checked out completed while the third is being connected with the third display console. Completion of light gun checkout (C029) is also scheduled to coincide with the completion of checkout of the three display consoles. No difficulties other than tube failure and minor wiring errors are anticipated. d. Magnetic Tape Units Checkout of the znagnetic tape units (C026) is scheduled to be completed on August 12. are all the manual controls. Mechanically these units are operational as Thus, all the remaining troubles with these units are electronic and it is not anticipated that any serious difficulties will be encountered here. e. IBM Card Machines All the wiring for the IBM card machines was checked very thoroughly during the moving and reassembly phase last fall. The IBM 523 gang summary punches used with this system are in good mechanical shape. These two machines, which were specially modified by MIT for use with Whirlwind, were being leased from IBM by MIT. The Wolf Research and Development Corporation took over the lease from MIT and has since purchased the machines outright from IBM. Since the wiring associated with these card machines has been thoroughly checked, checkout of the Whirlwind card machine· system (C024) should be a fairly straightforward task and should be completed around August 15. f. Anelex Alphanumeric Printer The Anelex Alphanumeric Synchroprinter used with Whirlwind was not acquired from Lincoln Laboratory until September, 1962. As the task of reconnecting computer wires and cables was nearly completed at that point, it was decided to defer recabling of the Anelex printer until the checkout phase. All units of the Anelex printer system were acquired from Linc9ln with the exception of the transition panel which could not be located in their warehouse. Thus, it was necessary to build a new transition panel and 27 this task (ME23) was com.pleted on April 11 of this year. Recabling of the Anelex equipment has been partially completed over the past couple of months as time permits. Presently, this task (ME24) is about half completed and is scheduled for final completion on August 9. Operational checkout of the Anelex system will be accomplished during the last two weeks of August with a scheduled date of August 30. Here again, little difficulty is anticipated particularly since one of our engineers has had considerable experience with the operation of this printer at MIT. g. Test Control Camera Some difficulties wi~h the checkout of the Test Control ) camera subsystem were encountered during June when the Test Control Display Scopes were checked out. This is not a very' complicated system, but MITis drawings and records associated with this system are in very poor shape and apparently a few wiring errors were made in reconnecting the camera. At present, the camera can be indexed manually but not by program command. One of the known troubles is that about six plug-in units are missing from this subsystem and were missing, according to our records, when we acquired responsibility for the computer. Also, because of the poor records involved, about two dozen wires will have to be traced manually before the cam.era can be checked out. Since this is a relatively low priority item, it has been deferred until the first week of September and this task (C027B) is scheduled for completion on September 4. While this job will not take more than two or three days, the amount of effort is out of proportion relative to the complexity of the system due to the poor records available. h. Magnetic Drums Checkout of the Auxiliary Drum (C038) is scheduled for October 11 while checkout of the Buffer Drum (C039) is scheduled for November 8. These two tasks cannot be started until AC and DC checkout I (C034, C035, C036, and C037) of the drum bays and associated input-output equipment is completed. It is somewhat more difficult to anticipate what troubles may be encountered in checking out the drums, but possible trouble sources include adjustment and alignment of read and write heads, cabling 28 '. errors between the drums and the main computer, troubles with the electronic chassis in the drum bays, and possible difficulties with drum bearings. A preliminary check of the condition of the drum. bearings was made during the moving and reassembly phase. This check indicated that the drum bearings are in good shape and that the oil leakage problem. was due to over filling of the oil reservoirs ~t MIT. Although we have not been able to obtain mechanical assembly drawings for the drums from Sperry Rand, we do know that the bearings are commercially available. We have also been advised by Sperry Rand that the run down time from full speed to rest when power is removed should not be less than 2-1/2 to 3 minutes after the drum has been