IQOQ_Series4 IQOQ Series4

User Manual: IQOQ_Series4

Open the PDF directly: View PDF PDF.
Page Count: 14

DownloadIQOQ_Series4 IQOQ Series4
Open PDF In BrowserView PDF
Installation Qualification/Operational Qualification
Protocols and Instructions
AquaLab 4TE, 4TEV
4TE DUO and 4TEV DUO

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

1

Table of Contents
Section 1
Section 2
Section 2.1
Section 2.2
Section 2.3
Section 2.4
Section 2.5
Section 3
Section 3.1
Section 3.2
Section 3.2.1
Section 3.2.2
Appendix 1
Appendix 2

Introduction
Installation Qualification (IQ)
Equipment Identification
Receiving and Unpacking
Visual Inspection
Environmental Conditions
Power Up Test
Operational Qualification (OQ)
Hardware testing
System information
Sensor Verification
Equipment Familiarization
Training Record
Deficiencies and Corrective Actions

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

Pg. 3
Pg. 5
Pg. 5
Pg. 5
Pg. 7
Pg. 8
Pg. 8
Pg. 10
Pg. 10
Pg. 10
Pg. 10
Pg. 12
Pg. 13
Pg. 14

2

Section 1 – Introduction
This Qualification protocol is solely intended to be used with new or relocated AquaLab Water Activity
instruments. It is written to assist the end-user in validation of predetermined specifications.
The use of this document does not replace the need for the AquaLab Series 4 User’s Manual. Information
within the User’s Manual is required to complete this IQ/OQ Protocol. If the manual has been misplaced,
copies can be obtained from the manufacturer or downloaded from their website, www.aqualab.com.
Qualification of instrumentation is a formal process of documenting that an instrument is fit for its intended
use and that it is kept maintained and calibrated.

Responsibilities
The instrument qualification carried out onsite is the sole responsibility of the instrument owner/user.
However, Decagon Devices supports their customers in performing the qualification by providing the
instrument qualification dedicated documentation and offering a qualification service. In this regard, the
following responsibilities are defined:
Performance of Qualification
Execution of the instrument qualification and entire qualification of the installed system covered in
this document is performed by a Decagon Devices trained and authorized service personnel 		
when ordered from a customer.
Review and final qualification approval
Final approval for the qualification has to be completed after review of the qualification documentation
filled out during performance of the qualification procedures (IQ/OQ protocols). The customer representative then signs the approved form.

Installation Qualification (IQ)
Installation qualification is documented proof that the instrument was received as designed and specified by the manufacturer, that it is properly installed in the selected environment, and that this environment is suitable for the operation and use of the instrument. The IQ section therefore describes and
documents the instrument installation in the pre-determined environment. Further, the IQ verifies and
ensures that all ordered parts and documentation are in place and that all supplied items are in working
order and condition.

Operational Qualification (OQ)
The operational qualification serves as proof that the equipment operates as designed and intended,
as well as fulfills acceptance criteria defined and stated in the Operational Qualification documentation.
These criteria are defined and are based on the equipment technical specifications of the manufacturer.

Performance Qualification (PQ)
Performance qualification is documented proof that an instrument consistently performs according to the
specifications appropriate for its routine use. Monitoring of equipment during routine operation is essential
for ensuring that the ongoing performance is within specifications. The performance qualification, execution
Decagon Devices, Inc 		

June 28, 2016 11:24 AM

3

and frequency are solely under responsibility of the user. Performance validation should be designed to meet
the specifications and accuracy for a given application.

Equipment familiarization and operator training records
All equipment users are to be instructed in basic operation, functionality, instrument parameters, as well
as on basic hardware features of the installed system including routine maintenance and cleaning procedures. Please contact Decagon Devices to learn about available training and seminars.
Authorized support specialists perform the qualification services offered by Decagon Devices.

