Huawei Technologies RRU32682G6 Remote Radio Unit User Manual Installation Guide

Huawei Technologies Co.,Ltd Remote Radio Unit Installation Guide

Contents

Installation Guide

RRU3268Installation GuideIssue 10Date 2015-12-30HUAWEI TECHNOLOGIES CO., LTD.
  Copyright © Huawei Technologies Co., Ltd. 2015. All rights reserved.No part of this document may be reproduced or transmitted in any form or by any means without prior writtenconsent of Huawei Technologies Co., Ltd. Trademarks and Permissions and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.All other trademarks and trade names mentioned in this document are the property of their respectiveholders. NoticeThe purchased products, services and features are stipulated by the contract made between Huawei and thecustomer. All or part of the products, services and features described in this document may not be within thepurchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,and recommendations in this document are provided "AS IS" without warranties, guarantees orrepresentations of any kind, either express or implied.The information in this document is subject to change without notice. Every effort has been made in thepreparation of this document to ensure accuracy of the contents, but all statements, information, andrecommendations in this document do not constitute a warranty of any kind, express or implied.        Huawei Technologies Co., Ltd.Address: Huawei Industrial BaseBantian, LonggangShenzhen 518129People's Republic of ChinaWebsite: http://www.huawei.comEmail: support@huawei.comIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.i
About This DocumentPurposeThis document describes the process of installing a DC blade RRU3268 (referred to as RRUin this document).Product VersionsThe following table lists the product versions related to this document.Product Name Solution Version Product VersionDBS3900 SRAN6.0 and later versions V100R004C00 and laterversionseRAN2.1 and later versions V100R003C00 and laterversions Intended AudienceThis document is intended for:Base station installation engineersOrganization1 Changes in the RRU3268 Installation GuideThis chapter describes the changes in the RRU3268 Installation Guide.2 Installation PreparationsThis chapter describes the reference documents, tools, and instruments that must be readybefore the installation. In addition, it specifies the skills and prerequisites that installationengineers must have.3 Information About the InstallationBefore installing an RRU, you must be familiar with its exterior, ports, indicators, installationoptions and installation clearance requirements.RRU3268Installation Guide About This DocumentIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.ii
4 Unpacking the EquipmentThis chapter describes how to unpack and check the delivered equipment to ensure that all thematerials are included and intact.5 Installation ProcessThe installation process involves installing an RRU and RRU cables, checking the RRUhardware installation, and powering on the RRU.6 (Optional) Installing the Plastic Shells of the RRUThis section describes the procedure for installing the plastic shells of the RRU.7 Hoisting an RRU and Related Cables onto a TowerThis section describes the procedure for hoisting an RRU and related cables onto a tower andthe precautions that must be taken.8 Installing the RRUThis chapter describes the procedure for installing the RRU. The procedure for installing theRRU varies depending on installation options.9 Installing RRU CablesThis chapter describes the procedure for installing RRU cables.10 Checking the RRU Hardware InstallationAfter an RRU is installed, check the hardware installation.11 Powering On an RRUAfter all the devices are installed, check the power-on status of an RRU.12 AppendixThis section describes the procedure for adding an easy power receptacle (pressfit type)connector.ConventionsSymbol ConventionsThe symbols that may be found in this document are defined as follows.Symbol DescriptionIndicates an imminently hazardous situation which, if notavoided, will result in death or serious injury.Indicates a potentially hazardous situation which, if notavoided, could result in death or serious injury.Indicates a potentially hazardous situation which, if notavoided, may result in minor or moderate injury.RRU3268Installation Guide About This DocumentIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.iii
Symbol DescriptionIndicates a potentially hazardous situation which, if notavoided, could result in equipment damage, data loss,performance deterioration, or unanticipated results.NOTICE is used to address practices not related to personalinjury.Calls attention to important information, best practices andtips.NOTE is used to address information not related topersonal injury, equipment damage, and environmentdeterioration. General ConventionsThe general conventions that may be found in this document are defined as follows.Convention DescriptionTimes New Roman Normal paragraphs are in Times New Roman.Boldface Names of files, directories, folders, and users are inboldface. For example, log in as user root.Italic Book titles are in italics.Courier New Examples of information displayed on the screen are inCourier New. Command ConventionsThe command conventions that may be found in this document are defined as follows.Convention DescriptionBoldface The keywords of a command line are in boldface.Italic Command arguments are in italics.[ ] Items (keywords or arguments) in brackets [ ] are optional.{ x | y | ... } Optional items are grouped in braces and separated byvertical bars. One item is selected.[ x | y | ... ] Optional items are grouped in brackets and separated byvertical bars. One item is selected or no item is selected.{ x | y | ... }*Optional items are grouped in braces and separated byvertical bars. A minimum of one item or a maximum of allitems can be selected.RRU3268Installation Guide About This DocumentIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.iv
Convention Description[ x | y | ... ]*Optional items are grouped in brackets and separated byvertical bars. Several items or no item can be selected. GUI ConventionsThe GUI conventions that may be found in this document are defined as follows.Convention DescriptionBoldface Buttons, menus, parameters, tabs, window, and dialog titlesare in boldface. For example, click OK.> Multi-level menus are in boldface and separated by the ">"signs. For example, choose File > Create > Folder. Keyboard OperationsThe keyboard operations that may be found in this document are defined as follows.Format DescriptionKey Press the key. For example, press Enter and press Tab.Key 1+Key 2 Press the keys concurrently. For example, pressing Ctrl+Alt+A means the three keys should be pressedconcurrently.Key 1, Key 2 Press the keys in turn. For example, pressing Alt, A meansthe two keys should be pressed in turn. Mouse OperationsThe mouse operations that may be found in this document are defined as follows.Action DescriptionClick Select and release the primary mouse button withoutmoving the pointer.Double-click Press the primary mouse button twice continuously andquickly without moving the pointer.Drag Press and hold the primary mouse button and move thepointer to a certain position.RRU3268Installation Guide About This DocumentIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.v
ContentsAbout This Document.....................................................................................................................ii1 Changes in the RRU3268 Installation Guide........................................................................... 12 Installation Preparations..............................................................................................................52.1 Reference Documents.....................................................................................................................................................62.2 Tools and Instruments.....................................................................................................................................................62.3 Skills and Requirements for Onsite Personnel............................................................................................................... 83 Information About the Installation........................................................................................... 93.1 RRU Exterior................................................................................................................................................................103.2 RRU Ports..................................................................................................................................................................... 113.3 RRU Indicators............................................................................................................................................................. 133.4 Installation Scenarios....................................................................................................................................................143.5 Installation Clearance Requirements of an RRU..........................................................................................................233.5.1 Clearance for a Single RRU...................................................................................................................................... 233.5.2 Clearances for Three or More RRUs.........................................................................................................................263.5.3 Installation Spacing Between RRUs..........................................................................................................................304 Unpacking the Equipment.........................................................................................................335 Installation Process..................................................................................................................... 356 (Optional) Installing the Plastic Shells of the RRU..............................................................367 Hoisting an RRU and Related Cables onto a Tower............................................................ 387.1 Hoisting an RRU onto a Tower.................................................................................................................................... 397.2 Hoisting Fiber Optic Cables onto a Tower................................................................................................................... 427.3 Hoisting Power Cables onto a Tower........................................................................................................................... 458 Installing the RRU.......................................................................................................................488.1 Mounting Kits for an RRU........................................................................................................................................... 498.2 Installing the RRU on a Pole........................................................................................................................................ 508.2.1 Installing a Single RRU.............................................................................................................................................508.2.2 Installing Two RRUs................................................................................................................................................. 538.2.3 Installing Three or More RRUs................................................................................................................................. 578.3 Installing the RRU on U-steel...................................................................................................................................... 628.4 Installing the RRU on Angle Steel............................................................................................................................... 67RRU3268Installation Guide ContentsIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.vi
8.5 Installing the RRU on a Wall........................................................................................................................................718.6 Installing an RRU on an IFS06.....................................................................................................................................779 Installing RRU Cables................................................................................................................ 849.1 Cabling Requirements.................................................................................................................................................. 869.2 Cable Connections........................................................................................................................................................929.3 Installation Process....................................................................................................................................................... 949.4 RRU Cable List............................................................................................................................................................ 959.5 Installing an RRU PGND Cable...................................................................................................................................969.6 Installing an RRU RF Jumper...................................................................................................................................... 979.7 Installing an RRU AISG Multi-Wire Cable and AISG Extension Cable................................................................... 1019.8 Installing an RRU Alarm Cable..................................................................................................................................1039.9 Opening the Cover Plate of an RRU Cabling Cavity................................................................................................. 1059.10 Installing an RRU Power Cable................................................................................................................................1079.11 Installing a CPRI Fiber Optic Cable......................................................................................................................... 1099.12 Closing the Cover Plate of an RRU Cabling Cavity.................................................................................................11210 Checking the RRU Hardware Installation..........................................................................11511 Powering On an RRU............................................................................................................. 11712 Appendix...................................................................................................................................11912.1 Adding a Tool-Less Female Connector (Pressfit Type) to the RRU Power Cable on the RRU Side.......................120RRU3268Installation Guide ContentsIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.vii
