Huawei Technologies RRU3203 Distributed Base Station Remote Radio Unit User Manual Installation Guide

Huawei Technologies Co.,Ltd Distributed Base Station Remote Radio Unit Installation Guide

Installation Guide

HUAWEI TECHNOLOGIES CO., LTD.
RRU3203 V100R001C01
Installation Guide
Issue: 01
Date: 2010-04-13
1
Installation Tools ……………………………………
Space Requirements …………………………………
Installation Modes ……………………………………
Installation Procedure ………………………………
Components Delivered with the RRU ……………
Installing the RRU on a Metal Pole ………………..
Installing the RRU on a U-Steel ……………………
Installing the RRU on an Angle Steel ……………
Installing the RRU on Wall …………………………
Installing the RRU Cables …………………………
RRU Hardware Installation Checklist ……………
Powering On the RRU ………………………………
Appendix………………………………………………
Change History …………………………………...…
Contents
Copyright © Huawei Technologies Co., Ltd. 2010. All rights reserved.
2
3
4
6
6
7
11
11
12
14
20
20
21
26
2
Multimeter
Knife
Hammer drill (with bit 14) Vacuum cleaner
Claw hammer
ESD gloves
Heat gun
Flat-head screwdriver
(M3~M6)
Wire stripper
Wire cutter
Power cable crimping pliers
Adjustable wrench
(with the diameter of at least 32 mm [1.3 in.])
Torque screwdriver
Measuring tape
Level
Marking pen
(with the diameter of no more
than 10 mm [0.4 in.])
Combination wrench
(21mm~21mm) for pole installation
(17mm~17mm) for wall installation
Phillips screwdriver
(M3~M6)
Torque wrench
Torque socket
Installation Tools
3
60 mm [2.4 in.] to 114 mm [4.5 in.]
63mm
80mm
63 mm [2.5 in.] to 75 mm [3 in.]
10°
RRU
Angle steel
or U-steel
On a metal pole On a wall
On an angle steel
On a U-steel
Installation Options
The following figure describes the specifications for the metal pole, angle steel, and U-steel where the RRU is
installed.
Metal pole Angle steel U-steel
The brackets cannot be
combined when the RRUs
are installed on the wall.
zA maximum of two RRUs can be installed on a metal pole with a diameter of 60 mm [2.4 in.] to 75 mm [3 in.] ,
and the installation mode must be standard mode. Three or more RRUs must be installed on a metal pole with
a diameter of 76 mm [3 in.] to 114 mm [4.5 in.] in a centralized way.
zIt is recommended that only one RRU be installed on a U-steel or an angle steel.
zWhen installed on a tower, one RRU can be installed only in standard mode or reverse mode rather than
side-mounted. Two RRUs cannot be installed in back-to-back mode.
The angle between
the vertical and the
angle steel or U-
steel or angle steel
where the RRU is
installed must be
less than or equal
to 10 degree.
63 mm [2.5 in.] to 75 mm [3 in.] 50 mm [2 in.] to 100 mm [3.9 in.]
30 mm [1.2 in.] to 50 mm [2.0 in.]
4
Dimensions and Installation Clearance
300 mm [11.8 in.]
500 mm [19.7 in.]
800 mm [31.5 in.]
600 mm [23.6 in.]
300 mm [11.8 in.]
a
381 mm [15.0 in.] 170 mm [6.7 in.]
485 mm [19.1 in.]
Dimensions of the RRU
bRecommended Clearance for a
Single RRU
dRecommended Clearance for
Multiple Centralized RRUs eMinimum Clearance for Multiple
Centralized RRUs
cMinimum Clearance for a Single
RRU
200 mm [7.9 in.]
300 mm [11.8 in.]
400 mm [15.7 in.]
100 mm [3.9 in.]
600 mm [23.6 in.]
800 mm [31.5 in.]
500 mm [19.7 in.]
300 mm [11.8 in.]
500 mm [19.7 in.]
