IQOQ_Series4 IQOQ Series4
User Manual: IQOQ_Series4
Open the PDF directly: View PDF 
.
Page Count: 14

Installation Qualification/Operational Qualification
Protocols and Instructions
AquaLab 4TE, 4TEV
4TE DUO and 4TEV DUO
Decagon Devices, Inc     June 28, 2016 11:24 AM  1
Table of Contents
2
Introduction
Installation Qualification (IQ)
Equipment Identification
Receiving and Unpacking 
Visual Inspection
Environmental Conditions
Power Up Test
Operational Qualification (OQ)
Hardware testing
System information
Sensor Verification 
Equipment Familiarization
Training Record
Deficiencies and Corrective Actions
Section 1
Section 2
Section 2.1
Section 2.2
Section 2.3
Section 2.4
Section 2.5
Section 3
Section 3.1 
Section 3.2 
Section 3.2.1
Section 3.2.2
Appendix 1
Appendix 2
Decagon Devices, Inc     June 28, 2016 11:24 AM 
Pg. 3
Pg. 5
Pg. 5
Pg. 5
Pg. 7
Pg. 8
Pg. 8
Pg. 10
Pg. 10
Pg. 10
Pg. 10
Pg. 12
Pg. 13
Pg. 14
Section 1 – Introduction
This Qualification protocol is solely intended to be used with new or relocated AquaLab Water Activity 
instruments. It is written to assist the end-user in validation of predetermined specifications. 
The use of this document does not replace the need for the AquaLab Series 4 User’s Manual.  Information 
within the User’s Manual is required to complete this IQ/OQ Protocol.  If the manual has been misplaced, 
copies can be obtained from the manufacturer or downloaded from their website, www.aqualab.com.
Qualification of instrumentation is a formal process of documenting that an instrument is fit for its intended 
use and that it is kept maintained and calibrated.  
Responsibilities 
The instrument qualification carried out onsite is the sole responsibility of the instrument owner/user.  
However, Decagon Devices supports their customers in performing the qualification by providing the 
instrument qualification dedicated documentation and offering a qualification service. In this regard, the 
following responsibilities are defined:
  Performance of Qualification
  Execution of the instrument qualification and entire qualification of the installed system covered in     
          this document is performed by a Decagon Devices trained and authorized service personnel    
  when ordered from a customer.
  Review and final qualification approval
 Final approval for the qualification has to be completed after review of the qualification documentation 
filled out during performance of the qualification procedures (IQ/OQ protocols). The customer repre-
sentative then signs the approved form.  
Installation Qualification (IQ)
Installation qualification is documented proof that the instrument was received as designed and speci-
fied by the manufacturer, that it is properly installed in the selected environment, and that this environ-
ment is suitable for the operation and use of the instrument.  The IQ section therefore describes and 
documents the instrument installation in the pre-determined environment.  Further, the IQ verifies and 
ensures that all ordered parts and documentation are in place and that all supplied items are in working 
order and condition.  
Operational Qualification (OQ)
The operational qualification serves as proof that the equipment operates as designed and intended, 
as well as fulfills acceptance criteria defined and stated in the Operational Qualification documentation.  
These criteria are defined and are based on the equipment technical specifications of the manufacturer.  
Performance Qualification (PQ)
Performance qualification is documented proof that an instrument consistently performs according to the 
specifications appropriate for its routine use.  Monitoring of equipment during routine operation is essential 
for ensuring that the ongoing performance is within specifications.  The performance qualification, execution 
Decagon Devices, Inc     June 28, 2016 11:24 AM  3
and frequency are solely under responsibility of the user. Performance validation should be designed to meet 
the specifications and accuracy for a given application.  
Equipment familiarization and operator training records
All equipment users are to be instructed in basic operation, functionality, instrument parameters, as well 
as on basic hardware features of the installed system including routine maintenance and cleaning proce-
dures. Please contact Decagon Devices to learn about available training and seminars.  
Authorized support specialists perform the qualification services offered by Decagon Devices.  
Decagon Devices, Inc     June 28, 2016 11:24 AM  4

Decagon Devices, Inc     June 28, 2016 11:24 AM  5
Section 2 – Installation Qualification (IQ)
Initial Qualification and Requalification
The IQ protocols described below are dedicated to initial qualification and/or to requalification.  Instal-
lation Qualification tests should be performed, 1) when the system is installed, 2) when the system is 
moved to a new location, 3) prior to running OQ tests.
This section describes the procedure for receiving, unpacking, and installing a Series 4 AquaLab 
Water Activity instrument.  
The purchased AquaLab Water Activity instrument undergoing qualification is located at:
Company Name:
Department:
Address:
City:                                                                    State:
Country:
Zip code/Postal Code:
Phone Number:
2.1 Equipment identification
Fill out this section after unpacking the AquaLab instrument and corresponding accessories.  
     4                 4TE               4TEV            4TE DUO      4TEV DUO
Manufacturer:  DECAGON DEVICES     
Model Number:     
Serial Number: 
Decagon Devices Authorized Representative
Name:       
Date:       
Signature:      
Initials: 
2.2 Receiving and Unpacking
Verify that the external packaging was not damaged during shipment in a way that the internal package 
content might be damaged.  
External package condition      Satisfactory    Not Satisfactory
Remarks:     N/A 