1 Changes in the RRU3268 Installation GuideThis chapter describes the changes in the RRU3268 Installation Guide.10 (2015-12-30)This is the tenth official release.Compared with issue 09 (2015-08-30), this issue includes the following change:Topic Change Description9.11 Installing a CPRI Fiber Optic Cable Added the procedure of installing CPRIoptical cables for single-fiber bidirectionaloptical modules. Compared with issue 09 (2015-08-30), this issue does not include any new information andno information is deleted from this issue.09 (2015-08-30)This is the ninth official release.Compared with issue 08 (2015-03-23), this issue includes the following change:Topic Change DescriptionThe whole document Optimized the contents in this document. Compared with issue 08 (2015-03-23), this issue does not include any new information andno information is deleted from this issue.08 (2015-03-23)This is the eighth official release.Compared with issue 07 (2014-11-10), this issue includes the following change:RRU3268Installation Guide 1 Changes in the RRU3268 Installation GuideIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.1
Topic Change DescriptionThe whole document Added security related precautions. Compared with issue 07 (2014-11-10), this issue does not include any new information and noinformation is deleted from this issue.07 (2014-11-10)This is the seventh official release.Compared with issue 06 (2014-10-24), this issue includes the following change:Topic Change Description9.10 Installing an RRU Power Cable Modified the precautions in the backgroundinformation.12.1 Adding a Tool-Less FemaleConnector (Pressfit Type) to the RRUPower Cable on the RRU SideAdded the precaution that do not reverselyconnect the positive and negative poles inthe procedure. Compared with issue 06 (2014-10-24), this issue does not include any new information andno information is deleted from this issue.06 (2014-10-24)This is the sixth official release.Compared with issue 05 (2014-06-30), this issue includes the following change:Topic Change Description3.4 Installation Scenarios Optimized the description of restrictions.8 Installing the RRU Optimized the description of the distancebetween the mounting kit and the ground. Compared with issue 05 (2014-06-30), this issue does not include any new information andno information is deleted from this issue.05 (2014-06-30)This is the fifth official release.Compared with issue 04 (2013-12-30), this issue includes the following change:RRU3268Installation Guide 1 Changes in the RRU3268 Installation GuideIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.2
Topic Change Description3.5.1 Clearance for a Single RRU Added the clearance for a single RRU ormultiple RRUs on the bitumen ground.3.5.2 Clearances for Three or More RRUsInstalling an RRU Alarm Cable Added notes under the procedure.3.4 Installation Scenarios Added restrictions on RRU mounting kits inassembled installation mode. Compared with issue 04 (2013-12-30), this issue does not include any new information andno information is deleted from this issue.04 (2013-12-30)This is the fourth official release.Compared with issue 03 (2013-12-23), this issue includes the following change:Topic Change Description3.4 Installation Scenarios Modified the figure showing the U-steelspecifications. Compared with issue 03 (2013-12-23), this issue does not include any new information andno information is deleted from this issue.03 (2013-12-23)This is the third official release.Compared with issue 02 (2013-06-26), this issue includes the following change:Topic Change Description7.1 Hoisting an RRU onto a Tower Optimized the procedure for hoisting anRRU onto a Tower. Compared with issue 02 (2013-06-26), this issue does not include any new information andno information is deleted from this issue.02 (2013-06-26)This is the second official release.Compared with issue 01 (2013-04-28), this issue includes the following change:RRU3268Installation Guide 1 Changes in the RRU3268 Installation GuideIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.3
Topic Change Description9.10 Installing an RRU Power Cable Added the power device DCDU-12B for theRRU. Compared with issue 01 (2013-04-28), this issue does not include any new information andno information is deleted from this issue.01 (2013-04-28)This is the first official release.RRU3268Installation Guide 1 Changes in the RRU3268 Installation GuideIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.4
2 Installation PreparationsAbout This ChapterThis chapter describes the reference documents, tools, and instruments that must be readybefore the installation. In addition, it specifies the skills and prerequisites that installationengineers must have.2.1 Reference DocumentsBefore the installation, you must be familiar with reference documents.2.2 Tools and InstrumentsYou must prepare the following tools and instruments before the installation.2.3 Skills and Requirements for Onsite PersonnelOnsite personnel must be qualified and trained. Before performing any operation, onsitepersonnel must be familiar with correct operation methods and safety precautions.RRU3268Installation Guide 2 Installation PreparationsIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.5
2.1 Reference DocumentsBefore the installation, you must be familiar with reference documents.The following reference documents are required during RRU installation:lSafety InformationlRRU3268 Hardware DescriptionlDBS3900 Installation GuidelOCB User GuidelOCB-01M User Guide2.2 Tools and InstrumentsYou must prepare the following tools and instruments before the installation.Hammer drill (a φ12 bit) ESD gloves Vacuum cleanerHeat gun Phillips screwdriver (M3 toM6)Flat-head screwdriver (M3 toM6)Rubber mallet COAX crimping tool Wire stripperRRU3268Installation Guide 2 Installation PreparationsIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.6
Utility knife Cable cutter Adjustable wrench (size ≥ 32mm [1.26 in.])Torque wrenchSize: 16 mm (0.63 in.) and32 mm (1.26 in.)Combination wrenchSize: 16 mm (0.63 in.) and32 mm (1.26 in.)Level Torque screwdriver5 mm5 mm(M3 to M6)(M3 to M6)Torque socketMultimeter Marker (diameter ≤ 10 mm[0.39 in.])Measuring tapeInner hexagon wrench5 mmFixed pulley(weight-bearing capacity > 500 kgor 1102.5 lb)Lifting slingHydraulic pliers - -RRU3268Installation Guide 2 Installation PreparationsIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.7
 2.3 Skills and Requirements for Onsite PersonnelOnsite personnel must be qualified and trained. Before performing any operation, onsitepersonnel must be familiar with correct operation methods and safety precautions.Before the installation, pay attention to the following items:lThe customer's technical engineers must be trained by Huawei and be familiar with theproper installation and operation methods.lThe number of onsite personnel depends on the engineering schedule and installationenvironment. Generally, only three to five onsite personnel are necessary.RRU3268Installation Guide 2 Installation PreparationsIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.8
3 Information About the InstallationAbout This ChapterBefore installing an RRU, you must be familiar with its exterior, ports, indicators, installationoptions and installation clearance requirements.3.1 RRU ExteriorThis section describes the exterior and dimensions of an RRU.3.2 RRU PortsThis section describes ports on the RRU panels. An RRU has a bottom panel, cabling cavitypanel, and indicator panel.3.3 RRU IndicatorsThis section describes six indicators on an RRU. They indicate the running status.3.4 Installation ScenariosAn RRU can be installed on a pole, U-steel, angle steel, wall, or IFS06. Installation scenariosmust meet heat-dissipation and waterproofing requirements of the RRU.3.5 Installation Clearance Requirements of an RRUThis section describes the requirements for the installation clearance of a single RRU andmultiple RRUs and the requirements for the installation spacing between RRUs.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.9
3.1 RRU ExteriorThis section describes the exterior and dimensions of an RRU.Figure 3-1 shows an RRU.Figure 3-1 RRU exterior Figure 3-2 shows RRU dimensions.Figure 3-2 RRU dimensions You can obtain the RRU frequency band and power supply information from theconfiguration label on the cover plate and obtain the RRU name from the nameplate on theside of RRU that accommodates the conversion bracket. Figure 3-3 shows the positions of theconfiguration label and nameplate on the RRU.NOTEThe actual label and nameplate may differ from what is shown in the figure.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.10
Figure 3-3 Positions of the label and nameplate(1) Configuration label (2) Nameplate (3) Frequency band(4) Power supply type (5) Module name - 3.2 RRU PortsThis section describes ports on the RRU panels. An RRU has a bottom panel, cabling cavitypanel, and indicator panel.Figure 3-4 shows the ports on the RRU panels.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.11
Figure 3-4 Ports on the RRU panels Table 3-1 describes ports and indicators on the RRU panels.Table 3-1 Ports and indicators on the RRU panelsItem Silkscreen Remarks(1) Ports in thecabling cavityRTN(+) Power supply socketNEG(-)CPRI0 Optical/electrical port 0, connected to theBBUCPRI1 Optical/electrical port 1, reserved(2) Ports at thebottomANT_TX/RXA TX/RX port A, supporting RET signaltransmissionANT_TX/RXB TX/RX port BEXT_ALM Alarm monitoring port used for monitoringone RS485 signal and two dry contactsignalsRRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.12
Item Silkscreen RemarksRET Communication port for the RET antenna,supporting RET signal transmission(3) Indicators RUN See 3.3 RRU Indicators.ALMACTVSWRCPRI0CPRI1 NOTEThe port for transmitting RET signals is determined by the software.3.3 RRU IndicatorsThis section describes six indicators on an RRU. They indicate the running status.For detailed positions of RRU indicators, see 3.2 RRU Ports.Table 3-2 describes RRU indicators.Table 3-2 RRU indicatorsIndicator Color Status MeaningRUN Green Steady on There is power supply, but the module isfaulty.Steady off There is no power supply, or the module isfaulty.Blinking (on for1s and off for 1s)The board is functioning properly.Blinking (on for0.125s and off for0.125s)Software is being loaded to the module, orthe module is not started.ALM Red Steady on Alarms are generated, and the module mustbe replaced.Blinking (on for1s and off for 1s)Alarms are generated. The alarms may becaused by the faults on the related boards orports. Therefore, you need to locate thefault before deciding whether to replace themodule.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.13
Indicator Color Status MeaningSteady off No alarm is generated.ACT Green Steady on The module is running properly with TXchannels enabled or the software is beingloaded without RRU running.Blinking (on for1s and off for 1s)The module is running properly with TXchannels disabled.VSWR Red Steady off No Voltage Standing Wave Ratio (VSWR)alarm is generated.Blinking (on for1s and off for 1s)VSWR alarms are generated on theANT_TX/RXB port.Steady on VSWR alarms are generated on theANT_TX/RXA port.Blinking (on for0.125s and off for0.125s)VSWR alarms are generated on theANT_TX/RXA and ANT_TX/RXB ports.CPRI0 Red orgreenSteady green The CPRI link is functioning properly.Steady red An optical module fails to transmit orreceive signals because the optical moduleis faulty or the fiber optic cable is broken.Blinking red (onfor 1s and off for1s)The CPRI link is out of lock because of afailure in clock lock between two modes ormismatched data rates over CPRI ports.Steady off The optical module cannot be detected, orthe optical module is powered off.CPRI1 Red orgreenSteady green The CPRI link is functioning properly.Steady red An optical module fails to transmit orreceive signals because the optical moduleis faulty or the fiber optic cable is broken.Blinking red (onfor 1s and off for1s)The CPRI link is out of lock because of afailure in clock lock between two modes ormismatched data rates over CPRI ports.Steady off The optical module cannot be detected, orthe optical module is powered off. 3.4 Installation ScenariosAn RRU can be installed on a pole, U-steel, angle steel, wall, or IFS06. Installation scenariosmust meet heat-dissipation and waterproofing requirements of the RRU.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.14
Requirements for the Installation ScenariosApplication scenarios:To ensure proper heat dissipation of the RRU, the following requirements must be met:lThe RRU cannot be installed in an enclosed cabinet without a cooling system.lThe RRU cannot be installed in an enclosed camouflage box.lThe RRU cannot be installed in an enclosed equipment room without a cooling system.lWhen multiple RRUs are installed in centralized mode, the minimum clearancerequirements must be met. For details about the minimum clearance requirements, see3.5.2 Clearances for Three or More RRUs and 3.5.3 Installation Spacing BetweenRRUs.lRRU mounting kits in assembled installation mode are not allowed in indoor scenarios.NOTICEIf the RRU is improperly installed, heat dissipation of the RRU deteriorates and the RRU maynot work properly, as shown in Figure 3-5.Figure 3-5 Improperly installed RRUs Method of installation:lThe installation supports' specifications described in this document are only based on theexterior and dimensions of the mounting kits. Before installing equipment, assess thestrength and reliability of the installation support to determine whether it can bear theweight of the equipment.lTo ensure the heat dissipation of the RRU and waterproofing of the ports at the bottom ofthe RRU, the vertical deviation angle of an RRU must be less than or equal to 10degrees, as shown in Figure 3-6.lOn a tower, an RRU can be installed on a pole, angle steel, or U-steel. The side-mountedinstallation mode (one side instead of the rear of an RRU is mounted on the support) isrecommended for RRUs on the main pole secured on a tower. This installation modeRRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.15