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

4

Section 2 – Installation Qualification (IQ)
Initial Qualification and Requalification
The IQ protocols described below are dedicated to initial qualification and/or to requalification. Installation Qualification tests should be performed, 1) when the system is installed, 2) when the system is
moved to a new location, 3) prior to running OQ tests.
This section describes the procedure for receiving, unpacking, and installing a Series 4 AquaLab
Water Activity instrument.
The purchased AquaLab Water Activity instrument undergoing qualification is located at:
Company Name:
Department:
Address:
City:
Country:
Zip code/Postal Code:
Phone Number:

State:

2.1 Equipment identification
Fill out this section after unpacking the AquaLab instrument and corresponding accessories.
4

4TE

4TEV

4TE DUO

4TEV DUO

Manufacturer: DECAGON DEVICES			
Model Number: 		
Serial Number:
Decagon Devices Authorized Representative
		
Name:							
Date:							
Signature:						
Initials:
				

2.2 Receiving and Unpacking

Verify that the external packaging was not damaged during shipment in a way that the internal package
content might be damaged.
External package condition
Remarks:

Satisfactory		

Not Satisfactory

N/A

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

5

													
Compare shipment list with supplied items to ensure completeness of order.						
Water Activity Instrument		

Complete

Not Complete

N/A

Quick Start Guide			

Complete

Not Complete

N/A

User’s Manual

Complete

Not Complete

N/A

AquaLink 4 Software 		

Complete

Not Complete

N/A

Certificate of Calibration		

Complete

Not Complete

N/A

Trial Verification Standards

Complete

Not Complete

N/A

SDS Documents			

Complete

Not Complete

N/A

Power Cable				

Complete

Not Complete

N/A

USB Cable				

Complete

Not Complete

N/A

Filters (TEV only)			

Complete

Not Complete

N/A

Cleaning Kit 		

Complete

Not Complete

N/A

LDPE Sample Cups and Lids		

Complete

Not Complete

N/A

DUO Quick Start Guide
(DUO only)

Complete

Not Complete

N/A

Remarks:
N/A														
															

														
All parts were received as ordered and the delivery is complete.
Yes 		
No
					
Any parts that were missing at the time of this supply verification and reported as Not Complete must be delivered to complete the shipment. Any parts marked as Not Complete must be indicated below and reviewed
with the customer. Minor parts or accessories that do not impact the installation or qualification procedure or
the functionality of the instrument can be accepted, if agreed upon by the customer in order to complete the
remainder of the IQ/OQ process. Completed can be marked once the item has been received.
Date

Initials

Item:
											
					 Accepted			
Completed
					

Accepted			

Completed

					

Accepted			

Completed

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

6

Date

Accepted			

Completed

Accepted			

Completed

Accepted			

Completed

Initials

Remarks:
N/A													
															
		
															
Qualified by:
Date:					Initials:				

2.3 Visual Inspection
After unpacking, verify that there is no physical damage to the instrument, cables, and accessories.
Note all observed damage in the Remarks section. Minor defects that do not affect functionality can be
marked as accepted, if approved by the customer.
AquaLab Instrument		

Satisfactory

Not Satisfactory

Accepted

Documentation		

Satisfactory

Not Satisfactory

Accepted

Other				

Satisfactory

Not Satisfactory

Accepted

Remarks:

N/A											

Qualified by:
Date:					Initials:				
Severe damage to any of the delivered parts interrupts the installation qualification until the part is replaced. Completion of the installation qualification after replacement is documented below.
AquaLab Instrument		

Satisfactory

Not Satisfactory

N/A

Documentation		

Satisfactory

Not Satisfactory

N/A

Other				

Satisfactory

Not Satisfactory

N/A

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

7

Remarks:
N/A			
											
																
				

Qualified by:
Date:					Initials:				

2.4 Environmental Conditions
Installation of the AquaLab Water Activity instrument includes placing the instrument on a level surface in a
location where the temperature remains fairly stable. This location should be well away from air conditioner
and heater vents, open windows, outside doors, or other items that may cause rapid
temperature fluctuation.
						