running for one hour. bearing troubles. A shorter run down time would indicate As for bearing life, Sperry Rand indicated that the bearings should be good for at least another ten years on the basis of usage to date by MIT. We feel that our present schedule makes ample provision for any diffi- culties which may be encountered in checking out the drums. i. Teletype Input and Output Thorough checking of teletype input and output subsystems requires a teletype transmitter distributor, a typing reperforator, and a Type 28RO teletypewriter. Since we have no immediate plans for use of these sub- systems, we will be able to check out only those portions of these subsystems which can be checked without the teletype equipment mentioned above. A reasonably thorough check of the electronics can be made by means of the Teletype Test Message Generator on a closed loop basis with a computer program. and this type of checking is all that is planned for the accomplishment of events C033 and C040. Checking of the teletype input subsystem which uses slots on the buffer drum cannot be started until checkout of the buffer drum. is completed, however. 29 TABLE 3-1 Check Out (CO) Event No. COl Desc ription Standby Alternator Cycling to Date Completed or Scheduled December 19, 1962 Computer Bus C02 AC to Computer Racks December 19, 1962 C03 DC Supplies to Computer Busses January 21, 1963 C04 DC to Compute r Racks February 28, 1963 COS Ma rginal Checking System April 30, 1963 C06 Pulse Generator, Frequency February 28, 1963 Divider, and Restorer Pulse Generator C07 Clock Pulse Control February 28, 1963 C08 Time Pulse Distributor February 28, 1963 C09 Test Control Synchronizers February 28, 1963 COlO Alarm System May 10, 1963 COlI Control Switch March 15, 1963 COl2 Ope ration Matrix. March 15, 1963 COl3 Control Pulse Output Units March 15, 1963 COl4 Program Counter April 23, 1963 COIS Toggle Switch Storage and Parity April 22, 1963 . Register C016 Flip Flop Storage May 16, 1963 C017A Initial Check Arithmetic Element May 16, 1963 C017B Final Check Arithmetic Element July 30, 1963 C018A Initial Che'ck Core Memory June 4, 1963 C018B Final Check Core Memory July 3, 1963 30 TABLE 3-1 Check Out (CO) (Cont'd) Event No. Description Date Completed or Scheduled C019 In-Out Element June 5, 1963 C020 Check Register May 10, 1963 C021 Start I/O Equipment Check June 5, 1963 C022 Flexowriter Keyboard Input, June 5, 1963 Punch, Reader and Printer >:< >!< >!< >!< C023 Photoelectric Tape Reader June 5, 1963 C024 IBM Card Machines August 15, 1963 C025 Anelex Printer August 30, 1963 C026 Magnetic Tape Units August 12, 1963 C027A Test Control Displays June 19, 1963 C027B Test Control Camera September 4, 1963 C028 Intervention and Activate June 19, 1963 Registers * C029 >!< >:( Light Guns August 7, 1963 C030 Indicato'r Light Registers August 7, 1963 C031 Display Consoles (3) August 7, 1963 C032 Real Time Clock June 13, 1963 C033 Teletype Output September 13) 1963 C034 400A Alternator C'ycling to Bus August 23, 1963 C035 AC to I/O Racks August 30, 1963 C036 DC Supplies to I/O Busses September 6, 1963 ~:c >!< >!( >!< 31 TABLE 3-1 Check Out (CO) (Cont'd) Event No. * C03? De sc ription Date Completed or Scheduled DC Supplies to 1/0 Racks September 20, 1963 C038 Auxiliary Drum October 11" 1963 C039 Buffer Drum November 8, 1963 ~O40 Teletype Input November 15" 1963 ~:c ):c ):c *Incomplete as of July 31" 1963 33 IV MAJOR PROBLEMS ENCOUNTERED TO DATE During the checkout phase, we have encountered several major problems. Two of these, namely troubles with defective wire-wound resistors and phenolic breakdowns had been anticipated. Two other difficulties, one with slip rings on the 400 amp standby alternator, and the other, troubles with the air conditioning equipment, occurred unexpectedly. We felt that we had solved the wire-wound resistor problem last Summer when we replaced all the existing 8 watt wirewound resistors in the computer, but unexpected difficulties were encountered with these new res istors. Phenolic breakdowns did not occur initially and for several months. We had finally reached a point where we felt the problem did not exi st when a rash of such trouble s occurred. Except for wire-wound resistor problems, failure rates of other electronic components have been much lower than we had anticipated. In particular, vacuum tube failure has been extremely low as has failure of crystal diodes. Relay operation has also been excellent and we have encountered trouble with only one relay out of more than 2000. A. Wire-Wound Resistors Tests of wire -wound resi stors at Navy Building 61 during the Summer of 1961 indicated a need for replacing all such resistors in the computer panels. The sample tested indicated about 75% of these resistors had opened up since the computer was shut down in May, 1959. During the Summer of 1962, new military RW3lG ten watt wire-wound resistors were purchased to replace the 8 watt resistors in the computer panels. These resistors were carefully bridged on a Wheatstone Bridge and matched to within 10/0 tolerance of nominal value and of each other as specified in Whirlwind records. Two students from Wentworth Institute were hired for the Summer and were assigned the task of replacing these resistors. Although MIT had replaced some 6f the 8 watt resistors with 12 watt resistors of a type similar to that which we purchased, our decision to purchase 10 watt rather than 12 watt resistors was based on two factors. 