allows multiple RRUs to be installed next to each other at the same level on a pole.When the horizontal distance between the main and auxiliary poles on a tower is equal toor greater than 810 mm (23.62 in.), the side-mounted mode is recommended forinstalling RRUs on the auxiliary pole to meet the minimum clearance requirements.Otherwise, the standard mode is recommended for installing RRUs on the auxiliary pole.Figure 3-6 Requirements for the vertical deviation angle of an RRU(1) RRU (2) Installation support (pole, U-steel, angle steel, or wall) Installing an RRU on a PoleFigure 3-7 shows the diameter of a pole for installing an RRU.Figure 3-7 Diameter of a pole RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.16
NOTICElThe diameter of a pole for installing an RRU ranges from 60 mm (2.36 in.) to 114 mm(4.49 in.). The recommended diameter is 80 mm (3.15 in.).lWhen the diameter of a pole ranges from 60 mm (2.36 in.) to 76 mm (2.99 in.), amaximum of three RRUs can be installed on the pole and the side-mountedinstallation is recommended.lOnly a pole whose diameter ranges from 76 mm (2.99 in.) to 114 mm (4.49 in.)supports more than three RRUs.lThe recommended thickness of the wall of a pole is 3.5 mm (0.14 in.) or above.Figure 3-8 shows a single RRU installed on a pole.Figure 3-8 A single RRU installed on a pole Figure 3-9 shows two RRUs installed on a pole.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.17
Figure 3-9 Two RRUs installed on a pole Installing an RRU on U-steelFigure 3-10 shows U-steel specifications.Figure 3-10 U-steel specifications NOTICEU-steel supports the standard or reverse installation of a single RRU only.Figure 3-11 shows an RRU installed on U-steel.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.18
Figure 3-11 RRU installed on U-steel Installing an RRU on Angle SteelFigure 3-12 shows angle steel specifications.Figure 3-12 Angle steel specifications NOTICEAngle steel supports the standard or reverse installation of a single RRU only.Figure 3-13 shows an RRU installed on angle steel.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.19
Figure 3-13 RRU installed on angle steel Installing an RRU on a WallThe wall for installing RRUs must meet the following requirements:lFor each RRU, the wall must be able to bear a weight four times the RRU's weight andthe bolts' pulling force of 1.25 kN (281.25 lbf) vertical to the wall.lExpansion anchor bolts must be tightened to 30 N·m (265.52 lbf·in.) so that the boltsstay secured without damaging the wall.NOTICElIt is recommended that the RRU be installed on a wall in standard mode.lWhen RRUs are installed on a wall in side-mounted mode, do not combine mountingbrackets for multiple RRUs, as shown in Figure 3-14.Figure 3-14 Correct installation of mounting brackets for multiple RRUs installed on a wallin side-mounted mode Figure 3-15 shows an RRU installed on a wall.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.20
Figure 3-15 RRU installed on a wall Installing an RRU on an IFS06In an IFS06 scenario:lThe upper and lower adjustable beams on an IFS06 can be moved up and down to fit forheights of RRUs.lThe IFS06 supports at least three RRUs when the ambient temperature is higher than orequal to the lowest operating temperature of the RRU and at least 5°C (41°F) lower thanthe highest operating temperature of the RRU. The IFS06 supports a maximum of sixRRUs when the ambient temperature is higher than or equal to the lowest operatingtemperature of the RRU and at least 10°C (50°F) lower than the highest operatingtemperature of the RRU.NOTEFor details about the operating temperature of the RRU, see section "Technical Specifications ofRRUs" in 3900 Series Base Station Technical Description.NOTICEThe mounting brackets for multiple RRUs cannot be combined when the RRUs are installedon an IFS06, as shown in Figure 3-16.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.21
Figure 3-16 Correct installation of mounting brackets for RRUs installed on an IFS06 Figure 3-17 and Figure 3-18 show RRUs installed on an IFS06.Figure 3-17 Three RRUs installed on an IFS06(1) Height-restricted scenario (2) Height-unrestricted scenario RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.22
Figure 3-18 Six RRUs installed on an IFS06(1) Height-restricted scenario (2) Height-unrestricted scenario 3.5 Installation Clearance Requirements of an RRUThis section describes the requirements for the installation clearance of a single RRU andmultiple RRUs and the requirements for the installation spacing between RRUs.3.5.1 Clearance for a Single RRUThis section describes the recommended and minimum clearance for a single RRU.NOTICEIf an RRU is installed on the bitumen ground, the RRU must be at least 500 mm (700 mm ormore as recommended) away from the bitumen ground. The following describes the spacerequirements for installing a single RRU on the non-bitumen ground.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.23
NOTElThe recommended clearance ensures normal running and provides an appropriate space foroperation and maintenance (OM). If there is sufficient space, leave the recommended clearance afterinstalling the equipment.lThe minimum clearance ensures normal running and heat dissipation, but OM activities such aschecking indicator status and opening the cabling cavity cannot be properly conducted. If theinstallation space is restricted, leave the minimum clearance after installing the equipment.Clearance for a Single RRU in Standard or Reverse ModeFigure 3-19 shows the clearance for a single RRU in standard or reverse mode.Figure 3-19 Clearance for a single RRU in standard or reverse mode Clearance for a Single RRU in Side-Mounted ModeFigure 3-20 shows the clearance for a single RRU in side-mounted mode.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.24
Figure 3-20 Clearance for a single RRU in side-mounted mode Clearance for a Single Tower-mounted RRUFigure 3-21 and Figure 3-22 show the clearance for a single tower-mounted RRU in standardor reverse mode and in side-mounted mode, respectively.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.25
Figure 3-21 Minimum clearance for a single tower-mounted RRU in standard or reversemode Figure 3-22 Minimum clearance for a single tower-mounted RRU in side-mounted mode 3.5.2 Clearances for Three or More RRUsThis section describes the recommended and minimum clearances for three or more RRUs.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.26
NOTICEIf an RRU is installed on the bitumen ground, the RRU must be at least 500 mm (700 mm ormore as recommended) away from the bitumen ground. The following describes the spacerequirements for installing multiple RRUs on the non-bitumen ground.NOTElThe recommended clearances ensure normal running and provide an appropriate space for operationand maintenance (OM). If there is sufficient space, retain the recommended clearances.lThe minimum clearances ensure normal running and heat dissipation but do not allow OM activitiessuch as checking indicator status and opening the cabling cavity. If the installation space isinsufficient, retain the minimum clearances after the installation.Recommended Clearances for Three or More RRUs Installed on a PoleFigure 3-23 shows the recommended clearances for multiple RRUs installed in centralizedmode.Figure 3-23 Recommended clearances for three or more RRUs installed on a pole Minimum Clearances for Three or More RRUs Installed on a PoleFigure 3-24 shows the minimum clearances for multiple RRUs installed in centralized mode.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.27
Figure 3-24 Minimum clearances for multiple RRUs installed in centralized mode Recommended Clearances for Three or More RRUs Installed on a Wall inStandard ModeFigure 3-25 shows the recommended clearances for multiple RRUs installed on a wall instandard mode.Figure 3-25 Recommended clearances for three or more RRUs installed on a wall in standardmode RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.28
Minimum Clearances for Three or More RRUs Installed on a Wall in StandardModeFigure 3-26 shows the minimum clearances for three or more RRUs installed on a wall instandard mode.Figure 3-26 Minimum clearances for three or more RRUs installed on a wall in standardmode Recommended Clearances for Three or More RRUs Installed on a Wall in Side-Mounted ModeFigure 3-27 shows the recommended clearances for three or more RRUs side-mounted on awall.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.29
Figure 3-27 Recommended clearances for three or more RRUs installed on a wall in side-mounted mode 3.5.3 Installation Spacing Between RRUsThis section describes the horizontal and vertical spacing between RRUs.Recommended Horizontal Spacing Between RRUsFigure 3-28 shows the recommended horizontal spacing between RRUs.Figure 3-28 Recommended horizontal spacing between RRUs Minimum Horizontal Spacing Between RRUsFigure 3-29 shows the minimum horizontal spacing between RRUs.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.30
Figure 3-29 Minimum horizontal spacing between RRUs Recommended Vertical Spacing Between RRUsFigure 3-30 shows the recommended vertical spacing between RRUs.Figure 3-30 Recommended vertical spacing between RRUs Minimum Vertical Spacing Between RRUsFigure 3-31 shows the minimum vertical spacing between RRUs.RRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.31
Figure 3-31 Minimum vertical spacing between RRUsRRU3268Installation Guide 3 Information About the InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.32
4 Unpacking the EquipmentThis chapter describes how to unpack and check the delivered equipment to ensure that all thematerials are included and intact.ContextNOTEWhen transporting, moving, or installing the equipment, components, or parts, you must:lPrevent them from colliding with doors, walls, shelves, or other objects.lWear clean gloves, and avoid touching the equipment, components, or parts with bare hands,sweat-soaked gloves, or dirty gloves.NOTICElAfter a cabinet or an BBU is unpacked, it must be powered on within 7 days.lAfter an RRU is unpacked, it must be powered on within 24 hours.ProcedureStep 1 Check the total number of articles in each case according to the packing list.If ... Then ...The total number tallies with the packinglistGo to Step 2.The total number does not tally with thepacking listFind out the cause and report any missingarticles to the local Huawei office.Step 2 Check the exterior of the packing case.RRU3268Installation Guide 4 Unpacking the EquipmentIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.33
If ... Then ...The outer packing is intact Go to Step 3.The outer packing is severely damaged orsoakedFind out the cause and report it to the localHuawei office.Step 3 Check the type and quantity of the equipment in the cases according to the packing list.If ... Then ...Types and quantity of the article tallywith those on the packing listSign the Packing List with the customer.Either shipment shortage, wrongshipment or damaged articles.Report to the local Huawei office.CAUTIONlTo protect the equipment and prevent damage to the equipment, you are advised to keepthe unpacked equipment and packing materials indoors, take photos of the stockingenvironment, packing case or carton, packing materials, and any rusted or erodedequipment, and then file the photos.lVerify that the insulation layers of all RRU cables are intact. If the insulation layers aredamaged or broken, water will penetrate into the cables, which may cause damages toRRUs or human injury.----EndRRU3268Installation Guide 4 Unpacking the EquipmentIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.34
5 Installation ProcessThe installation process involves installing an RRU and RRU cables, checking the RRUhardware installation, and powering on the RRU.Figure 5-1 shows the process of installing an RRU.Figure 5-1 Process of installing an RRURRU3268Installation Guide 5 Installation ProcessIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.35
6 (Optional) Installing the Plastic Shells ofthe RRUThis section describes the procedure for installing the plastic shells of the RRU.ContextAn RRU is equipped with a plastic shell only when necessary.ProcedureStep 1 Use an M6 Phillips screwdriver to loosen the two screws on the metal sheet of the RRU andremove the metal sheet, as shown in Figure 6-1.Figure 6-1 Removing the metal sheet (1) Screw (2) Metal sheetRRU3268Installation Guide 6 (Optional) Installing the Plastic Shells of the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.36
Step 2 Install a buckle on each side at the bottom of the RRU, and use an M4 torque wrench totighten the screws on the buckles to 1.4 N·m (12.39 lbf·in.), as shown in Figure 6-2.Figure 6-2 Installing buckles at the bottom (1) Buckle (2) ScrewStep 3 Use four hex screws to secure the plastic shells onto the RRU and use an M6 hex key wrenchto tighten the screws to 2.8 N·m (24.78 lbf·in.), as shown in Figure 6-3.Figure 6-3 Installing the plastic shells of the RRU----EndRRU3268Installation Guide 6 (Optional) Installing the Plastic Shells of the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.37
7 Hoisting an RRU and Related Cables onto aTowerAbout This ChapterThis section describes the procedure for hoisting an RRU and related cables onto a tower andthe precautions that must be taken.7.1 Hoisting an RRU onto a TowerThis section describes the procedures and precautions for hoisting an RRU and its mountingkits onto a tower. In tower-mounted scenarios, the RRU can be installed on a pole, U-steel, orangle steel.7.2 Hoisting Fiber Optic Cables onto a TowerThis section describes the procedure for hoisting fiber optic cables onto a tower and theprecautions that must be taken.7.3 Hoisting Power Cables onto a TowerThis section describes the procedure for hoisting power cables onto a tower and theprecautions that must be taken.RRU3268Installation Guide 7 Hoisting an RRU and Related Cables onto a TowerIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.38