Location				 Satisfactory 		
Not Satisfactory
Adequate Power			

Satisfactory 		

Not Satisfactory

Stable Surface				

Satisfactory 		

Not Satisfactory

Temperature 			

Satisfactory 		

Not Satisfactory

Remarks:
N/A
													
																
															

Qualified by:
Date:					Initials:				

2.5 Power Up Test
After finding a good location for the AquaLab Water Activity meter, plug the power cord into the back of the
unit and a standard AC outlet. The ON/OFF switch is located in the lower left corner of the back panel.
Instrument is powered upon switching on

Yes

No

Remarks: N/A														
										

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

8

Completeness of Installation Qualification (IQ)
Installation Qualification was completed and documented according to manufacturer’s guidelines.
Initial Qualification

Requalification

Decagon Devices Authorized Representative
Name:							
Function:						
Company:						
Date:							
Signature:						
Initials:						
Installation Qualification was reviewed by the representative of the system owner.
Reviewed and approved by:
Name:							
Function:						
Company:						
Date:							
Signature:						
Initials:						
															
Remarks:
N/A
												

															

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

9

Section 3 – Operational Qualification (OQ)
This section describes tests that are to be executed for Operational Qualification of the AquaLab Water
Activity instrument in order to prove proper operation of the installed instrument.

3.1 Hardware testing						
Display is functional			

Yes			

No

Keypad is functional 			

Yes			

No

Remarks:

N/A

																
															
Qualified by:
Date:					Initials:				

3.2 System Information
AquaLab Water Activity Instrument Information
Manufacturer:						
Model Number:						
Serial Number:						
Firmware Version:						

3.2.1 Sensor Verification
The AquaLab Series 4 line of instruments contain a chilled mirror dewpoint sensor for
determining water activity. The 4TEV model contains both the chilled mirror sensor and a
capacitance relative humidity sensor. The performance of the sensors is verified by measuring
specially prepared calibration standards that have a specific molality and water activity.
Performance Verification Standards in four water activity levels are used for qualification:
0.250, 0.500, 0.760, 1.000 aw. The AquaLab dew point sensor will read each standard within
+/- 0.003 aw of the stated value. The capacitance (volatiles) sensor will read each standard
within +/- 0.015 aw of the stated value. To measure the water activity of the standards, follow
the instructions in the User’s Manual for taking a reading.

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

10

Dew Point Sensor
Standard @ 25°C
Lot #
aw ±0.003
°C
13.41m LiCl 0.250					
0.250		
8.57m LiCl 0.500					
0.500					
6.0m NaCl 0.760					
0.760				
Steam Distilled H O 1.00					
1.00
								
Water Activity Verification Standards Within Specification
Yes		

Volatiles Sensor (TEV only)
aw ±0.015

°C

2

No

Remarks:
N/A														
																
				

If verification standards are out of specification, clean the instrument and follow the procedure in the
User’s Manual to perform a linear offset. Repeat the verification process with fresh standards.
				
			
Dew Point Sensor
Volatiles Sensor (TEV only)
Standard @ 25°C Lot # 		
aw ±0.003
°C		 aw ±0.015
°C
13.41m LiCl 0.250					
0.250		
8.57m LiCl 0.500					
0.500					
6.0m NaCl 0.760					
0.760				
Steam Distilled H 0 1.00					
1.00
							
Water Activity Verification Standards Within Specification
Yes		
No		
N/A
2

Remarks:
N/A														
																
				

Qualified by:
Date:

Initials:

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

11

3.2.2 Equipment Familiarization
This section ensures that the instrument operators receive appropriate equipment training to ensure proper
operation, maintenance, and generation of results with the AquaLab instrument. Product
familiarization covers instruction on basic operations, functionality and features of the instrument, and
routine maintenance including cleaning procedures.
Equipment familiarization and training				
completed for the AquaLab.				
Yes		

No

Qualified by:
Date:					Initials:			
			

Completeness of Operational Qualification (OQ)
Operational Qualification was completed and documented according to manufacturers guidelines.
Initial Qualification				
Qualifications met Vendor Acceptance Criteria		

Requalification
Yes		

No

If any deficiencies are found, fill out the instructions for a corrective action on Pg. 14 of this document.
																