500 mm [19.7 in.]
300 mm [11.8 in.]
300 mm [11.8 in.]
200 mm [7.9 in.]
300 mm [11.8 in.]
600 mm [23.6 in.]
5
Dimensions and Installation Clearance
f g
Recommended Horizontal Spacing for
Two RRUs Installed in Parallel Minimum Horizontal Spacing for Two
RRUs Installed in Parallel
hi
Recommended Vertical Spacing for
Two RRUs Installed in Parallel Minimum Vertical Spacing for Two
RRUs Installed in Parallel
300 mm [11.8 in.]
500 mm [19.7 in.]
500 mm [19.7 in.]
200 mm [7.9 in.]
300 mm [11.8 in.]
300 mm [11.8 in.]
300 mm
[11.8 in.]
600 mm
[23.6 in.]
600 mm
[23.6 in.] 100 mm
[3.9 in.] 400 mm
[15.7 in.] 400 mm
[15.7 in.]
6
Dual-nut bolt
Main bracket
Auxiliary bracket
Cover plate Attachment plate
Installation Procedure
Preparing the Installation
Main and auxiliary brackets for the RRU Front Back
Prepare the
installation
Start
Install the RRU on a
metal pole Install the RRU on a
U-steel Install the RRU on an
angle steel Install the RRU on a
wall
Install the RRU
cables
Power on the RRU
End
Checking the RRU
Hardware Installation
7
1200 mm [47.2 in.]
1600 mm [63 in.]
40 N•m
[354 lbf•in.]
When installing the
main bracket,
ensure that the
contact piece on
the bracket is fixed.
You may fit one end of the auxiliary bracket on one dual-nut bolt assembly and then the other end on the
other dual-nut bolt assembly during the installation.
Fasten the two dual-nut bolt assemblies
alternatively. After the brackets are secure,
use a tape to measure the spacing between
the main bracket and the auxiliary bracket at
the two sides and ensure that the spacing is
the same.
zThe weight-bearing capacity of the RF
ports at the bottom of the RRU is low. Do
not place the RRU at its bottom.
zDuring the operation, place the foam
pad or cardboard under the RRU to
prevent any damage to the housing of
the RRU.
2. Use an adjustable wrench to tighten the nut until the fastening torque is 40 N·m [354
lbf•in.]. In this way, the main and auxiliary brackets are secured on the pole.
1. Install the main bracket.
Installing the RRU on a Metal Pole
aInstalling a Single RRU on a Metal Pole
3. Install the RRU on the main bracket. When you hear click sound, you can infer that
the RRU is in position.
8
Cabling cavity
In standard mode
In reverse mode
Installing the RRU on a Metal Pole
Installing Two RRUs Back-To-Back on a Metal Pole
b
4. Install the second RRU on the main bracket.
3. Reinstall the attachment plate and cover plate on the second RRU by interchanging
their positions.
1. Install an RRU. For details, see page 7
Installing a Single RRU on a Metal Pole.2. Install the main fixture for another RRU.
Ensure that the cabling
cavities of the two RRUs
face the same direction
when installing the RRUs.
M6X16
4.8 N•m
[42.5 lbf•in.]
9
Installing the RRU on a Metal Pole
Installing Multiple RRUs in Centralized Mode
c
2. Relocate the attachment plate.
1. Install the main fixture and the auxiliary fixture. For details, see page 7
Installing a Single RRU in Ordinary Mode.
4. Install the second main fixture.3. Fit the tabs on the attachment plate of the
RRU into the anchor slots on the main fixture.
5. Fit the tabs on the attachment plate of
the second RRU into the anchor slots on
the second main fixture.
6. Install the third RRU.
M6X16
4.8 N•m
[42.5 lbf•in.]
10
7. Install the fourth main fixture. 8. Fit the tabs on the attachment plate of
the fourth RRU into the anchor slots on
the fourth main fixture.