34 First, the 10 watt resistors which we purchased were the same physical size as the 8 watt resistors to be replaced, whereas the 12 watt resistors are longer and present some mechanical problems in :mounting. Second, it was known that 12 watt wire -wound resistors were a standard stock item at Lincoln Laboratory and were therefore easier to obtain than the 10 watt resistors. Although it was obvious that 10 watt resistors would certainly handle the power dissipation since the original resistors were only rated at 8 watts, we did compute the power dissipation in these resistors and found that the. results, namely dis sipations ranging from 2 to 4 watts, confirmed our conclusions. At this point we felt that we had solved the problem and due to other urgent tasks we assigned the resistor replacement job to the Wentworth students. During the latter part of the Summer of 1962·, some pulse checking was done on the Control Element and the resistors which had been replaced here seemed to give very satisfactory performance. However, in the Spring of 1963 while checking the operation of the Program Counter, difficulty was encountered with self-sustained os cillations in many of the flip-flops in the Program Counter. After a few days of intensive bench testing of one of the Program Counter panels, and review of early MIT records and memos for indications of such troubles in the past, it was determined that the cause of the trouble was primarily the 2000 ohm 10 watt resistors. Although each flip-flop contains two, 2000 ohm resistors, two 5000 ohm resistors, and two 1600 ohm resistors, in the vast majority of cases proper operation of flip-flops with voltage margins of plus or minus 30 to 40 volts has been accomplished merely by replacing the 2000 ohm ten watt resistors with 2000 ohm twelve watt resistors. Recently, however, it has been neces sary to change the 1600 ohm resistors in the Accumulator Parital Sum flip-flops and the B -Register flip-flops to obtain proper shifting operations. 35 A series of tests on ten and twelve watt wire wound resistors run by the manufacturer at our request revealed the probable cause of the problem. These tests measured the resistance and inductance of both ten and twelve watt resistors at l, 2 and 5 megacycles. The results sho~ed that the effective AC resistance as a function of frequency increased much faster in the case of the ten watt resistors than in the case of the twelve watt resistors. This was particularly true in the case of the 2000 ohm resistors and the trouble is assumed to be due to the smaller wire size used to get the same resistance in the smaller ten watt resistors. While most computer operations are performed at a maximum speed of 1 megacycle, shifting in the Accumulator and B -Register is done at 2 'megacycles and thus the 1600 ohm resistors also had to be replaced . ,to cure this latter problem. While most of the open wire-wound resistors found to date have been of the eight watt Navy-type, there have been other instances of open wire-wound resistors. Several commercial ten watt, non-inductive wire- wound resistors in the digit plane drivers of Core Memory Ban-ks A and B were found to be open, and one 22, 000 ohm, twelve watt resistor' used in a cathode follower in In-Out Control was also found to be open. Just this week, trouble developed in an A-Register panel and this was traced to an open 2000 ohm twelve watt resistor which had been installed at MIT in place of an eight watt resistor. Environmental conditions to which the computer was subject during the storage period are felt to be the cause of open wire -wound resistors. Since the computer was stored in unheated space, it is felt that the low temperatures encountered during the winter months caused the wire to become brittle and that contraction of the wire at these low temperatures caused it to break. B. 400 Amp Standby Alternator Slip 'Rings On April 12, after nearly two months of trouble-free operation, difficulty was encountered with the 400 amp standby alternator. This trouble was evidenced by a higher than normal field current which could not be adjusted downward