7.1 Hoisting an RRU onto a TowerThis section describes the procedures and precautions for hoisting an RRU and its mountingkits onto a tower. In tower-mounted scenarios, the RRU can be installed on a pole, U-steel, orangle steel.PrerequisitesWhen the RRU is powered by an AC/DC power module, you need to install the AC/DCpower module onto the RRU before hoisting them onto a tower. For detailed operations, seeAC/DC Power Module User Guide or OPM15M User Guide.NOTICElPlace a foam pad or cardboard on the ground to protect the housing of the RRU fromdamage before the binding. Do not stand the RRU upright because the RF ports cannotsupport the weight of the RRU.lThe routing and protection of power cables should follow the local safety regulations,industry standards, and enterprise standards of the operator.ProcedureStep 1 After climbing up to the tower, technician A secures the fixed pulley to the tower platformsupport and leads the lifting sling through the fixed pulley.Step 2 Technician C binds the mounting kits using the lifting sling and traction sling on the ground,as shown in Figure 7-1. Then technician B pulls the lifting sling downwards, and technicianC pulls the traction sling outwards to protect the mounting kits from colliding with the tower.Figure 7-1 Binding mounting kits for the RRURRU3268Installation Guide 7 Hoisting an RRU and Related Cables onto a TowerIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.39
(1) Lifting sling (2) Traction slingStep 3 Technician A catches the mounting kits and then unties the slings.Step 4 Install the mounting kits. For detailed operations, see steps 1 to 3 in 8.2.1 Installing a SingleRRU.Step 5 Technician C binds the RRU using the lifting sling and traction sling, as shown in Figure 7-2.The binding methods in Figure 7-3 and Figure 7-4 are incorrect.Figure 7-2 Binding the RRU(1) Handle (2) Lifting sling (3) Traction eye (4) Traction sling Figure 7-3 Incorrect binding method (1) RRU3268Installation Guide 7 Hoisting an RRU and Related Cables onto a TowerIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.40
Figure 7-4 Incorrect binding method (2) Step 6 Hoist the RRU onto the tower, as shown in Figure 7-5. Technician B pulls the lifting slingdownwards, and technician C pulls the traction sling outwards to protect the RRU fromcolliding with the tower.Figure 7-5 Hoisting the RRU onto the tower(1) Lifting sling (2) Fixed pulley (3) Traction sling RRU3268Installation Guide 7 Hoisting an RRU and Related Cables onto a TowerIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.41
NOTICElThe load-bearing capacity of each sling must be greater than 200 kg (441 lb) and thediameter of each sling must be less than 25 mm (0.98 in.).lWhen hoisting each device onto a tower, protect them from colliding with the tower.lHoist the RRU onto the tower before it is installed on a pole, angle steel, or U-steel.lDo not hoist any thing by the traction eye.Step 7 Technician A catches the RRU hoisted onto the tower.Step 8 Technician A installs the RRU onto the main bracket and uses an inner hexagon torquescrewdriver to tighten the captive screw into the hole of the attachment plate and main bracketto 5 N·m (44.25 lbf·in.). For detailed operations, see steps 4 and 5 in 8.2.1 Installing a SingleRRU.Step 9 Untie the lifting sling and traction sling.NOTEThe procedure for hoisting the RRU and its mounting kits onto the tower is for your reference only.----End7.2 Hoisting Fiber Optic Cables onto a TowerThis section describes the procedure for hoisting fiber optic cables onto a tower and theprecautions that must be taken.ContextCabling requirements for power cables are met. For details, see 9.1 Cabling Requirements.ProcedureStep 1 Hoist the fiber optic cables onto the tower, as shown in Figure 7-6.RRU3268Installation Guide 7 Hoisting an RRU and Related Cables onto a TowerIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.42
Figure 7-6 Hoisting fiber optic cables onto the tower(1) Lifting sling (2) Fixed pulley (3) Traction slingNOTICEBefore hoisting fiber optic cables onto the tower, connect the fiber optic cables to the RRU orBBU based on the labels on both ends of the cables and determine the hoisting direction.1. After climbing up to the tower, installation engineer A secures the fixed pulley to thetower platform support and leads the lifting sling through the fixed pulley.2. Installation engineer B places the fiber coiler for coiling fiber optic cables on the fiberspools, and installation engineer D lead the lifting sling through the stretch sling of thefiber optic cables and use the other sling as a traction sling to secure the cables 4 m(13.12 ft) away from the lifting sling, as shown in Figure 7-7.RRU3268Installation Guide 7 Hoisting an RRU and Related Cables onto a TowerIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.43
Figure 7-7 Binding fiber optic cables(1) Lifting sling (2) Stretch sling (3) Traction sling NOTICEDo not remove the stretch sling and protection pipe or bind fiber optic cables using onesling, as shown in Figure 7-8.Figure 7-8 Incorrect binding method 3. Installation engineer B rotates the fiber spools at the speed of 5 m (16.4 ft) to 15 m(49.21 ft) per minute to coil the fiber optic cables.4. Installation engineer C pulls the lifting sling downwards, and installation engineer Dpulls the traction sling outwards to protect the fiber optic cables from colliding with thetower.RRU3268Installation Guide 7 Hoisting an RRU and Related Cables onto a TowerIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.44
Step 2 Secure the fiber optic cables to the tower vertically using cable clips.Step 3 Remove the lifting sling, traction sling, and protection pipe.NOTEThe procedure for hoisting the fiber optic cables onto the tower is for your reference only.----End7.3 Hoisting Power Cables onto a TowerThis section describes the procedure for hoisting power cables onto a tower and theprecautions that must be taken.ContextCabling requirements for power cables are met. For details, see 9.1 Cabling Requirements.The procedure for adding a connector to the RRU power cable on the RRU side is done underthe tower.ProcedureStep 1 Hoist the power cables onto the tower, as shown in Figure 7-9.Figure 7-9 Hoisting power cables onto the tower(1) Lifting sling (2) Fixed pulley RRU3268Installation Guide 7 Hoisting an RRU and Related Cables onto a TowerIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.45
1. After climbing up to the tower, installation engineer A secures the fixed pulley to thetower platform support and leads the lifting sling through the fixed pulley.2. Installation engineer B secures three cable ties to the power cable connector, and thensecures the power cable to the lifting sling, as shown in Figure 7-10.NOTEThe connector on the power cable in the figure is only an example. The actual connector may varyaccording to the situation.Figure 7-10 Binding cable ties 3. Installation engineer B wraps the power cable connector with a layer of PVC insulationtape, as shown in Figure 7-11.NOTEWrap the PVC insulation tape from 30 mm (1.18 in.) away from one end of the connector until itreaches the other end of the connector. The total length of the wrapped connector is 100 mm (3.94in.).RRU3268Installation Guide 7 Hoisting an RRU and Related Cables onto a TowerIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.46
Figure 7-11 Wrapping the PVC insulation tape 4. Installation engineer C pulls the lifting sling downwards, and installation engineer Bpulls the other end of the lifting sling outwards to protect the power cables fromcolliding with the tower.Step 2 Secure the power cables to the tower vertically using cable clips.Step 3 Remove the cable ties, PVC insulation tape, and lifting sling.NOTEThe procedure for hoisting the power cables onto the tower is for your reference only.----EndRRU3268Installation Guide 7 Hoisting an RRU and Related Cables onto a TowerIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.47
8 Installing the RRUAbout This ChapterThis chapter describes the procedure for installing the RRU. The procedure for installing theRRU varies depending on installation options.8.1 Mounting Kits for an RRUThis section describes the bracket assembly and the attachment plate for an RRU.8.2 Installing the RRU on a PoleOne or more RRUs can be installed on a pole.8.3 Installing the RRU on U-steelThis section describes the procedure and precautions for installing the RRU on U-steel. AnRRU can be installed on U-steel secured on the ground or a tower. Each piece of U-steelallows only one RRU to be installed in standard or reverse mode.8.4 Installing the RRU on Angle SteelThis section describes the procedure and precautions for installing the RRU on angle steel. AnRRU can be installed on angle steel secured on the ground or a tower. Each piece of anglesteel allows only one RRU to be installed in standard or reverse mode.8.5 Installing the RRU on a WallThis section describes the procedure and precautions for installing the RRU on a wall.8.6 Installing an RRU on an IFS06This section describes the procedure and precautions for installing an RRU on an IFS06.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.48
8.1 Mounting Kits for an RRUThis section describes the bracket assembly and the attachment plate for an RRU.Figure 8-1 shows the front and side of an RRU.Figure 8-1 Front and side view of an RRU(1) Front view (2) Side view (3) Attachment plate Figure 8-2 shows the bracket assembly for an RRU.Figure 8-2 12 L blade RRU mounting kit(1) Plastic cap (2) Standard M10nut(3) Spring washer (4) Thick flat washer (5) Square-neck boltRRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.49
(6) Hoist clamp onthe main bracket(7) Main bracket (8) Inner hexagonscrew(9) Pole installationbracket(10) Auxiliarybracket 8.2 Installing the RRU on a PoleOne or more RRUs can be installed on a pole.8.2.1 Installing a Single RRUThis section describes the procedure and precautions for installing a single RRU on a pole.PrerequisitesBefore you install an RRU on a pole secured on a tower, the RRU and its mounting bracketsare hoisted onto the tower. For details, see 7.1 Hoisting an RRU onto a Tower.The hoist clamp on the main bracket is secured properly.NOTICElDo not stand the RRU upright because the RF ports cannot support the weight of the RRU.lPlace a foam pad or cardboard under the RRU to protect the RRU housing from damageduring the installation.ProcedureStep 1 Determine a position for installing the mounting brackets.lIf the pole must be installed on a tower, determine a position for installing the mountingbrackets according to the instructions in 3.5.1 Clearance for a Single RRU.lIf the pole must be installed on the ground, determine a position for installing themounting brackets according to Figure 8-3.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.50
Figure 8-3 Distance between the mounting brackets and the ground NOTEAs shown in the figure above, it is recommended that the mounting kits be installed at a position1200 mm (47.24 in.) to 1600 mm (59.06 in.) high above the ground. If the space is insufficient,only the 3.5 Installation Clearance Requirements of an RRU needs to be provided.Step 2 Install the RRU mounting brackets, as shown in Figure 8-4.Figure 8-4 Installing the RRU mounting brackets NOTEVerify that the arrows on the mounting brackets are pointing up.1. Adjust the position of the nut and remove one end of the square-neck bolt from the sloton the auxiliary bracket.2. Slide the mounting brackets onto the pole horizontally and insert the square-neck boltinto the slot.Step 3 Use a 16 mm (0.63 in.) M10 torque wrench to tighten the nuts to 40 N·m (354.03 lbf·in.) sothat the mounting brackets are secured onto the pole, as shown in Figure 8-5.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.51
NOTICETighten the nuts on the two square-neck bolts alternatively. After the main and auxiliarybrackets are secured properly, measure the spacing between the brackets on both sides andensure that the spacing is the same on the two sides.Figure 8-5 Securing the RRU mounting brackets Step 4 Install the RRU onto the main bracket, as shown in Figure 8-6.Figure 8-6 Installing the RRU onto the main bracket Step 5 Use an inner hexagon torque screwdriver to tighten the captive screw into the holes on the topof the attachment plate and main bracket to 5 N·m (44.25 lbf·in.) so that the attachment plateand main bracket are firmly secured, as shown in Figure 8-7.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.52
Figure 8-7 Securing the captive screw into the connection hole ----End8.2.2 Installing Two RRUsThis section describes the procedure and precautions for installing two RRUs on a pole.PrerequisitesThe hoist clamp on the main bracket is secured properly.NOTICElDo not stand the RRU upright because the RF ports cannot support the weight of the RRU.lPlace a foam pad or cardboard under the RRU to protect the RRU housing from damageduring the installation.ProcedureStep 1 Install the first RRU onto the main bracket, as shown in Figure 8-8. For details, see 8.2.1Installing a Single RRU.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.53
Figure 8-8 Installing the first RRU onto the main bracket Step 2 Use an M6 inner hexagon screwdriver to remove the four inner hexagon screws from thesecond set of mounting brackets, and remove the main bracket from the auxiliary bracket, asshown in Figure 8-9.Figure 8-9 Removing the RRU main bracket(1) Main bracket (2) Pole installation bracket Step 3 Install the removed main bracket on one side of the first main bracket, as shown in Figure8-10.NOTICEThe second main bracket must be installed with the opening ends of U-shaped slots on bothsides facing downwards.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.54
Figure 8-10 Installing the second main bracket(1) Removed main bracket NOTEThe main mounting bracket for installing a 12 L blade RRU can connect to the main mounting bracketfor installing a common RRU in the scenarios of adding RRUs, as shown in Figure 8-11.Figure 8-11 Connect to the main mounting bracket for installing a common RRU(1) Main mounting bracket for a 12 L blade RRU (2) Main mounting bracket for a common RRU Step 4 Install the second RRU onto the main bracket, as shown in Figure 8-12.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.55
Figure 8-12 Installing the second RRU onto the main bracket NOTICEAfter installing each RRU on its main bracket, use an inner hexagon torque screwdriver totighten the captive screw into the holes of the attachment plate and main bracket to 5 N·m(44.25 lbf·in.) so that the attachment plate and main bracket are firmly secured, as shown inFigure 8-13.Figure 8-13 Securing the captive screw into the connection hole RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.56