Installing the RRU on a Metal Pole
Installing Multiple RRUs in Centralized Mode
c
9. Four RRUs installed in centralized mode. 10. Six RRUs installed in centralized mode.
11
U-steel
Installing the RRU on a U-Steel
Plan view
Plan view
Angle steel
zThe procedure for installing the RRU on a U-steel is the same as that for installing the RRU on a metal pole.
zIt is recommended that only one RRU be installed on a U-steel.
zThe procedure for installing the RRU on an angle steel is the same as that for installing the RRU on a metal
pole.
zIt is recommended that only one RRU be installed on an angle steel.
Installing the RRU on an Angle Steel
12
1200 mm [47.2 in.]
to 1600 mm [63.0 in.]
650 mm
[25.6 in.] 128 mm
[5 in.]
RRU
Level
Ø14
After the expansion bolt is removed,
dispose of the plastic tube.
90°
Installing the RRU on a Wall
1. Place the auxiliary bracket at the installation position. Use a level to check that the
auxiliary bracket is placed horizontally. Then, mark the anchor points by using a
marking pen.
zIt is recommended that the auxiliary bracket be 1,200 mm [47.2 in.] to 1,600 mm [63.0 in.] above the ground.
zThe RRUs cannot installed on a wall in centralized mode. Therefore, expansion bolt assemblies should be
prepared for each RRU.
2. Drill holes at the anchor points and then install the expansion bolt assemblies.
When the RRU is installed on a wall, the requirements are as follows:
zFor one RRU, the wall has a weight-bearing capacity of 96 kg [211.7 lb].
zThe fastening torque of the expansion bolt reaches 30 N•m [265.5 lbf•in.] the expansion bolt works properly,
and no damages such as cracks are on the wall.
M10x65 bolt
Spring washer 10
Plastic tube
Flat washer 10
Expansion tube
Do not hammer the bolt entirely into the
wall. Instead, leave 20 mm to 30 mm of
the bolt outside the wall.
650 mm
[25.6 in.]
126.5 mm
[5 in.] 126.5 mm
[5 in.]
20 mm [0.8 in.]
to 30mm [1.2 in.]
55 mm [2.2 in.]
to 60mm [2.4 in.]
13
Arrows are upwards
30 N•m
[265.5 lbf•in.]
M10
Installing the RRU on a Wall
3. Fit the auxiliary bracket on the expansion
bolts downward, and then tighten the bolts by
using a combination wrench 17 mm [0.7 in.].
4. Install the main bracket.
5. Install the RRU.
14
Installing the RRU on a Wall
6. Install multiple RRUs.
70 mm
[2.8 in.]
855 mm
[33.7 in.]
Minimum Clearance:
Recommended Clearance :
Installing the RRU Cables
RRU Cable Connections
a
Standard AISG female connector of the AISG multi-wire cableStandard AISG male connector
Standard AISG male connector of the AISG extension cable or
RCU
Standard AISG female connector
Port labeled RET/MON on the RRUWaterproof DB9 connectorAISG multi-wire cable
between the RRU and the
RCU
The connectors labeled 2A and 2B are connected to port labeled
CPRI0 to CPRI5 on the LBBP board of the BBU.
DLC connector
CPRI optical cable The connectors labeled 1A and 1B are connected to the optical
module on the port labeled CPRI_W on the RRU
DLC connector
AISG extended cable
between the RRU and the
RCU Standard AISG male connector of the RCUStandard AISG female connector
The blue OT terminal is connected to socket labeled NEG(-)0 in the
RRU cabling cavity. And the black OT terminal is connected to
socket labeled RTN(+)0.
Two OT terminals
(M4
DC RRU power cable
(North American standard:
3.3 mm2
European standard:
4 mm2 )
External power supplyBare wire
Feeder or antennaDIN male connector
Ports labeled ANT_TX/RXA and ANT_TX/RXB on the RRU
(Only the ANT_TX/RXA port supports the OOK signal).