Compare shipment list with supplied items to ensure completeness of order.          
Water Activity Instrument     Complete        Not Complete         N/A
Quick Start Guide       Complete        Not Complete          N/A
User’s Manual                          Complete        Not Complete          N/A
AquaLink 4 Software      Complete        Not Complete          N/A
Certificate of Calibration     Complete        Not Complete          N/A
Trial Verification Standards      Complete        Not Complete          N/A
SDS Documents       Complete        Not Complete          N/A
Power Cable      Complete        Not Complete          N/A
USB Cable      Complete        Not Complete          N/A
Filters (TEV only)       Complete        Not Complete          N/A
Cleaning Kit                     Complete        Not Complete          N/A
LDPE Sample Cups and Lids    Complete        Not Complete          N/A
DUO Quick Start Guide                Complete        Not Complete          N/A
(DUO only)
Remarks:     N/A              
All parts were received as ordered and the delivery is complete.   Yes     No
Any parts that were missing at the time of this supply verification and reported as Not Complete must be de-
livered to complete the shipment.  Any parts marked as Not Complete must be indicated below and reviewed 
with the customer.  Minor parts or accessories that do not impact the installation or qualification procedure or 
the functionality of the instrument can be accepted, if agreed upon by the customer in order to complete the 
remainder of the IQ/OQ process.  Completed can be marked once the item has been received.
Item:                                                                
       Accepted       Completed
       Accepted       Completed
       Accepted       Completed
Decagon Devices, Inc     June 28, 2016 11:24 AM  6
InitialsDate

Remarks:     N/A             
Qualified by:
Date:     Initials:    
2.3 Visual Inspection
After unpacking, verify that there is no physical damage to the instrument, cables, and accessories. 
Note all observed damage in the Remarks section. Minor defects that do not affect functionality can be 
marked as accepted, if approved by the customer.  
AquaLab Instrument    Satisfactory               Not Satisfactory         Accepted
Documentation    Satisfactory           Not Satisfactory               Accepted
Other      Satisfactory          Not Satisfactory          Accepted
Remarks:     N/A           
Qualified by:
Date:     Initials:    
Severe damage to any of the delivered parts interrupts the installation qualification until the part is re-
placed.  Completion of the installation qualification after replacement is documented below.  
AquaLab Instrument    Satisfactory          Not Satisfactory         N/A  
Documentation    Satisfactory          Not Satisfactory          N/A
Other      Satisfactory          Not Satisfactory          N/A
Decagon Devices, Inc     June 28, 2016 11:24 AM  7
 Accepted       Completed
 Accepted       Completed
 Accepted       Completed
Date Initials

Decagon Devices, Inc     June 28, 2016 11:24 AM  8
Remarks:     N/A                 
Qualified by:
Date:     Initials:    
2.4 Environmental Conditions
Installation of the AquaLab Water Activity instrument includes placing the instrument on a level surface in a 
location where the temperature remains fairly stable.  This location should be well away from air conditioner 
and heater vents, open windows, outside doors, or other items that may cause rapid 
temperature fluctuation.  
Location      Satisfactory      Not Satisfactory
Adequate Power       Satisfactory      Not Satisfactory
Stable Surface      Satisfactory      Not Satisfactory
Temperature          Satisfactory      Not Satisfactory
Remarks:    N/A               
Qualified by:
Date:     Initials:    
2.5 Power Up Test
After finding a good location for the AquaLab Water Activity meter, plug the power cord into the back of the 
unit and a standard AC outlet. The ON/OFF switch is located in the lower left corner of the back panel.  
Instrument is powered upon switching on      Yes   No  
Remarks:   N/A              

Completeness of Installation Qualification (IQ)
Installation Qualification was completed and documented according to manufacturer’s guidelines.  
   Initial Qualification   Requalification
Decagon Devices Authorized Representative
Name:       
Function:      
Company:      
Date:       
Signature:      
Initials:      
Installation Qualification was reviewed by the representative of the system owner.  
Reviewed and approved by:
Name:       
Function:      
Company:      
Date:       
Signature:      
Initials:      
Remarks:    N/A              
Decagon Devices, Inc     June 28, 2016 11:24 AM  9