Decagon Devices Authorized Representative
Name:							
Function:						
Company:						
Date:
						
Signature:						
Initials:						
Operational Qualification was reviewed by the representative of the system owner.
Reviewed and approved by:
Name:							
Function:						
Company:						
Date:
						
Signature:						
Initials:						

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

12

Appendix 1
Training Record
This training record is for instruction in basic operation, functionality, instrument parameters, as well as on
basic hardware features of the installed system including routine maintenance and cleaning procedures.
Please contact Decagon Devices to learn about available training and seminars.
Authorized support specialists perform the qualification services offered by Decagon Devices.
Name:									Date:
Name:									Date:
Name:									Date:
Name:									Date:
Name:									Date:
Name:									Date:
Name:									Date:
Name:									Date:
Name:									Date:
Name:									Date:
Decagon Devices Authorized Representative
Name:							
Function:						
Company:						
Date:
						
Signature:						
Initials:						
Reviewed and approved by:
Name:							
Function:						
Company:						
Date:
						
Signature:						
Initials:						

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

13

Appendix 2
Deficiencies and Corrective Actions
If any deficiencies were found, they are to be followed with an instruction for Corrective Action. Once acceptable results are obtained, the deficiency is accepted by checking the “accepted” box under the deficiency.
Deficiency:										
		
																
						
Corrective Action:
		

Accepted 		

Initial			

																
																
														
Deficiency:										
		
																
				
Corrective Action:
Accepted		Initial				
									

Decagon Devices Authorized Representative
Name:							
Function:						
Company:						
Date:
						
Signature:						
Initials:						

Decagon Devices, Inc 		

June 28, 2016 11:24 AM

14



Source Exif Data:
File Type                       : PDF
File Type Extension             : pdf
MIME Type                       : application/pdf
PDF Version                     : 1.4
Linearized                      : Yes
Language                        : en-US
Tagged PDF                      : Yes
XMP Toolkit                     : Adobe XMP Core 5.6-c015 84.158975, 2016/02/13-02:40:29
Create Date                     : 2016:06:28 11:24:40-07:00
Metadata Date                   : 2016:06:28 11:24:56-07:00
Modify Date                     : 2016:06:28 11:24:56-07:00
Creator Tool                    : Adobe InDesign CC 2015 (Macintosh)
Instance ID                     : uuid:8adfe1f6-f0c2-0a40-8e10-e506c46f14bc
Original Document ID            : xmp.did:f77c2ca3-ef84-439e-a997-ed9f00f38595
Document ID                     : xmp.id:bc15b5ea-1dd6-499b-a82c-94860026242f
Rendition Class                 : proof:pdf
Derived From Instance ID        : xmp.iid:1e16c421-f045-4521-bcd2-39303db12279
Derived From Document ID        : xmp.did:a961d82f-4ea2-4085-bf93-b38af571b1ee
Derived From Original Document ID: xmp.did:f77c2ca3-ef84-439e-a997-ed9f00f38595
Derived From Rendition Class    : default
History Action                  : converted
History Parameters              : from application/x-indesign to application/pdf
History Software Agent          : Adobe InDesign CC 2015 (Macintosh)
History Changed                 : /
History When                    : 2016:06:28 11:24:40-07:00
Format                          : application/pdf
Producer                        : Adobe PDF Library 15.0
Trapped                         : False
Page Count                      : 14
Creator                         : Adobe InDesign CC 2015 (Macintosh)
EXIF Metadata provided by EXIF.tools

Navigation menu