DIN male connectorRRU RF jumper
Nearest grounding barOT terminal
Grounding bolt on the RRUOT terminal (M6)PGND cable
(16 mm2)
Connector toConnector TypeCable
Cable List
855 mm
[33.7 in.]
655 mm
[25.8 in.]
655 mm
[25.8 in.]
70 mm
[2.8 in.]
15
Installing the RRU Cables
RCU
zWhen the length of the AISG multi-wire cable
between the RRU and the RCU is not enough, you
can choose the optional AISG extended cable
between the RRU and the RCU.
zIf the coaxial cable is used for the RET antenna
when the STMA or Smart Bias-Tee (SBT) is used,
the OOK signals are required. Therefore, the port for
the RET antenna needs to use the ANT_TX/RXA
port.
PGND cable
RRU RF jumper
DC RRU power
cable
CPRI optical cable
AISG multi-wire cable between
the RRU and the RCU
AISG extended cable between
the RRU and the RCU
Antenna
BBU
Single RRU
RRU Cable Connections
a
External power
system
Multiple RRUs
External power
system
Antenna
Antenna
Antenna
For detail information of the cable, see Cable List on Page 14.
PGND cable
RRU RF jumper
DC RRU power
cable
CPRI optical cable
AISG multi-wire cable
between the RRU and
the RCU
AISG extended cable
between the RRU and
the RCU
Install PGND cable
Start
Install RRU RF
jumper
Install feeder
(optional)
Install DC RRU
power cable
Install CPRI optical cable
Install AISG multi-wire
cable between the RRU
and the RCU (optional)
Install AISG extended
cable between the RRU
and the RCU (optional)
End
16
Installing the RRU Cables
b c Cabling Cavity of the RRU
Opening the Cover Plate
of the RRU Cabling Cavity
Waterproofing filler
Cable troughs for
optical cables
Cable troughs for
power cables
Cabling cavity
Cover plate of the
cabling cavity
Label for preparing
the power cable cable clip
Cable troughs for
power cables
dCable Connections on the RRU
zBefore connecting a power cable,
ensure that other end of the power cable
not connected to any power supply.
zUse the DC RRU power cable clip to
press the shielding layer tightly and
ensure that the lower part of the
shielding layer does not exceed the
position shown in the preceding figure.
zGround the shielding layer at the
other end of the power cable.
zDo not remove the dustproof cap from
the idle antenna port, and use the
waterproof tape to wrap the joint.
zFor details on how to add OT
terminals to the DC RRU power cable of
the RRU, see page 22 " Adding OT
Terminals by Using a Wire Stripper."
zWhen wrapping the waterproof tape,
apply even force to extend the tape until
the width of the tape is 1/2 of the
original width.
zWrap the joint spirally upward,
downward, and then upward again. In
other words, the joint is wrapped by
three layers of the tape. Ensure that the
two immediate layers overlap with each
other about half the width of the tape.
For details, see page 24 “Waterproofing
Outdoor Cables.”
zInstall the optical module before
installing the optical cables. For details,
see page 25 “Installing the Optical
Module.”
After the cables
are installed on
the RRU, insert
the waterproofing
fillers into the idle
cable troughs.
CPRI optical cable RRU RF
jumper
DC RRU
power cable
Shielding
layer of the
power cable
First wrap the joint
with the waterproof
tape, and then
wrap the joint with
the PVC insulating
tape.
M4
17
Installing the RRU Cables
eClosing the Cover Plate of the RRU Cabling Cavity
zThe screws on the cover plate should
be tightened until the fastening torque is
1.4 N·m [12.4 lbf•in.].
zTighten the screws on the cover plate
of the cabling cavity in the sequence
shown in the figure.
fRRU+APM30H
RRU1
DC RRU power cable
CPRI optical cable
a
b
DC RRU
power
cable
zThe DC RRU power cable is connected to one of the RRU0 to RRU5 terminals of the PDU.
zStrip the jacket of the DC RRU power cable for a small part, press the exposed shielding layer in the power
cable clip, and then connect the PGND cable on the clip to the nearest grounding bolt on the side of the cabinet.