Decagon Devices, Inc     June 28, 2016 11:24 AM  10
Section 3 – Operational Qualification (OQ)
This section describes tests that are to be executed for Operational Qualification of the AquaLab Water 
Activity instrument in order to prove proper operation of the installed instrument.
3.1 Hardware testing      
Display is functional       Yes       No
Keypad is functional       Yes       No
Remarks:    N/A
Qualified by:
Date:     Initials:    
3.2 System Information
AquaLab Water Activity Instrument Information
Manufacturer:      
Model Number:      
Serial Number:      
Firmware Version:      
3.2.1 Sensor Verification
The AquaLab Series 4 line of instruments contain a chilled mirror dewpoint sensor for
determining water activity. The 4TEV model contains both the chilled mirror sensor and a
capacitance relative humidity sensor. The performance of the sensors is verified by measuring
specially prepared calibration standards that have a specific molality and water activity.
Performance Verification Standards in four water activity levels are used for qualification:
0.250, 0.500, 0.760, 1.000 aw. The AquaLab dew point sensor will read each standard within
+/- 0.003 aw of the stated value. The capacitance (volatiles) sensor will read each standard
within +/- 0.015 aw of the stated value. To measure the water activity of the standards, follow
the instructions in the User’s Manual for taking a reading. 

                                                                        Dew Point Sensor           Volatiles Sensor (TEV only)                     
Standard @ 25°C   Lot #                    aw ±0.003                   °C                       aw ±0.015                 °C
 13.41m LiCl   0.250     
            0.250   
 8.57m LiCl    0.500     
            0.500         
 6.0m NaCl   0.760         
            0.760    
Steam Distilled H2O 1.00     
            1.00 
Water Activity Verification Standards Within Specification    Yes     No
Remarks:    N/A              
If verification standards are out of specification, clean the instrument and follow the procedure in the 
User’s Manual to perform a linear offset.  Repeat the verification process with fresh standards.  
                      Dew Point Sensor       Volatiles Sensor (TEV only) 
   Standard @ 25°C   Lot #          aw ±0.003            °C    aw ±0.015          °C
 13.41m LiCl   0.250     
            0.250   
 8.57m LiCl    0.500     
            0.500         
 6.0m NaCl   0.760         
            0.760    
Steam Distilled H20  1.00     
            1.00 
Water Activity Verification Standards Within Specification    Yes     No     N/A
Remarks:    N/A              
Qualified by:
Date:                                              Initials: 
Decagon Devices, Inc     June 28, 2016 11:24 AM  11

3.2.2 Equipment Familiarization
This section ensures that the instrument operators receive appropriate equipment training to ensure proper 
operation, maintenance, and generation of results with the AquaLab instrument. Product 
familiarization covers instruction on basic operations, functionality and features of the instrument, and 
routine maintenance including cleaning procedures.
Equipment familiarization and training       
completed for the AquaLab.         Yes     No
Qualified by: 
Date:     Initials:   
Completeness of Operational Qualification (OQ)
Operational Qualification was completed and documented according to manufacturers guidelines.  
   Initial Qualification         Requalification
Qualifications met Vendor Acceptance Criteria     Yes     No 
If any deficiencies are found, fill out the instructions for a corrective action on Pg. 14 of this document.
Decagon Devices Authorized Representative
Name:       
Function:      
Company:      
Date: 
Signature:      
Initials:      
Operational Qualification was reviewed by the representative of the system owner.  
Reviewed and approved by:
Name:       
Function:      
Company:      
Date: 
Signature:      
Initials:      
Decagon Devices, Inc     June 28, 2016 11:24 AM  12

Appendix 1
Training Record
This training record is for instruction in basic operation, functionality, instrument parameters, as well as on 
basic hardware features of the installed system including routine maintenance and cleaning procedures. 
Please contact Decagon Devices to learn about available training and seminars.  
Authorized support specialists perform the qualification services offered by Decagon Devices.  
Name:         Date:
Name:         Date:
Name:         Date:
Name:         Date:
Name:         Date:
Name:         Date:
Name:         Date:
Name:         Date:
Name:         Date:
Name:         Date:
Decagon Devices Authorized Representative
Name:       
Function:      
Company:      
Date: 
Signature:      
Initials:      
Reviewed and approved by:
Name:       
Function:      
Company:      
Date: 
Signature:      
Initials:      
Decagon Devices, Inc     June 28, 2016 11:24 AM  13

Appendix 2
Deficiencies and Corrective Actions
If any deficiencies were found, they are to be followed with an instruction for Corrective Action. Once accept-
able results are obtained, the deficiency is accepted by checking the “accepted” box under the deficiency.
Deficiency:          
Corrective Action:      Accepted     Initial     
Deficiency:          
Corrective Action:     Accepted  Initial    
Decagon Devices Authorized Representative
Name:       
Function:      
Company:      
Date: 
Signature:      
Initials:      
Decagon Devices, Inc     June 28, 2016 11:24 AM  14