Step 5 Install the metal sheet for neighboring RRUs, as shown in Figure 8-14.Figure 8-14 Installing the metal sheet(1) Screw (2) Metal sheet 1. Use an M6 Phillips screwdriver to loosen the screw on the metal sheet farther from thehandle of the second RRU and remove the screw.2. Use an M6 Phillips screwdriver to loosen the screw on the metal sheet closer to handle ofthe second RRU. Then rotate the metal sheet to align the vacant hole in the metal sheetwith a hole on the top of the first RRU.3. Insert the removed screw into the hole on the top of the first RRU and use an M6 torquescrewdriver to tighten the screw to 5 N·m (44.25 lbf·in.).----End8.2.3 Installing Three or More RRUsThe section describes the procedure and precautions for installing three or more RRUs on apole.PrerequisitesThe hoist clamp on the main bracket is secured properly.NOTICElDo not stand the RRU upright because the RF ports cannot support the weight of the RRU.lPlace a foam pad or cardboard under the RRU to protect the RRU housing from damageduring the installation.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.57
ContextA pole supports the installation of three, four, or six RRUs. The procedures for installing themare the same. Following is the procedure of installing four RRUs on a pole.NOTICEModules can be combined only when installed on one or more poles, and a maximum of threemodules can be combined.ProcedureStep 1 Install the two RRUs, as shown in Figure 8-15. For details, see 8.2.2 Installing Two RRUs.Figure 8-15 Two RRUs installed on a pole Step 2 Use an M6 inner hexagon screwdriver to remove the four inner hexagon screws from thesecond set of mounting brackets, and remove the main bracket from the auxiliary bracket, asshown in Figure 8-16.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.58
Figure 8-16 Removing the RRU main bracket(1) Main bracket (2) Pole installation bracket Step 3 Install the third main bracket and install the third RRU onto the third main bracket. Then usean inner hexagon torque screwdriver to tighten the captive screw into the connection holes onthe top of the attachment plate and main bracket for the RRU, with a torque of 5 N·m (44.25lbf·in.), as shown in Figure 8-17.NOTICEThe third main bracket must be installed with the opening ends of U-shaped slots on bothsides facing downwards.Figure 8-17 Installing the third RRU onto the third main bracket RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.59
NOTEThe main mounting bracket for installing a 12 L blade RRU can connect to the main mounting bracketfor installing a common RRU in the scenarios of adding RRUs, as shown in Figure 8-11.Figure 8-18 Connect to the main mounting bracket for installing a common RRU(1) Main mounting bracket for a 12 L blade RRU (2) Main mounting bracket for a common RRU Step 4 Install the metal sheet for neighboring RRUs, as shown in Figure 8-19.Figure 8-19 Installing the metal sheet(1) Screw (2) Metal sheet 1. Use an M6 Phillips screwdriver to loosen the screw on the metal sheet farther from thehandle of the first RRU and remove the screw.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.60
2. Use an M6 Phillips screwdriver to loosen the screw on the metal sheet closer to handle ofthe first RRU. Then rotate the metal sheet to align the vacant hole in the metal sheet witha hole on the top of the third RRU.3. Insert the removed screw into the hole on the top of the third RRU and use an M6 torquescrewdriver to tighten the screw to 5 N·m (44.25 lbf·in.).Step 5 Install the second set of RRU mounting brackets above or below the first set of RRUmounting brackets and maintain a space equal to or greater than 80 mm (3.15 in.) between thetwo sets of brackets, as shown in Figure 8-20.Figure 8-20 Installing the second set of RRU mounting brackets Step 6 Install the fourth RRU onto the fourth main bracket, use an inner hexagon torque screwdriverto tighten the captive screw into the holes of the attachment plate and main bracket to 5 N·m(44.25 lbf·in.) so that the attachment plate and main bracket are firmly secured, as shown inFigure 8-21.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.61
Figure 8-21 Installing the fourth RRU onto the fourth main bracket ----End8.3 Installing the RRU on U-steelThis section describes the procedure and precautions for installing the RRU on U-steel. AnRRU can be installed on U-steel secured on the ground or a tower. Each piece of U-steelallows only one RRU to be installed in standard or reverse mode.PrerequisitesBefore you install an RRU on U-steel secured on a tower, the RRU and its mounting bracketsare hoisted onto the tower. For details, see 7.1 Hoisting an RRU onto a Tower.The hoist clamp on the main bracket is secured properly.NOTICElDo not stand the RRU upright because the RF ports cannot support the weight of the RRU.lPlace a foam pad or cardboard under the RRU to protect the RRU housing from damageduring the installation.ContextFigure 8-22 shows the top view of the RRU installed on U-steel.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.62
NOTICEWhen the width of the narrower edges of the U-steel is less than 40 mm (1.57 in.), only the aand b modes are supported.Figure 8-22 Top view of the RRU(1) U-steel ProcedureStep 1 Determine a position for installing the mounting brackets.lIf the RRU must be installed on U-steel secured on a tower, see 3.5.1 Clearance for aSingle RRU to determine a position.lIf the RRU must be installed on U-steel secured on the ground, see Figure 8-23 todetermine a position.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.63
Figure 8-23 Distance between the mounting brackets and the ground NOTEAs shown in the figure above, it is recommended that the mounting kits be installed at a position1200 mm (47.24 in.) to 1600 mm (59.06 in.) high above the ground. If the space is insufficient,only the 3.5 Installation Clearance Requirements of an RRU needs to be provided.Step 2 Install the RRU mounting brackets, as shown in Figure 8-24.Figure 8-24 Installing the RRU mounting brackets NOTEVerify that the arrows on the mounting brackets are pointing up.1. Adjust the position of the nut and remove one end of the square-neck bolt from the sloton the auxiliary bracket.2. Slide the mounting brackets onto the U-steel horizontally and insert the square-neck boltinto the slot.Step 3 Use a 16 mm (0.67 in.) M10 torque wrench to tighten the nuts to 40 N·m (354.03 lbf·in.) sothat the mounting brackets are secured onto the U-steel, as shown in Figure 8-25.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.64
NOTICETighten the nuts on the two square-neck bolts alternatively. After the main and auxiliarybrackets are secured properly, measure the spacing between the brackets on both sides andensure that the spacing is the same on the two sides.Figure 8-25 Securing the RRU mounting brackets Step 4 Use an inner hexagon screwdriver to remove the attachment plate from one side of the RRU,reinstall the attachment plate onto the rear of the RRU, and tighten the four stainless screws to5 N·m (44.25 lbf·in.), as shown in Figure 8-26.Figure 8-26 Installing the attachment plate onto the rear of the RRU RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.65
Step 5 Install the RRU onto the main bracket, as shown in Figure 8-27.Figure 8-27 Installing the RRU onto the main bracket Step 6 Use an inner hexagon screwdriver to tighten the captive screw into the holes on the top of theattachment plate and main bracket to 5 N·m (44.25 lbf·in.) so that the attachment plate andmain bracket are firmly secured, as shown in Figure 8-28.Figure 8-28 Securing the captive screw into the connection hole ----EndRRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.66
8.4 Installing the RRU on Angle SteelThis section describes the procedure and precautions for installing the RRU on angle steel. AnRRU can be installed on angle steel secured on the ground or a tower. Each piece of anglesteel allows only one RRU to be installed in standard or reverse mode.PrerequisitesBefore you install an RRU on angle steel secured on a tower, the RRU and its mountingbrackets are hoisted onto the tower. For details, see 7.1 Hoisting an RRU onto a Tower.The hoist clamp on the main bracket is secured properly.NOTICElDo not stand the RRU upright because the RF ports cannot support the weight of the RRU.lPlace a foam pad or cardboard under the RRU to protect the RRU housing from damageduring the installation.ContextFigure 8-29 shows the top view of the RRU installed on angle steel.Figure 8-29 Top view of the RRU(1) Angle steel ProcedureStep 1 Determine a position for installing the mounting brackets.lIf the RRU must be installed on angle steel secured on a tower, see 3.5.1 Clearance fora Single RRU to determine a position.lIf the RRU must be installed on angle steel secured on the ground, see Figure 8-30 todetermine a position.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.67
Figure 8-30 Distance between the mounting brackets and the ground NOTEAs shown in the figure above, it is recommended that the mounting kits be installed at a position1200 mm (47.24 in.) to 1600 mm (59.06 in.) high above the ground. If the space is insufficient,only the 3.5 Installation Clearance Requirements of an RRU needs to be provided.Step 2 Install the RRU mounting brackets, as shown in Figure 8-31.Figure 8-31 Installing the RRU mounting brackets NOTEVerify that the arrows on the mounting brackets are pointing up.1. Adjust the position of the nut and remove one end of the square-neck bolt from the sloton the auxiliary bracket.2. Slide the mounting brackets onto the angle steel horizontally and insert the square-neckbolt into the slot.Step 3 Use a 16 mm (0.67 in.) M10 torque wrench to tighten the nuts to 40 N·m (354.03 lbf·in.) sothat the mounting brackets are secured onto the angle steel, as shown in Figure 8-32.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.68
NOTICETighten the nuts on the two square-neck bolts alternatively. After the main and auxiliarybrackets are secured properly, measure the spacing between the brackets on both sides andensure that the spacing is the same on the two sides.Figure 8-32 Securing the RRU mounting brackets Step 4 Use an inner hexagon screwdriver to remove the attachment plate from one side of the RRU,reinstall the attachment plate onto the rear of the RRU, and tighten the four stainless screws to5 N·m (44.25 lbf·in.), as shown in Figure 8-33.Figure 8-33 Installing the attachment plate onto the rear of the RRU RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.69
Step 5 Install the RRU onto the main bracket, as shown in Figure 8-34.Figure 8-34 Installing the RRU onto the main bracket Step 6 Use an inner hexagon screwdriver to tighten the captive screw into the holes on the top of theattachment plate and main bracket to 5 N·m (44.25 lbf·in.) so that the attachment plate andmain bracket are firmly secured, as shown in Figure 8-35.Figure 8-35 Securing the captive screw into the connection hole ----EndRRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.70
8.5 Installing the RRU on a WallThis section describes the procedure and precautions for installing the RRU on a wall.PrerequisitesThe hoist clamp on the main bracket is secured properly.NOTICElDo not stand the RRU upright because the RF ports cannot support the weight of the RRU.lPlace a foam pad or cardboard under the RRU to protect the RRU housing from damageduring the installation.ContextThe wall on which RRUs are installed must meet the following requirements:lFor each RRU, the wall must be able to bear a weight four times the RRU's weight andthe bolts' pulling force of 1.25 kN (281.25 lbf) vertical to the wall.lExpansion anchor bolts must be tightened to 30 N·m (265.52 lbf·in.) so that the boltsstay secured without damaging the wall.ProcedureStep 1 Disassemble the RRU mounting brackets, as shown in Figure 8-36.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.71
Figure 8-36 Disassembling the mounting brackets(1) Main bracket (2) Square-neck bolt (3) Pole installation bracket (4) Auxiliary bracket(5) Flat washer (6) Spring washer (7) Nut (8) Plastic cap 1. Use an M6 inner hexagon torque screwdriver to remove the four inner hexagon screwson the pole installation bracket, and remove the main bracket from the pole installationbracket.2. Use an M10 torque wrench to loosen the nuts on the two square-neck bolts, and removethe plastic cap, nuts, spring washers, flat washers, square-neck bolts, and poleinstallation bracket from the auxiliary bracket.Step 2 Place the pole installation bracket against the installation position, use a level to verify thatthe pole installation bracket is placed horizontally, and then mark anchor points with a marker,as shown in Figure 8-37.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.72
Figure 8-37 Marking anchor points(1) Level (2) Pole installation bracket (3) RRU NOTEAs shown in the figure above, it is recommended that the pole installation bracket be installed at aposition 1200 mm (47.24 in.) to 1600 mm (59.06 in.) high above the ground. If the space is insufficient,only the 3.5 Installation Clearance Requirements of an RRU needs to be provided.Step 3 Drill holes at the anchor points, and then insert expansion anchor bolt assemblies, as shown inFigure 8-38.Figure 8-38 Drilling a hole and inserting expansion anchor bolt assemblies(1) M10x80 bolt (2) Nut (3) Spring washer (4) Flat washer (5) Expansion tube 1. Use a hammer drill with a Ф12 bit to drill holes vertically at the marked anchor pointswith the depth ranging from 55 mm (2.17 in.) to 60 mm (2.36 in.), use a vacuum cleanerto clear the dust out from inside and around the holes, and measure the distances betweenRRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.73
holes. If any of the hole is beyond the acceptable range, mark a new anchor point anddrill a new hole.NOTICETake proper safety measures to protect your eyes and respiratory tract against the dustbefore drilling holes.2. Tighten the expansion anchor bolts slightly and place one vertically into each hole.3. Use a rubber mallet to pound the expansion anchor bolt until it goes all the way into thehole.4. Tighten and then loosen the expansion bolt, and remove the M10 bolt, spring washer,and flat washer in sequence.NOTICEAfter dismantling an expansion anchor bolt, ensure that the top of the expansion tube ison the same level as the wall. Otherwise, the device cannot be installed on the wallevenly and securely.Step 4 Install the pole installation bracket on the expansion anchor bolts, place the flat washers,spring washers, and nuts through the expansion anchor bolts in sequence, and then use a 16mm (0.63 in.) torque socket to tighten the nuts to 30 N·m (265.52 lbf·in.), as shown in Figure8-39.Figure 8-39 Installing the pole installation bracket on the expansion anchor bolts RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.74