M4
1.4 N•m
[12.4 lbf•in.]
Metal Shielding layer
(25 mm [1 in.]) PGND cable
Grounding the shielding layer
of the power cable:
18
h
Installing the RRU Cables
gRRU+BBU Installed Against the Wall
DCDU panel facing
the side, and the
BBU panel facing
downward
LOAD6
LOAD0
zThe DC RRU power cable is connected to one group of the LOAD0 to LOAD5 terminals of the DCDU-03B.
zWhen the BBU and RRU are installed indoors, the DC RRU power cables need not to be grounded.
RRU+19-Inch Cabinet
zAt the end of the DC RRU power cable connected to the DCDU-03B, you need to make the shielding
layer of the power cable into an OT terminal, and then connect the OT terminal to the PGND terminal of the
corresponding port on the DCDU-03B. For details about making an OT terminal, see pages 22 and 23.
zThe DC RRU power cable is connected to LOAD0 to LOAD5 on the DCDU-03B.
DC RRU power cable
CPRI optical cable
LOAD0
DC RRU power cable
CPRI optical cable
BBU power cable
PGND cable
19
Installing the RRU Cables
iRRU+TMC/TMC11H
DC RRU power cable
CPRI optical cable
a
b
LOAD0
zAt the end of the DC RRU power cable connected to the DCDU-03B, you need to make the shielding layer
of the power cable into an OT terminal, and then connect the OT terminal to the PGND terminal of the
corresponding port on the DCDU-03B. For details about making an OT terminal, see pages 22 and 23.
zThe DC RRU power cable is connected to LOAD0 to LOAD5 on the DCDU-03B.
Metal Shielding layer
(25 mm [1 in.]) PGND cable
Grounding the shielding layer
of the power cable:
DC RRU
power
cable
20
a
b
Start
Check
whether the input
voltage of the RRU is
normal?
End
Power on the RRU
Check
whether the status of
the LEDs on the RRU
is normal?
Rectify the fault
Rectify the fault
Yes
No
aNormal input voltage of the
RRU:
If the BBU is supplied with
-48 V DC power, the
external input power
voltage ranges from -57 V
DC to -36 V DC.
Normal status of the
LEDs on the RRU:
RUN LED: ON for 1s
and OFF for 1s
ALM LED: OFF
b
Yes
No
RRU Hardware Installation Checklist
Powering on the RRU
When the RRU is unpacked, it must
be powered on within 24 hours.
There are no connectors or joints on the power cable or PGND cable.5
The connector of the signal cable is intact, and no damaged or broken parts exist on the cable.10
Labels are correct, legible, and complete on both ends of each cable.11
The power cable, PGND cable, feeder, optical cable and the E1/T1/FE signal cable are bound separately with a
spacing of larger than 30 mm [1.2 in.] .
9
All the power cables and PGND cables are not short-circuited or reversely connected. In addition, no damaged or
broken parts exist.
8
The flat washer and the spring washer are well mounted on all OT terminals.7
The terminals at both ends of the power cable or PGND cable are securely soldered or crimped.6
Waterproof fillers are installed in the idle cable troughs of the cabling cavity of the RRU, and the cover plate of the
cabling cavity is securely installed. In addition, the idle RF ports are covered with waterproof caps and waterproofed.
4
The cover plate is securely installed on the cabling cavity of the RRU.3
The RRU and the installation parts are securely installed.2
All self-made PGND cables are copper-based with the proper wire diameters. No breaking device such as switch and
fuse is allowed for the electric connection of the grounding system. No short circuit is allowed. Each terminal on the
grounding bar can be connected with only one wiring terminal of the PGND cable.
1
ItemsNo.
21
A
B C
Lifting rope
Lower part of the
adapting piece
Steering rope
aBinding the RRU and Installation Components
1. Bind the RRU by leading the lifting rope along the lower part of the adapting piece and
through the handle, bind the main and auxiliary brackets with the lifting rope, and then
bind the steering rope with the handle of the RRU, as shown in the following figures.