to give proper operation. Field resistance from pole to pole was checked and found to be additive in a non-linear fashion, despite the fact that the individual pole resistances were measured to be two ohms, which is the corr¢ct value. The inescapable colusion was that somehow additional parallel resistance was being interposed between the two field terminals. Further checking revealed that the screws supporting the slip rings were too long ,and 36 nearly shorted the slip rings together. A carbon buildup on the ends of these screws was producing a twelve ohm resistance between the slip rings with the field disconnected. The screws were removed and replaced with shorter ones and this corrected the trouble. While the long screws were obviously a manufacturing defect, the elapsed time meter indicated that the machine had run for some 17, 000 hours prior to occurrence of this trouble. While this trouble would have occurred eventually, its onset m.ay have been hastened by an accident which occurred a few days earlier .. At that time, it was noticed that power was being applied to a relay as sociated with the magnetic tape racks. When the filament, switch for the tape racks was switched to what was thought to be the off position to turn off this relay, two No. 10 filament wires suddenly burned up. . When this switch was thrown, it effectivley placed a short across the output of the 400 amp standbyalternator\ due'to some temporary jumpers which had been installed last summer and which had not been removed. 'This sudden overload on the alternator burned up these wires, rather than blowing the 600 amp fuse in the output of the alternator. Thu~, this accidental overload probably hastened the breakdown between slip rings. Although the slip ring breakdown was in the ;motor exciter, investigation of the alternator exciter revealed that oversized screws had been used there as well. To prevent future troubles, the screws in the alternator exciter were also replaced with shorter ones at that time. c. Air Conditioning Equipment Trouble During the week of May 20 to May 24 we encountered our first heat wave of the summer season. Twice during the week the computer shut itself down as a result of excessive temperature in the vicinity of the overheat thermostat. We concluded, at first, that the trouble was due to dirty filters in the liquid line which were causing inefficient ope ration of the air conditioning system. On May 24, however, the air conditioning contractor, who had installed the system, came to replace the filter elem.ents. We were told that the difficulty was due to a nearly complete los s of Freon in the system.. Consequently, the system had to be completely leak checked and then refilled with Freon .. While leak checking, a few small leaks were found and corrected 37 and it was concluded that the Freon loss :must have occurred over a long period of ti:me due to these s:mall leaks. To prevent future losses of such proportion l a schedule of periodic leak checking was instituted. Prior to the Freon loss 1 the syste:m was shut down each evening l :merely by turning off the :main· circuit breaker to the air conditioning syste:m. After replenishing the Freon supply 1 this procedure resulted in severe slugging of the co:mpressors with liquid Freon during the night. To alleviate this slugging proble:m 1 it was decided to let the syste:m run continuouslYI even though unattended safe devices. l since it is :more than adequately protected with fail- On MondaYI June 171 exactly one week after instituting twenty- four hour operation, we arrived to find the syste:m shut down and the floor covered with oil. So:meti:me during the week-end the nu:mber 4 co:mpressor had blown a flare fitting in an oil line which resulted in co:mplete loss of oil in the entire syste:m and very possibly si:multaneous loss of a. few cylinders of Freon. The oil fitting was replaced and fifty gallons of Capella oil were added to replenish the oil supply. Following the oil loss, twenty-four hour operation of the air conditioning syste:m was abandoned and instead the syste:m is shut down each evening after pu:mping the Freon back into the receiver to prevent slugging of the co:mpressors. This procedure has worked reasonably well, but this was not the end of our air conditioning troubles. During a heat wave at the end of June, it beca:me obvious that the air conditioning syste:m was still not operating properly and the co:mputer again shut itself off due to overheating. After checking several possible causes of the trouble, it was finally concluded that additional Freon was required. More careful checking revealed that we had replenished only half the original supply of Freon at the ti:me of the loss in May. Additional Freon was added to bring the system up to capacity and, in addition, the cooling coils were washed down and several adjust:ments :made to the syste:m. These :measures have resulted in excellent operation of the air conditioning syste:m during the :month of July and particularly during the excessively hot days from. Wednesday, July 24 through Friday, July 26. 