NOTICEVerify that the arrows on the pole installation bracket are pointing up.Step 5 Install the main bracket onto the pole installation bracket, and use an inner hexagonscrewdriver to tighten four M6x16 inner hexagon screws to 5 N·m (44.25 lbf·in.) so that themain bracket and pole installation bracket are firmly secured, as shown in Figure 8-40.Figure 8-40 Installing the main bracket (1) Main bracket (2) Pole installation bracketStep 6 Use an inner hexagon screwdriver to remove the attachment plate from one side of the RRU,reinstall the attachment plate onto the rear of the RRU, and tighten the four stainless screws to5 N·m (44.25 lbf·in.), as shown in Figure 8-41.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.75
Figure 8-41 Installing the attachment plate onto the rear of the RRU Step 7 Install the RRU onto the main bracket, as shown in Figure 8-42.Figure 8-42 Installing the RRU onto the main bracket Step 8 Use an inner hexagon screwdriver to tighten the captive screw into the holes on the top of theattachment plate and main bracket to 5 N·m (44.25 lbf·in.) so that the attachment plate andmain bracket are firmly secured, as shown in Figure 8-43.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.76
Figure 8-43 Securing the captive screw into the connection hole ----End8.6 Installing an RRU on an IFS06This section describes the procedure and precautions for installing an RRU on an IFS06.PrerequisitesThe hoist clamp on the main bracket is secured properly.NOTICElDo not stand the RRU upright because the RF ports cannot support the weight of the RRU.lPlace a foam pad or cardboard under the RRU to protect the RRU housing from damageduring the installation.ContextlThe upper and lower adjustable beams on an IFS06 can be moved up and down to fit forheights of RRUs.lRRUs can be installed on an IFS06 only when the ambient temperature is higher than orequal to the lowest working temperature of the RRU and at least 5°C (41°F) lower thanthe highest working temperature of the RRU. In this scenario, the IFS06 supports at leastthree RRUs. When the ambient temperature is higher than or equal to the lowest workingtemperature of the RRU and at least 10°C (50°F) lower than the highest workingtemperature of the RRU, the IFS06 supports a maximum of six RRUs.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.77
NOTEFor details about the operating temperature of the RRU, see section "Technical Specifications ofRRUs" in 3900 Series Base Station Technical Description.lInstall RRUs in the sequence from bottom to top and from left to right.lThis section describes how to install an RRU in height-unrestricted scenarios. Theprocedure for installing an RRU in height-restricted scenarios is the same as that inheight-unrestricted scenarios.lWhen installing the pole installation bracket, you need to use the M10x50 bolts deliveredwith the IFS06.lRubber washers are easily compressed or broken, whereas do not need to be replaced.ProcedureStep 1 Disassemble the RRU mounting brackets, as shown in Figure 8-44.Figure 8-44 Disassembling the mounting brackets(1) Main bracket (2) Square-neck bolt (3) Pole installation bracket (4) Auxiliary bracket(5) Flat washer (6) Spring washer (7) Nut (8) Plastic cap 1. Use an M6 inner hexagon torque screwdriver to remove the four inner hexagon screwson the pole installation bracket, and remove the main bracket from the pole installationbracket.2. Use an M10 torque wrench to loosen the nuts on the two square-neck bolts, and removethe plastic cap, nuts, spring washers, flat washers, square-neck bolts, and poleinstallation bracket from the auxiliary bracket.Step 2 Use the M10x50 bolts delivered with the IFS06 to secure the pole installation bracket to theIFS06, and then use an M10 torque socket wrench to secure the bolts to 30 N·m (265.52lbf·in.).RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.78
NOTICEEnsure that the arrows on the pole installation bracket are pointing up.lHeight-restricted scenariosUse one finger to push and remove the rubber plugs on the beam and then install the poleinstallation bracket, as shown in Figure 8-45.Figure 8-45 Installing the pole installation bracket in height-restricted scenarios(1) Spring washer (2) Rubber washerlHeight-unrestricted scenariosInstall the pole installation bracket, as shown in Figure 8-46.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.79
Figure 8-46 Installing the pole installation bracket in height-unrestricted scenarios(1) Spring washer (2) Rubber washerStep 3 Attach the main bracket to the pole installation bracket, and use an inner hexagon screwdriverto tighten four M6x16 screws to 5 N·m (44.25 lbf·in.) so that the main bracket and poleinstallation bracket are firmly secured, as shown in Figure 8-47.Figure 8-47 Installing the main bracket(1) Main bracket (2) Pole installation bracket RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.80
Step 4 Attach the RRU to the main bracket, and then use an inner hexagon screwdriver to tighten thecaptive screw into the holes of the attachment plate and main bracket to 5 N·m (44.25 lbf·in.)so that the attachment plate and main bracket are firmly secured, as shown in Figure 8-48.Figure 8-48 Installing the RRU onto the main bracket Step 5 Install the RRUs on the lower level from left to right, as shown in Figure 8-49.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.81
Figure 8-49 Installing RRUs on the lower level Step 6 Optional: When the ambient temperature is equal to or higher than the lowest operatingtemperature of the RRU and at least 10°C (10°F) lower than the highest operating temperatureof the RRU, repeat the preceding steps to install the RRUs on the higher level, as shown inFigure 8-50.RRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.82
Figure 8-50 Installing RRUs on the higher level----EndRRU3268Installation Guide 8 Installing the RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.83
9 Installing RRU CablesAbout This ChapterThis chapter describes the procedure for installing RRU cables.9.1 Cabling RequirementsCables must be laid out according to the specified cabling requirements to prevent signalinterference.9.2 Cable ConnectionsThis section describes the cable connections for a single RRU and multiple RRUs.9.3 Installation ProcessThis section describes the process of installing RRU cables.9.4 RRU Cable ListThis section describes RRU cable connections.9.5 Installing an RRU PGND CableThis section describes the procedure for installing an RRU PGND cable.9.6 Installing an RRU RF JumperThis section describes the procedure for installing an RRU RF jumper.9.7 Installing an RRU AISG Multi-Wire Cable and AISG Extension CableThis section describes the procedures for installing an RRU AISG multi-wire cable and AISGextension cable.9.8 Installing an RRU Alarm CableThis section describes the procedure for installing an RRU alarm cable.9.9 Opening the Cover Plate of an RRU Cabling CavityThis section describes the procedure for opening the cover plate of an RRU cabling cavity.9.10 Installing an RRU Power CableThis section describes the procedure for installing an RRU power cable.9.11 Installing a CPRI Fiber Optic CableThis section describes the procedure for installing a CPRI fiber optic cable.9.12 Closing the Cover Plate of an RRU Cabling CavityRRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.84
This section describes the procedure for closing the cover plate of an RRU cabling cavity.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.85
9.1 Cabling RequirementsCables must be laid out according to the specified cabling requirements to prevent signalinterference.NOTEIf a cable listed below is not required, skip the cabling requirements of the cable.General Cabling RequirementsBending radius requirementslThe bending radius of a 7/8'' feeder must be greater than 250 mm (9.84 in.), and thebending radius of a 5/4'' feeder must be greater than 380 mm (14.96 in.).lThe bending radius of a 1/4'' jumper must be greater than 35 mm (1.38 in.). The bendingradius of a super-flexible 1/2'' jumper must be greater than 50 mm (1.97 in.), and thebending radius of an ordinary 1/2'' jumper must be greater than 127 mm (5 in.).lThe bending radius of a power cable or PGND cable must be at least three times itsdiameter.lThe bending radius of a fiber optic cable is at least 20 times of its diameter, and thebending radius of a breakout cable is at least 30 mm (1.18 in.).lThe bending radius of an E1/T1 cable must be at least three times its diameter.lThe bending radius of a signal cable must be at least five times its diameter.Cable binding requirementslCables of the same type must be bound together.lDifferent types of cables must be separately laid out and bound, with a minimumdistance of 30 mm (1.18 in.) from each other.lThe cables must be bound tightly and neatly. The sheaths of the cables must not bedamaged.lThe cable ties must face the same direction, and those at the same horizontal line must bein a straight line.lThe excess of the indoor cable ties is cut off. The excess of 5 mm (0.197 in.) of theoutdoor cable ties is reserved, and the cut surfaces are smooth without sharp edges.lAfter cables are installed, labels or nameplates must be attached to the cables at theirends, curves, and interconnection positions.Security requirementslWhen routing cables, avoid sharp objects, for example sharp edges on the wall. Ifnecessary, use tubes to protect the cables.lWhen routing cables, keep the cables away from heat sources and use heat insulationmaterials to insulate the cables from the heat sources.lReserve a proper distance (0.1 m or 3.937 in. is recommended) between equipment andcables especially at the cable curves to protect the cables and equipment.Indoor cabling requirementslRoute each cable into the room through the feeder window.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.86
lReserve drip loops for all cables outside the feeder window before routing them into theroom. Ensure that the radiuses of the drip loops are greater than or equal to the minimumbending radiuses of the cables.lWhen routing a cable into the room, ensure that a person is assisting you in the room.lApply waterproof treatment to the feeder window.Outdoor Cabling RequirementslAfter being connected to a ground clip on power cables, a ground cable must be routeddownwards to prevent water from entering the equipment to which the power cablesconnect.lProtect outdoor cables against potential damage. For example, put the cables throughtubes.lThe cables to be protected include AC power cables, transmission cables, and cables laidout underground.lWhen routing cables through tubes on the ground below the cabinet, put a 30 mm to 50mm (1.18 in. to 1.97 in.) length of the tubes into the base of the cabinet but do not putthe tubes into the cabinet. Use waterproof tape or waterproof silicon gel to block bothends of the tubes and use sheet metal tabs to secure the tubes to the cable holes in thebase.lWhen routing cables through tubes along a metal cable trough below the cabinet, do notput the tubes into the base of the cabinet but cover the cable trough and connect the tubesto the cable holes in the base.lWhen routing RRU cables, ensure that the highest positions of the routes of all RRUcables (except RF cables and AISG cables) must be lower than the bottom of the RRU.lUse clips to secure cables outdoors. For the method of installing a clip, see theinstallation guide delivered with the clip.lArrange cables neatly along the routing direction and use clips to secure the cables.lDetermine the positions where the clips are installed according to the actual situation.For example, 7/8" feeders are secured with clips at an interval of 1.5 m to 2 m (4.92 ft to6.56 ft), CPRI fiber optic cables and power cables are secured with clips at an interval of1 m to 1.5 m (3.28 ft to 4.92 ft). Ensure that the clips are evenly spaced and in the samedirection.lWhen fastening cables with a clip, ensure that the cables are aligned neatly and arerouted through the holes in the clip. Do not stretch the cables too tightly.NOTEThere are two types of clips: 3-hole clip and 6-hole clip, which are described as follows:lA 3-hole clip is shown by illustration a in the following figure. It is often used to fasten feeders.lA 6-hole clip is shown by illustration b in the following figure. It is often used to fasten power cablesand CPRI fiber optic cables.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.87
Figure 9-1 Exterior of the clips(1) Cable hole for feeders (2) Cable hole for fiber optic cables (3) Cable hole for power cables The following figure shows the cables secured on a cable tray.Figure 9-2 Cables secured on a cable tray(1) 3-hole clip (2) 6-hole clip The following figure shows the cables secured on a tower.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.88
Figure 9-3 Cables secured on a tower(1) 3-hole clip (2) 6-hole clip Special Cabling RequirementsCabling of power cableslPower cables must be installed in the position specified in engineering designdocuments.lIf the length of power cables is insufficient, replace the cables rather than addingconnectors or soldering joints to lengthen the cables.lCables can only be laid out under well-planned instructions. The cabling activities offiber optic cables are allowed only when qualified personnel and communicationfacilities are available.lDo not circle and twist cables.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.89
lAfter routing a DC power cable onto the platform on a tower, route it along the shortestpath to the rails surrounding the platform, and route it along the inside of the rails.lAfter routing a DC power cable close to the equipment on a tower, use clips to secure thepower cable onto a pole or the rails surrounding the platform. Ensure that there is noexcessively long distance between the equipment and the position where the power cableis secured.Cabling of PGND cableslPGND cables for a base station must be connected to the same group of ground bars.lPGND cables must be buried in the ground or routed indoors.lThe external conductor of the coaxial wire and the shield layer of the shielded cable musthave proper electrical contact with the metal surface of the equipment to which they areconnected.lPGND cables and signal cables must be installed separately. A certain distance must bereserved between them to prevent interference from each other.lSwitches or fuses must not be installed on the PGND cables.lOther devices must not be used for electrical connections of the PGND cables.lAll the metal parts in the housing of the equipment must be reliably connected to theground terminal.Cabling of E1 cableslE1 cables must not cross power cables, PGND cables, or RF cables when laid out. Iftransmission cables are laid out with power cables, PGND cables, or RF cables inparallel, the spacing between them must be greater than 30 mm (1.18 in.).lE1 cables are lined up straight and bound neatly with cable ties.lSufficient slack is provided for E1 cables at turns.lE1 cables must not be pressed by the door of the cabinet when routed, as shown in thefollowing figure.Figure 9-4 E1 cables routed in the cabinet Cabling of fiber optic cableslAt least three people are required for laying out fiber optic cables. The cabling activitiesof fiber optic cables are allowed only when qualified personnel and communicationfacilities are available.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.90
