3300_Checklist CDX 480 3300 Gc Checklist
User Manual: CDX 480
Open the PDF directly: View PDF .
Page Count: 4
Download | |
Open PDF In Browser | View PDF |
Schindler 3300 Traction elevator installation checklist Schindler Passenger Elevators Schindler 3300 Traction elevator installation checklist Delivery of equipment Prior to elevator equipment delivery, an enclosed dry hoistway, a ready machinery space and temporary or permanent three-phase power must be available. C3 Hoistway walls – Masonry: Provide opening of +8” (203 mm) on each side and +4” (102 mm) on top of clear opening for installation of door frames and sills by Schindler. – Dry wall: Walls at entrance to be built after door sills General Contractor and frames are set in place. – Provide adequate, rollable access for delivery and – Grout entrances and sills after installation by Schindler. material unloading, and a dry place for storage of – No conduit, duct or piping allowed in the hoistway that equipment located near hoistway. is not related to the elevator equipment. – Refer to elevator layout. Please verify hoistway finished – Pit and hoistway must be dry at all times. clear width and depth, pit depth, floor-to-floor heights, – If job requires cutting and patching of walls, floors, etc., and clear overhead. and removal of such obstruction for proper installation – Build a clear, plumb, legal hoistway in accordance with of the elevator as well as pockets or blockouts for signal applicable code from top to bottom with variations not fixtures, it is to be done by General Contractor. Refer to to exceed 1” (25.4 mm) per 100’ (2540 mm). elevator layout. Seal all wall penetrations with material – Provide attachment points for elevator rail brackets. approved by code to maintain fire rating. Locate per layout. C4 – OSHA-approved barricades must be installed with kick – Provide a temporary work platform at the top floor of board at each opening. each hoistway for elevator construction; see Detail A. C5 – Attachment points for elevator rail bracket supports C1 – Vent at the top of hoistway to be located on side (inserts, steel or concrete) are needed at all floor opposite of the machine. Check local codes for levels and in the overhead at 8’-2” above top landing. ventilation requirements. Refer also to Ventilation Supports between floors may be necessary per code if Requirements. span is excessive. Coordinate locations with Schindler. C2 – Supply hoist beam for elevator construction and service – Bevel all hoistway projections and recesses in work. Beam to run across the width of the elevator accordance with applicable codes. shaft. Loads and location per elevator layout. – Divider beams are required between adjacent elevators at all floor levels and at 8’-2” above top landing. Locate per layout. C1 Pit Provide drain or sump hole in pit as required by governing local code. Cover for sump shall be level with pit floor. Drains connected directly to sewers shall not be installed in elevator pits. Location to be coordinated with Schindler. Pit must be dry at all times. C7 – Pit ladder may be supplied by Schindler if a collapsible pit ladder is necessary. C6 – C2 E4 Top Floor E1 C5 C3 E3 E2 C4 C7 Typical Floor E5 Pit C6 2 Schindler 3300 Checklist Machinery space – Temperature of machinery spaces must be maintained as follows for proper operation of equipment. – Hoistway: Between 32° F (0° C) & 110° F (43° C) – Top Landing: Between 32° F (0° C) & 104° F (40° C) – No conduit, duct or piping allowed in machinery spaces that is not related to the elevator equipment. – Provide fire extinguisher (type ABC) within sight of top landing entrance. – Provide live analog phone line. Electrical Contractor – Must immediately confirm the type of three-phase power to the elevator equipment room (208 volt, 460 volt, 480 volt, 575 volt or 600 volt) and provide before work can begin. Refer to Schindler power data sheet for approval. E1 – Provide a non-fused, enclosed, externally-operable motor circuit switch capable of being locked in the open position as a means to disconnect power from the machine in the hoistway overhead. This switch is to be in line of sight of the motor controller located on the front wall of the hoistway. E2 – Provide a fused, heavy duty, three-phase, lockable disconnect or shunt trip breaker in a machinery space accessible from outside of the hoistway with feeder branch wiring to the non-fused switch in the hoistway. Disconnect size to suit elevator contractor’s equipment requirements. All work must be per National Electric Code and ASME A17.1 and any local codes. Locate per layout. – Where transformers are necessary to provide the proper voltage to the operation controller or motor controller. Locate per layout. E3 – Provide a 110V single-phase lockable disconnect (for car lighting and fan) in the machinery space accessible from outside of the hoistway with feeder branch wiring to elevator controller. Disconnect size to suit elevator contractor’s equipment requirements. All work must be per National Electric Code, ASME A17.1 and any local codes. Locate per layout. E3 – Provide a 110V single-phase lockable disconnect (for top hoistway machinery space lighting) in the machinery space accessible from outside of the hoistway with feeder branch wiring to elevator controller. Disconnect size to suit elevator contractor’s equipment requirements. All work must be per National Electric Code, ASME A17.1 and any local codes. Locate per layout. E3 – Provide