2. Lift the RRU and installation components to the tower.
Do not bind the lifting rope
only on the handle when
lifting the RRU.
zWhen lifting the RRU and installation components to the tower,
prevent the RRU from colliding with the tower.
zLift the RRU to the tower before it is installed on the metal pole,
angle steel, or U-steel.
zInstaller A climbs onto the tower. Then, installer
A fixes the pulley to the support of the tower
platform and leads the lifting rope through the
pulley.
zInstaller C uses a lifting rope to bind the RRU
and installation components as shown in the
preceding figure and then ties a knot in the steering
rope at the handle of the RRU.
zInstaller B pulls the lifting rope, and at the same
time, installer C pulls the steering rope away from
the tower to prevent the RRU and installation
components from colliding with the tower.
zInstaller A holds the RRU and installation
components and untie the ropes.
Steering rope
Lifting rope
Pulley
Appendix
22
Label for preparing
the power cable
15mm
8mm
14mm
010203040
Adding the OT terminals to the power cable involves adding OT terminals to the RRU
power cable and adding OT terminals to the shielding layer of the RRU power cable.
bAdding OT Terminals by Using a Wire Stripper (Recommended)
Determine lengths of power cables for
different operations according to the scales on
the inner side of the cover plate of the cabling
cavity.
Based on the determined length, remove the
jacket and shielding layer off the power cable.
Add an OT terminal to each wire.
Strip a 15 mm jacket off the power cable to
reveal the shielding layer of the power cable
Remove the jacket from each wire.
The OT terminals must be added to the power cable before the RRU is installed on a metal pole.
Appendix
-48V DC power cable -48V DC power wire
GND wire
Shielding layer
OT terminals
23
Appendix
cAdding OT Terminals to the Shielding Layer of the DC RRU Power Cable
Lead the wires
made of the
shielding layers
through heat-
shrinkable tubes.
Wrap the PVC
insulating tape
at the joint
where the three
wires meet. OT terminal on
the shielding
layer
Do not damage the shielding layer of the power cable when cutting around the jacket.
WARNING
24
Waterproofing Outdoor Cables
d
zThe waterproof tape should be wrapped for an extra length of 20
mm [0.8 in.] away from the connectors at both ends.
zThe tapes should be wrapped around the connector from the
lower part to the upper part. When wrapped for another layer, the
tapes may not be cut.
zWhen wrapping the waterproof tape, apply even force to extend
the tape until the width of the tape is 1/2 of the original width.
zWhen wrapping the waterproof tape, ensure that the upper layer
of the tape covers at least 50% of the lower layer.
zThe insulating tape should be wrapped for an extra length of 20
mm [0.8 in.] away from the connectors at both ends.
zThe last layer of the waterproof tape should be wrapped from
the lower part to the upper part to prevent rainwater from
infiltrating into the tape.
Waterproof tape Insulating tape
Installing the Optical Module
e
Tightly pressing the tape
1. Wrap three layers of waterproof tape.
2. Wrap three layers of insulating tape.
Tightly pressing the tape
Binding cable ties at both
ends of the tape
tie
tie
Appendix
25
Pin Assignment of the RRU AISG Extension cable
f
Brown
+24VTwisted pairWhite/brownX2.6X1.6
RS485 AGreenX2.5X1.5
RS485 BTwisted pairWhite/greenX2.3X1.3
Orange
DC Return ATwisted pairWhite/orangeX2.7X1.7
Blue
+12VTwisted pairWhite/blueX2.1X1.1
InstructionWire TypeWire ColorPin of the AISG
female connector
Pin of the AISG
male connector
Appendix
26
Change History
This describes the changes in the RRU3203 Installation Guide.
z01 (2010-04-13)
This is the commercial issue.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Industrial Base Bantian Longgang
Shenzhen 518129
People’s Republic of China
www.huawei.com

Navigation menu