lThe operating temperature of fiber optic cables ranges from -40ºC to +60ºC (-40ºF to+140ºF). If the actual temperature is beyond this range, take protective measures orselect another route.lDo not circle and twist cables.lDo not bind a fiber optic cable at the position where it bends.lDo not stretch, step on, or place heavy objects on fiber optic cables. Keep the fiber opticcables away from sharp objects.lWhen fiber optic cables are routed, the excess of the fiber optic cables must be coiledaround special devices, such as a fiber coiler.lAn unarmored fiber optic cable must be bound using binding straps. If a fiber optic patchcord needs to be secured in a cabinet or a piece of equipment, use binding straps to bindit and then use cable ties to secure the binding straps to the cabinet or equipment. Ensurethat the fiber optic cables can flexibly move in the cable ties. Do not bend the fiber opticcables sharply. The following figure shows how to bind the fiber optic cables correctly.Figure 9-5 Binding fiber optic cables lWhen coiling fiber optic cables, apply even strength. Do not bend the fiber optic cableswith force.lUnused optical connectors must be covered with dustproof caps.lThe fiber optic cables must not be pressed by the door of the cabinet when routed, asshown in the following figures.Figure 9-6 CPRI fiber optic cables routed in the cabinet (1)RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.91
 Figure 9-7 CPRI fiber optic cables routed in the cabinet (2) Figure 9-8 FE/GE fiber optic cables routed in the cabinet lAfter routing a fiber optic cable onto the platform on a tower, route it along the shortestpath to the rails surrounding the platform, and route it along the inside of the rails.lAfter routing a fiber optic cable close to the equipment on a tower, use clips to secure thefiber optic cable onto a pole or the rails surrounding the platform. Ensure that there is noexcessively long distance between the equipment and the position where the cable issecured.lCoil the excess of the fiber optic cables near the equipment on the tower before securingthe cables on the tower.9.2 Cable ConnectionsThis section describes the cable connections for a single RRU and multiple RRUs.NOTElA lower-level RRU obtains power directly from the external power system, but not from an upper-level RRU using a power cable.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.92
Figure 9-9 shows the cable connections for a single RRU.Figure 9-9 Cable connections for a single RRU(1) PGND cable (2) RRU RF jumper (3) RRU AISG multi-wire cable(4) RRU AISG extension cable (5) RRU power cable (6) CPRI fiber optic cable(7) RRU alarm cable - - Figure 9-10 shows the cable connections for multiple RRUs.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.93
Figure 9-10 Cable connections for multiple RRUs(1) PGND cable (2) RRU RF jumper (3) RRU power cable(4) CPRI fiber optic cable - - 9.3 Installation ProcessThis section describes the process of installing RRU cables.Figure 9-11 shows the process of installing RRU cables.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.94
Figure 9-11 Process of installing RRU cables 9.4 RRU Cable ListThis section describes RRU cable connections.Table 9-1 lists RRU cables.Table 9-1 RRU cablesCable One End The Other EndConnector InstallationPositionConnector InstallationPositionRRU PGNDCableOT terminal(M6, 16 mm2 or0.025 in.2)Groundterminal on theRRUOT terminal(M8, 16 mm2 or0.025 in.2)Ground terminalon the ground barRRU PowerCableTool-less femaleconnector(pressfit type)NEG(-) andRTN(+) portson the RRUDepending onthe power supplyequipmentExternal powerequipmentRRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.95
Cable One End The Other EndConnector InstallationPositionConnector InstallationPositionRRU AlarmCableDB15waterproof maleconnectorEXT_ALMport on theRRUCord endterminalExternal alarmdeviceCPRI FiberOptic CableDLC connector CPRI0 port onthe RRUDLC connector CPRI port on aboard in the BBURRU RFJumperDIN maleconnectorANT_TX/RXA orANT_TX/RXB port on theRRUDIN maleconnectorAntenna systemRRU AISGMulti-WireCableDB9 waterproofmale connectorRET port onthe RRUStandard AISGfemale connectorStandard AISGmale connectoron the RCU or onthe AISGextension cableRRU AISGExtensionCableStandard AISGmale connectorStandard AISGfemaleconnector onthe AISGmulti-wirecableStandard AISGfemale connectorStandard AISGmale connectoron the RCU 9.5 Installing an RRU PGND CableThis section describes the procedure for installing an RRU PGND cable.ContextThe cross-sectional area of an RRU PGND cable is 16 mm2 (0.025 in.2). The cable has an M6OT terminal at one end and an M8 terminal at the other end.DANGERInstall RRU PGND cables by strictly following the following operations. Otherwise, damageto the RRU or personal injury may occur.ProcedureStep 1 According to the actual cable route, cut the PGND cable into a proper length to prepare anRRU PGND cable. Then add an OT terminal at each end of the cable according to theinstructions in Assembling the OT Terminal and the Power Cable.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.96
Step 2 Install the RRU PGND cable.Connect the M6 OT terminal at one end of the PGND cable to the ground terminal at the RRUbottom and the M8 OT terminal at the other end to the external ground bar, as shown inFigure 9-12.Figure 9-12 Installing an RRU PGND cable NOTECrimp OT terminals in correct positions, as shown in Figure 9-13.Figure 9-13 Correct position of an OT terminal Step 3 Label the installed cables according to the instructions in Attaching a Cable-Tying Label.----End9.6 Installing an RRU RF JumperThis section describes the procedure for installing an RRU RF jumper.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.97
ProcedureStep 1 Connect the DIN male connector at one end of the RRU RF jumper to the ANT port on theRRU, and use a torque wrench to tighten the connector to 25 N·m (221.27 lbf·in.), as shownin Figure 9-14.Figure 9-14 Installing an RRU RF jumper NOTICEOn AC-powered electric railways, such as high speed railways, when leaky cables areconnected to RRUs installed in tunnels, high-voltage-resistance DC blocks must be installedbetween RRU RF jumpers and the leaky cables to protect the RRUs against damage.Step 2 Link the other end of the RF jumper to the external antenna system.Step 3 Waterproof the connectors of the RF jumper by referring to Figure 9-15.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.98
Figure 9-15 Waterproofing a connector of the RF jumper (1) Waterproof tape (2) PVC insulation tapeNOTElBefore wrapping waterproof tape, stretch the tape evenly until the length of the tape becomes twice itsoriginal length.lDo not stretch the PVC insulation tape when wrapping the PVC insulation tape.lWrap each layer of tape around the connector tightly and neatly, and ensure that each layer of tapeoverlaps more than 50% of the preceding layer. Ensure that neighboring layers are stuck to each other.lEnsure that the adhesive surface of the tape overlaps the lower layer.lWhen cutting off the cable ties, reserve a redundant length of 3 mm (0.12 in.) to 5 mm (0.2 in.).1. Wrap three layers of waterproof tape on the connector, first from bottom up, then fromtop down, and finally from bottom up. Start wrapping the connector at a position 50 mm(1.97 in.) away below the bottom of the connector to the top of the connector, first frombottom up, then from top down, and finally from bottom up. Cut off the redundant tapeafter three layers are wrapped. Wrap each layer of tape around the connector tightly.2. Wrap three layers of PVC insulation tape. Start the wrapping at a position 30 mm (1.18in.) away below the bottom of the waterproof tape to the top of the connector, first frombottom up, then from top down, and finally from bottom up. Cut off the redundant tapeafter three layers are wrapped. Wrap each layer of tape around the connector tightly.3. Start binding cable ties to the cable at a position 3 mm (0.12 in.) to 5 mm (0.2 in.) awayfrom one end of the PVC insulation tape.Step 4 Check the dustproof caps on antenna connectors. In outdoor scenarios, dustproof caps must bewaterproofed, as shown in Figure 9-16.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.99
NOTICEDo not remove dustproof caps from vacant antenna connectors.Figure 9-16 Waterproofing a dustproof cap(1) Dustproof cap (2) Waterproof tape (3) PVC insulation tapeNOTElBefore wrapping waterproof tape, stretch the tape evenly until the length of the tape becomes twice itsoriginal length.lDo not stretch the PVC insulation tape when wrapping the PVC insulation tape.lWrap each layer of tape around the connector tightly and neatly, and ensure that each layer of tapeoverlaps more than 50% of the preceding layer. Ensure that neighboring layers are stuck to each other.lEnsure that the adhesive surface of the tape overlaps the lower layer.lWhen cutting off the cable ties, reserve a redundant length of 3 mm (0.12 in.) to 5 mm (0.2 in.). 1. Verify that dustproof caps are not removed.2. Wrap three layers of waterproof tape on the connector, first from bottom up, then fromtop down, and finally from bottom up. Wrap each connector with three layers ofwaterproof tape, from bottom up, then from top down, and finally from bottom up. Donot cut the tape until all the three layers of the tape are already wrapped. Cut off theredundant tape after three layers are wrapped. Wrap each layer of tape around theconnector tightly.3. Wrap three layers of PVC insulation tape. Wrap each connector with three layers ofwaterproof tape, from bottom up, then from top down, and finally from bottom up. Donot cut the tape until all the three layers of the tape are already wrapped. Cut off theredundant tape after three layers are wrapped. Wrap each layer of tape around theconnector tightly.4. Start binding cable ties to the cable at a position 3 mm (0.12 in.) to 5 mm (0.2 in.) awayfrom one end of the PVC insulation tape.Step 5 Route the cables according to the instructions in 9.1 Cabling Requirements, and then usecable ties to bind the cables.Step 6 Label the installed cables according to the instructions in Attaching a Sign Plate Label.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.100
Step 7 Attach color-coding to the installed RF jumper according to the instructions in Attaching theColor Ring.----End9.7 Installing an RRU AISG Multi-Wire Cable and AISGExtension CableThis section describes the procedures for installing an RRU AISG multi-wire cable and AISGextension cable.ContextWhen the distance between an RRU and a Remote Control Unit (RCU) is longer than 5 m(16.4 ft.), an AISG multi-wire cable is not long enough to connect the RRU and the RCU. Inthis case, an AISG extension cable is used to extend the AISG multi-wire cable.ProcedurelInstall an AISG multi-wire cable that is not configured with an AISG extension cable.a. Use an M3 flat-head screwdriver to loosen the screws on the dustproof cap on theRET port and remove the dustproof cap.b. Link the waterproofed DB9 connector at one end the AISG multi-wire cable to theRET port on the RRU bottom, as shown in Figure 9-17.Figure 9-17 Installing an RRU AISG multi-wire cable c. Use an M3 Phillips screwdriver to tighten the posts on both sides of the waterproofDB9 connector to 0.4 N·m (3.54 lbf·in.).d. Connect the other end of the cable to the standard AISG male connector on theRCU.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.101
e. Route the cables according to the instructions in 9.1 Cabling Requirements, andthen use cable ties to bind the cables.f. Label the installed cables according to the instructions in Attaching an L-ShapedLabel.lInstall an AISG multi-wire cable that is configured with an AISG extension cable.a. Use an M3 flat-head screwdriver to loosen the screws on the dustproof cap on theRET port and remove the dustproof cap.b. Link the waterproofed DB9 connector at one end of the AISG multi-wire cable tothe RET port on the RRU bottom, and link the other end to the standard AISG maleconnector of the AISG extension cable, as shown in Figure 9-18.Figure 9-18 Installing an RRU AISG multi-wire cable c. Use an M3 Phillips screwdriver to tighten the posts on both sides of the waterproofDB9 connector to 0.4 N·m (3.54 lbf·in.).d. Connect the other end of the AISG extension cable to the standard AISG maleconnector on the RCU, as shown in Figure 9-19.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.102
Figure 9-19 Installing an RRU AISG extension cable e. Route the cables according to the instructions in 9.1 Cabling Requirements, andthen use cable ties to bind the cables.f. Label the installed cables according to the instructions in Attaching an L-ShapedLabel.----End9.8 Installing an RRU Alarm CableThis section describes the procedure for installing an RRU alarm cable.ProcedureStep 1 Use an M3 Phillips screwdriver to loosen the screws on the dustproof cap on the EXT_ALMport and remove the dustproof cap.Step 2 Connect the waterproof DB15 connector at one end of the RRU alarm cable to theEXT_ALM port on the RRU, as shown in Figure 9-20.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.103
Figure 9-20 Installing an RRU alarm cable NOTEInstall the waterproof DB15 male connector on the RRU alarm cable with caution, preventing the pinassignment from being damaged.Step 3 Use an M3 Phillips screwdriver to tighten the posts on both sides of the waterproof DB15male connector to 0.4 N·m (3.54 lbf·in.).Step 4 Connect the eight cord end terminals at the other end to external alarm devices.NOTElRemove insulated protective tubes from the cord end terminals before connecting the cord end terminalsto devices, as shown in Figure 9-21.lUse insulating adhesive tapes to wrap cord end terminals that are not in use and fix them at a properposition based on the onsite situations. This prevents false alarm reporting and equipment damage due tocontact of exposed cables. Figure 9-22 shows the method for handling cord end terminals not in use.Figure 9-21 Removing insulated protective tubes from the cord end terminalsRRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.104