a 110V single-phase lockable disconnect (for hoistway pit lighting) in the machinery space accessible from outside of the hoistway with feeder branch wiring to elevator controller. Disconnect size to suit elevator contractor’s equipment requirements. All work must be per National Electric Code, ASME A17.1 and any local codes. Locate per layout. – If sprinklers are required, provide smoke-sensing devices at elevator lobbies and/or at top of elevator shaft, with electrical conductors terminating at elevator controller in machinery space for automatic elevator recall system in the event of a fire. – Shunt trip breaker required if sprinkler in pit, hoistway or machine room. E4 – Provide adequate lighting and receptacle in machinery spaces. Locate per layout. – Per the latest National Electrical Code, all receptacles installed in machinery spaces and pits must have Ground Fault Circuit Interrupter Protection (GFCI). E5 – Provide a light and receptacle in elevator pit. Locate per layout. Schindler Elevator Corporation – Supplies telephone in car and travel cable to car. Machine space considerations All wiring (including analog phone line) to machinery space supplied by owner. Local codes may vary. Consult with your architect/ engineer and local Schindler representative. Sound suppression The following guidelines are to be followed to reduce noise to acceptable levels: 1. The surrounding walls, floor, and ceiling assembly should have a substantial STC (Sound Transmission Class) rating. The higher the STC rating, the better. If noise-sensitive areas are nearby, STC 50 or 55 should be used as the design criteria for the surrounding structure. Concrete block walls will provide STC 42. Two layers of gypsum board on each side of 3 5/8” steel studs at standard spacing (total of four layers, two on each side) with fiberglass batt in the cavity will provide STC 56. All cracks and gaps around the perimeter must be copiously filled with the appropriate acoustical caulking. Wood studs should be avoided, but if they are used, attach drywall with resilient channel or use a staggered stud arrangement. 2. In situations where noise-sensitive areas are not an issue, two layers of drywall (four total) are still recommended and sufficient caulk around the perimeter. Double-layer drywall with staggered seams works best. 3. Penetrations into the hoistway must be kept to a minimum. When conduits pass through the walls, they must be sealed with mortar or the appropriate acoustical sealant to prevent noise leaks. A heavy, solid material must be used. Do not use fiberglass. 4. If the walls are concrete block, do not paint them. Unpainted block has about 33% absorption, which is lost with a coat of paint. Schindler 3300 Checklist 3 Schindler 3300 Traction elevator installation checklist CFM* 5.2 [FMB130-4M576-NA] 5050 258 5.2 [FMB130-4M256-NA] 5160 263 7.8 [FMB130-4M464-NA] 5120 261 7.8 [FMB130-4M192-NA] 5540 283 7.1 [FMB150-6D540-NA] 3880 198 7.1 [FMB150-6D234-NA] 4100 209 10.6 [FMB150-6D396-NA] 4330 220 10.6 [FMB150-6D162-NA] 5240 267 12” x 12” square cutout 2x8 studs as shown, spacing not to exceed 16” at any time 2’-6” 3’-0” 2’-6” 3’-0” center of car platform 2500 lb, 3000 lb and 3500 lb capacity cars 2x8 studs as shown, spacing 12” x 12” square cutout not to exceed 16” at any time center of rail * Minimum air at 70° F to be moved in and out of the machine room. 2x8 studs as shown, spacing not to exceed 16” at any time 2x8 studs as shown, spacing not to exceed 16” at any time 3’-0” 3’-6” 3’-0” 3’-6” center of car platform Notes: 1. All 2x8s to be grade 2, Douglas Fir, free of knots. 2. Platform to be covered by .75’ plywood. 3. Plywood decking to be .75’ thick CDX grade, tongue and groove. 4. Platform mounting to hold load of 1500 lb. For further information, including location of the Schindler office nearest you, please contact: Canada Headquarters. Scarborough, Ontario Tel. 416.332.8280 www.ca.schindler.com Schindler is a member organization of the U.S. Green Building Council. L1005 U.S. Headquarters. Morristown, New Jersey Tel. 973.397.6500 www.us.schindler.com © Schindler Elevator Corporation BTU/hr 2100 lb capacity car Schindler has received renewal to ISO 14001:2004 and ISO 9001:2008 certificates. Schindler prints with vegetable-based ink on paper containing post-consumer waste fiber. CMN-1203 Rated HP Detail A Temporary work platform center of rail Ventilation requirements These guidelines are to be followed to maintain acceptable elevator equipment room temperatures. 1. Temperature of machinery spaces must be maintained as follows for proper operation of equipment. – Hoistway: Between 32° F (0° C) and 110° F (43° C) – Top Landing: Between 32° F (0° C) and 104° F (40° C) 2. Minimum machinery space ventilation requirements for Schindler 3300 elevators:
Source Exif Data:
File Type : PDF File Type Extension : pdf MIME Type : application/pdf PDF Version : 1.5 Linearized : No XMP Toolkit : Adobe XMP Core 4.2.1-c043 52.372728, 2009/01/18-15:56:37 Producer : Acrobat Distiller 9.4.0 (Macintosh) Format : application/pdf Creator : nrago Title : 3300_Checklist.indd Modify Date : 2011:01:03 11:40:46-05:00 Creator Tool : Adobe InDesign CS3 (5.0.4) Create Date : 2011:01:03 11:40:25-05:00 Metadata Date : 2011:01:03 11:40:46-05:00 Document ID : uuid:b5e392c7-181d-4345-9913-4d303b52c155 Instance ID : uuid:d817a9d3-d2a6-4d9d-91c6-431df4aae19e Page Layout : TwoPageRight Page Count : 4 Author : nragoEXIF Metadata provided by EXIF.tools