38 During July we have had several occassions on which we thought additional Freon loss might have occurred. and subsequent ~fficient However, thorough leak checkin~ operation indicate that these were false alarms. The most recent of these occassions was on'Monday, July 29, the sixth and final day of a period of unseasonably hot weather. Due to the hot weather over the week-end with the system shut down, the system was taxed to its utmost to overcome the accumulated heat load of the week-end, without the additional heat load of the compute r. Two small leaks we re found on Monday and corrected, but low Freon indication at that time was follo.wed by extremely good operation on Tuesday, which was a much cooler day. Low Freon indica- tion on Monday is now felt to be due to some los s of Freon at the time of the oil leak in June, which means that two or three cylinders of Freon should probably be added to bring the system up to full capacity. D. Phenolic Breakdowns Our first encounter with what recent experience indicates was probably a phenolic breakdown occurred on May 20, nearly three months after power was first applied to the computer panels. No further trouble was encountered until July 11, when we encountered the first of six phenolic breakdowns in a two week period, four of which occurred in one panel. The phenolic breakdown problem had been a matter of considerable concern to MIT and, as mentioned in previous progres s reports, was felt by us to be a major difficulty to be encountered during computer checkout. However, since nearly five months of continuous power application had elapsed since turning on the computer with only one possible phenolic breakdown, we had thought that this would not be a serious problem. However, recent experience has reversed our thinking on this problem and we now feel that phenolic breakdown may be a serious difficulty which may increase in frequency as time goes on. Investigation of this problem. during July has resulted in the conclusion, however, that the phenolic breakdown problem is nota disastrous one because there is a relatively inexpensive solution. The conclusion that this problem is tending to increase in frequency is based on a fairly thorough search of MIT r s records which failed to reveal any two week period in which as many, as six breakdowns occurred. Our investigation generally concurs with 39 earlier investigation by MIT which indicated that phenolic breakdown is due to silver migration and that this is predominantly a surface effect. The first four breakdowns we encountered in July on one panel occurred on the component side of the phenolic and tended to confirrrl an MIT opinion that cool air heavily saturated with moisture at the air duct outlet was a major contributing factor. MIT records on this particular panel reveal about a half dozen previous breakdowns, whereas records on an identical panel at the top of the same rack show that no breakdowns have ever occurred. Consequently, the flow of cold air to the component side of this panel was blocked and no further breakdowns have . occurred. We feel, on the basis of the two more recent breakdowns, however, that cool air laden with moisture may not be as important a factor as we had originally thought. The two latter cases occurred on the back side of the phenolic board in panels which were remotely located from the cool air ducts. The latter of these two panels, B -Register digit 15, was removed from the computer and examined closely. After removing the phenolic board from the aluminum panel it was evident that several potential trouble spots existed which werel.n.ot. in evidence on the component side of the phenolic. Both sides of the phenolic panel are covered with dirt which is probably soot from Cambridge and a film whose composition is unknown. Cleaning with a good solvent removes both the soot and the film as well as deposits of silver, and in areas where breakdown has occurred, cleaning of the surface appears to restore the insulation resistance of the phenolic. Cleaning is a ve ry tedious task when done manually due to the necessity for opening up the panel and the complex layout of components and wires. Thought was given, therefore, to cleaning in an ultrasonic bath, but pricing of this procedure reveals it to be extremely expensive and cleaning of all computer panels would be costly in terms of time as well. Furthermore, MIT's chemical analysis revealed that some. silver migration occurs within the phenolic material itself, although to a considerably lesser degree. Since cleaning is an expensive process, and since body migration would not be cured by cleaning, consideration was given to c;t more effective way of eliminating the problem entirely. 