 Figure 9-22 Method for handling cord end terminals that are not in use Step 5 Route the cables according to the instructions in 9.1 Cabling Requirements, and then usecable ties to bind the cables.Step 6 Label the installed cables according to the instructions in Attaching an L-Shaped Label.----End9.9 Opening the Cover Plate of an RRU Cabling CavityThis section describes the procedure for opening the cover plate of an RRU cabling cavity.ProcedureStep 1 Wear ESD gloves.NOTICETake proper ESD protection measures, for example, wear ESD gloves, to prevent electrostaticdamage to the boards, modules, or electronic components.Step 2 Use an M5 Phillips screwdriver to loosen the three screws on the cover plate of the RRUcabling cavity, and open the cover plate, as shown in Figure 9-23.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.105
Figure 9-23 Opening the cover plate of the RRU cabling cavity(1) Cover plate (2) Cabling cavity (3) Clip(4) Cable trough for the power cable (5) Waterproof block (6) Cable trough for the fiber optic cable Step 3 Loosen the screws on the clip using an M4 Phillips screwdriver, and open the clip, as shownFigure 9-24.NOTEOpen the clip only for the associated cable.Figure 9-24 Opening clipsRRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.106
 Step 4 Remove the waterproof block.NOTERemove only the waterproof blocks for the cables to be installed.----End9.10 Installing an RRU Power CableThis section describes the procedure for installing an RRU power cable.PrerequisiteslA tool-less female connector (pressfit type) is added to the RRU power cable on theRRU side. For details, see 12.1 Adding a Tool-Less Female Connector (Pressfit Type)to the RRU Power Cable on the RRU Side.lA connector or OT terminals are added to the RRU power cable on the power deviceside. For details, see the DBS3900 Installation Guide.ContextIf a power device provided by the customer is used, the recommended specification of thecircuit breaker on this power device is 15 A to 30 A.Table 9-2 describes the RRU power cable.Table 9-2 RRU power cableCable On the RRUSideOn thePowerDevice SidePowerDeviceColorRRUpowercableTool-less femaleconnector(pressfit type)Tool-lessfemaleconnector(pressfit type)EPU A cable with a black jacket andtwo wires insidelNorth American standards:The RTN(+) wire is black andthe RNEG(-) wire is blue.lEuropean standards: TheRTN(+) wire is brown and theRNEG(-) wire is blue.DCDU-11BEPC5connectorDCDU-12B RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.107
CAUTIONlBefore installing the RRU power cable, ensure that the upper-level circuit breaker isswitched off and the power cable has no voltage.lA drip loop is required for the position between the RRU port and the cable, preventingrain from damaging the RRU.lWhen installing the RRU power cable, connect the power cable to the RRU connectorfirst and then to the power equipment connector. Incorrect connection sequence orreverse connection of positive and negative poles may damage the RRU or causepersonal injury.ProcedureStep 1 Connect the tool-less female connector (pressfit type) at one end of the RRU power cable tothe power supply socket on the RRU, as shown in Figure 9-25.Figure 9-25 Installing an RRU power cable NOTICEEnsure that the exposed shield layer of the power cable is properly tightened using the clip.Step 2 Connect the connector at the other end of the RRU power cable to the corresponding positionon the power device.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.108
NOTElA DCDU-11B/DCDU-12B can supply power to a maximum of six RRUs. Ensure that the RRUpower cable is connected to one of LOAD0 to LOAD5 ports on the DCDU-11B/DCDU-12B.lOne EPU can supply power to a maximum of six RRUs. Ensure that the RRU power cable isconnected to one of RRU0 to RRU5 ports on the EPU.lWhen the RRU power cable is connected to the EPU, the blue core wire in the tool-less femaleconnector (pressfit type) is connected to the upper port on the EPU, and the black/brown core wire isconnected to the lower port on the EPU.Step 3 Route the cable according to the instructions in 9.1 Cabling Requirements, and then use acable tie to bind the cable.Step 4 Label the installed cable according to the instructions in Attaching a Cable-Tying Label.----End9.11 Installing a CPRI Fiber Optic CableThis section describes the procedure for installing a CPRI fiber optic cable.PrerequisitesBefore the installation, single-mode optical modules can be distinguished from multi-modeoptical modules in either of the following ways:lSM and MM labels on an optical module: SM indicates a single-mode optical module,and MM indicates a multi-mode optical module.lColor of the puller on an optical module: Blue indicates a single-mode optical module,and black or gray indicates a multi-mode optical module.NOTICEThe optical modules to be installed must match CPRI rates.ContextlA CPRI fiber optic cable transmits CPRI signals between a BBU and an RRU.ProcedureStep 1 Lower the pullers of two optical modules, insert one optical module into the CPRI0 port onthe RRU and the other optical module into the CPRI port on the BBU, and raise the pullers, asshown in Figure 9-26.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.109
Figure 9-26 Installing an optical moduleNOTICElThe performance of an optical module may deteriorate if it is exposed to the air for morethan 20 minutes. Therefore, insert a fiber optic cable into an unpacked optical modulewithin 20 minutes.lThe CPRI optical cables must be correctly connected in one time during the installation.Otherwise, the RRU may become faulty, causing cells to fail to provide services.Step 2 Install CPRI optical cables.NOTICElEnsuring that CPRI optical cables are correctly connected before the RRU is powered on.Otherwise, the RRU may become faulty, causing cells to fail to provide services.lTo avoid any damage to fiber optic cables, the cables connected to the RRU must beinstalled according to the installation process. For details about the installation process, see9.3 Installation Process.lWhen installing CPRI optical cables for dual-fiber bidirectional optical modules, removethe dustproof cap from the optical cable, and connect the end labeled 1A and 1B on theoptical cable to the optical module on the RRU side, as shown in Figure 9-27. Connectthe DLC end labeled 2A and 2B to the CPRI port on the main control board (such as theGTMU) or baseband processing board (such as the WBBP) in the BBU.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.110
Figure 9-27 Installing CPRI optical cables for dual-fiber bidirectional optical moduleslWhen installing CPRI optical cables for single-fiber bidirectional optical modules,remove the dustproof cap from the LC end labeled 1A on the optical cable, divide theDLC end into two LC ends, and connect the end labeled 1A to the optical module on theRRU side, as shown in Figure 9-28. Connect the other LC end labeled 2A to the CPRIport on the main control board (such as the GTMU) or baseband processing board (suchas the WBBP) in the BBU.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.111
Figure 9-28 Installing CPRI optical cables for single-fiber bidirectional optical modulesStep 3 Route the cables according to the instructions in 9.1 Cabling Requirements, and then usecable ties to bind the cables.Step 4 Label the installed cables according to the instructions in Attaching an L-Shaped Label.----End9.12 Closing the Cover Plate of an RRU Cabling CavityThis section describes the procedure for closing the cover plate of an RRU cabling cavity.ProcedureStep 1 Close the clips for the installed cables. Use an M4 torque screwdriver to tighten the screws oneach clip to 1.4 N·m (12.39 lbf·in.), as shown in Figure 9-29.NOTICEEnsure that the exposed shield layer of the power cable is properly tightened using the clip.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.112
Figure 9-29 Closing clips Step 2 Insert waterproof blocks into vacant cable troughs in the cabling cavity, as shown in Figure9-30.NOTICEEnsure that cables and waterproof blocks are properly inserted into troughs.Figure 9-30 Correct placement of waterproof blocks Step 3 Close the cover plate of the RRU cabling cavity. Use an M5 torque screwdriver to partiallytighten the screws on the cover plate in the sequence shown in Figure 9-31. Then tighten thescrews to 2 N·m (17.7 lbf·in.) in the same sequence.RRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.113
NOTICEThe RRU cabling cavity must be securely tightened to prevent water.Figure 9-31 Closing the cover plate of an RRU cabling cavity Step 4 Take off the ESD gloves, and pack up all the tools.----EndRRU3268Installation Guide 9 Installing RRU CablesIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.114
10 Checking the RRU HardwareInstallationAfter an RRU is installed, check the hardware installation.Table 10-1 provides the checklist for the RRU hardware installation.Table 10-1 Checklist for the RRU hardware installationSN Item1 The position for each device conforms to the engineering drawing and meets thespace requirement. Sufficient space is reserved for equipment maintenance.2 The RRU is securely installed.3 The cover plate is securely installed on the RRU cabling cavity.4 Waterproof blocks are securely installed in vacant cable troughs of the RRUcabling cavity, and the cover plate for the cabling cavity is securely installed. Inaddition, vacant RF ports are covered with dustproof caps and the caps aretightened.5 There are no connectors or joints on each power cable or PGND cable.6 The terminals at two ends of each power cable or PGND cable are securelysoldered or crimped.7 None of power cables and PGND cables can be short-circuited or reverselyconnected. In addition, these cables are not damaged or broken.8 Power cables and PGND cables are separately bound from other cables.9 The protection grounding of the RRU and the surge protection grounding of thebuilding share one group of ground conductors.10 The connectors of each signal cable are intact and securely linked, and thesecables are not damaged or broken.11 Labels are correct, legible, and complete at both ends of each cable, feeder, andjumper.RRU3268Installation Guide 10 Checking the RRU Hardware InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.115
SN Item12 All ground cables are properly grounded.RRU3268Installation Guide 10 Checking the RRU Hardware InstallationIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.116
11 Powering On an RRUAfter all the devices are installed, check the power-on status of an RRU.NOTICEAfter you unpack an RRU, you must power on it within 24 hours. If you power off the RRUfor maintenance, you must restore power to the RRU within 24 hours.Figure 11-1 shows the RRU power-on check process.NOTEFor details about how to power on an RRU, see Powering On an RRU. For details about how to poweroff an RRU, see section "Powering-Off the RRU" in RRU Maintenance Guide.RRU3268Installation Guide 11 Powering On an RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.117
Figure 11-1 RRU power-on check process(a) The normal input voltage of an RRU is -48 V DC. The voltage of the external power supply should rangefrom -36 V DC to -57 V DC.(b) The RUN indicator on the RRU is on for 1s and off for 1s. The ALM indicator is steady off.RRU3268Installation Guide 11 Powering On an RRUIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.118
12 AppendixAbout This ChapterThis section describes the procedure for adding an easy power receptacle (pressfit type)connector.12.1 Adding a Tool-Less Female Connector (Pressfit Type) to the RRU Power Cable on theRRU SideThis section describes the procedure for adding a tool-less female connector (pressfit type) tothe RRU power cable on the RRU side.RRU3268Installation Guide 12 AppendixIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.119
12.1 Adding a Tool-Less Female Connector (Pressfit Type)to the RRU Power Cable on the RRU SideThis section describes the procedure for adding a tool-less female connector (pressfit type) tothe RRU power cable on the RRU side.ContextFigure 12-1 shows the cable diagram on labels.Figure 12-1 Cable diagram on labels(1) Cable diagram on labels NOTICEPrepare a Tool-Less Female Connector (Pressfit Type) to the RRU Power Cable on the RRUSide by strictly following the following operations. Otherwise, damage to the RRU orpersonal injury may occur.ProcedureStep 1 Determine the length of the power cable for different operations based on the labels, as shownin Figure 12-2.RRU3268Installation Guide 12 AppendixIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.120
Figure 12-2 Determining the length of the power cable Step 2 Strip the specified length of the sheath off the power cable, as shown in Figure 12-3.Figure 12-3 Stripping the specified length of sheath Step 3 Strip a specified length of sheath off each core wire. The length must be consistent with thelength of the notch in the tool-less female connector (pressfit type), as shown in Figure 12-4.Figure 12-4 Stripping the sheath off each core wire Figure 12-5 Matched length Step 4 Add a tool-less female connector (pressfit type) to two core wires.1. Tighten the screws using a Phillips screwdriver, as shown in Figure 12-6.RRU3268Installation Guide 12 AppendixIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.121
Figure 12-6 Tightening screws 2. Connect the blue core wire labeled NEG(-) to the - port and the black/brown core wirelabeled RTN(+) to the + port on the tool-less female connector (pressfit type), and thentighten the screws using a Phillips screwdriver, and then use a torque screwdriver totighten the M4 screws to 1.4 N·m (12.39 lbf·in.), as shown in Figure 12-7.DANGERDo not reversely connect the positive and negative poles. Reverse connection of positiveand negative poles may result in equipment malfunctions or personal injury. Therefore,check the power cable connection before powering on the RRU.Figure 12-7 Adding a tool-less female connector (pressfit type) to two core wires 3. After the core wires are installed, ensure that each core wire is securely installed afterbeing dragged with a torque of 30 N•m and all copper wires are inserted in the connectorterminal socket.Step 5 Strip the specified length of the sheath off the power cable to expose the intact shield layer, asshown in Figure 12-8.RRU3268Installation Guide 12 AppendixIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.122
Figure 12-8 Stripping the sheath off the power cable NOTICEEach core wire is exposed outside the tool-less female connector (pressfit type) for 1.5 mm(0.059 [in.]), as shown in Figure 12-9.Figure 12-9 Inserting core wires into the tool-less female connector (pressfit type)----EndRRU3268Installation Guide 12 AppendixIssue 10 (2015-12-30) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.123