40 MITts solution of correcting each breakdown as it occurs by replacing one of the affected lugs with an insulated standoff lug is acceptable provided the frequency of occurrence does not increase. Phenolic breakdown can be located and corrected quickly by this :means without excessive COIllputer down ti:me. required. However) if the frequency increases a Illore effective solution is ExaIllination of the panel taken from B -Register digit 15 revealed that the probleIll exists only between terIllinals having a relatively high potential difference in the order of 150 to 250 volts. Thus) a solution which effectively inhibits Illigration between such terIllinal pairs will eliIllinate the probleIll. After further consideration) it was concluded that the IllOSt effective and siIllplest :method for eliIllinating Illigration between these terIllinal pairs is to cut a slot in the phenolic board between these terIllinals thus iIllposing an air gap between them. While this in itself would be a fairly tiIlle consuIlling task) it is felt to be the fastest, :most effective) and least expensive solution. While there are sOIllewhere in the order of 170 panels affected by this probleIll, there are only about 35 different types of panels. Thus, it would be a fairly reasonable task to check the asseIllbly drawings for each of these panel type s, locate all potential trouble spots, and then proceed to cut air gaps between all potentially troublesome terminal pairs in all panels. This task) which Illight require in the order of one or two weeks of cOIllputer shutdown, will be instituted if it becomes necessary due to a sharp increase in the frequency of occurrence of phenolic breakdowns. In the meantime) however) we plan to follow MITts procedure of correcting each trouble as it occurs. E. Power Failures Two outside power failures have occurred during the checkout period. The first of these occurred on May 20 when some of Boston Edison's underground power lines were flooded in Maynard. The second failure occurred on July 18 when lightning struck a Boston Edison substation in Burlington) Massachusetts. On both occassions the computer under-voltage sensing mechanism worked correctly and cycled the computer down in the proper fashion. Both of these failures were external to the building and were due to circumstances beyond ourco,ntrol. Such failures cause a certain amount of incon- venience and delay as they did at Cambridge. This problem could be eliminated 41 by the installation of diesel generators, but this is an expensive solution to be resorted to only if the priority of future work demands it. No action on this matter is contemplated at the present time and this subject is mentioned here only for the purpose of documenting a major trouble encountered during checkout. to date no Another reason for including it here is to emphasize the fact that ~nternal power failures have occurred. 42 V SUMMARY This progress report describes, in some detail, the moving, reassem- bling, and checkout of the Whirlwind I computer from the commencement of its move from Navy Building 61 in South Boston on December 6, 1961 until the present. Also presented are our plans for completing the checkout of the computer by November 15, 1963. PERT networks showing the events of the moving and reassembly phase and the checkout phase, their interrelationships and completion dates are presented and described. To date this project has encountered several major problems, some of which were expected while others were unexpected. described as have their solutions. These problems have been Solutions to all problems have been effected with the exception of that for the phenolic breakdown problem and this will be effected when and as required. No further major problems are anticipated but if new ones should occur, they are not expected to be insurmountable. Thus, we feel that successful completion of checkout will be accomplished on November 15, 1963.
Source Exif Data:
File Type : PDF File Type Extension : pdf MIME Type : application/pdf PDF Version : 1.3 Linearized : No XMP Toolkit : Adobe XMP Core 4.2.1-c043 52.372728, 2009/01/18-15:56:37 Create Date : 2010:06:30 19:29:41-08:00 Modify Date : 2010:06:30 19:32:42-07:00 Metadata Date : 2010:06:30 19:32:42-07:00 Producer : Adobe Acrobat 9.32 Paper Capture Plug-in Format : application/pdf Document ID : uuid:acc95290-2418-4c66-8422-72951bb74f42 Instance ID : uuid:8aa2308f-7b96-4f15-81b4-0e5730c55f53 Page Layout : SinglePage Page Mode : UseNone Page Count : 45EXIF Metadata provided by EXIF.tools