NEC 07208901 LTE Base Station User Manual Installation Guide

NEC Corporation LTE Base Station Installation Guide

Installation Guide

Download: NEC 07208901 LTE Base Station User Manual Installation Guide
Mirror Download [FCC.gov]NEC 07208901 LTE Base Station User Manual Installation Guide
Document ID1768298
Application IDRhSDWIULl3ZXPxAerJqZ/w==
Document DescriptionInstallation Guide
Short Term ConfidentialNo
Permanent ConfidentialNo
SupercedeNo
Document TypeUser Manual
Display FormatAdobe Acrobat PDF - pdf
Filesize155.36kB (1941994 bits)
Date Submitted2012-08-16 00:00:00
Date Available2013-02-12 00:00:00
Creation Date2017-10-30 14:09:16
Producing SoftwareGPL Ghostscript 9.18
Document Lastmod2017-10-30 14:09:16
Document TitleInstallation Guide
Document CreatorFrameMaker 8.0

imnenb_LR3.0
LTE
Installation Manual
eNB
MB-14310050-001(E)-01
March, 2012
Copyright © 2012 by NEC Corporation
This document describes the current planned product and feature description and release. However, the
specifications, configuration and the release plan contained in this document are subject to change without any
notice due to NEC's continuing design improvement.
All rights reserved. No part of this publication may be reproduced, transmitted, transcribed, stored in a retrieval
system, or translated in any form for by any means without the written permission of NEC Corporation.
All designations used in this document can be trademarks, the use of which by third parties for their own
purposes violates the rights of their owners.
Printed in Japan
Revision History
Revision History
Issue
Date
Revision Description
Author
Approval
1.0
March 30, 2012
1st release
T.Araki
K. Yoshida
Remarks
Preface
Preface
Purpose of This Manual
This manual describes the required knowledge and procedure to install the LTE system (eNodeB, hereafter referred to as
eNB).
This manual targets the 700MHz All-in-one Type eNB.
Target Reader
This manual is intended for the LTE system installation personnel and operation and maintenance personnel of a network
operator.
Manual Structure
•
Section 1 Overview
Describes the system structure, equipment names and the main specification of the equipment.
•
Section 2 Equipment Appearance
Shows the appearance of eNB equipment and its dimensions.
•
Section 3 Equipment Installation Conditions
Shows the required space to install eNB equipment.
•
Section 4 Interface Conditions
Shows the cable connection system diagram and eNB equipment interface.
•
Section 5 Installation
Describes the cautions when carrying the equipment and the procedure to install eNB equipment.
•
Section 6 Cable Work
Describes the procedure to work on various types of cables.
•
Section 7 Voltage Check
Describes the procedure to check the voltage of the eNB equipment.
Symbols Used in This Manual
In this manual, the following symbol is used to show notes. When reference to a note is required, it is expressed as "Refer to
[i]."
CCC...CCC (CCC...CCC : note text)
Precautions
Precautions
The alert labels in this manual and attached to the eNB equipment body indicates the items you must follow to prevent
potential injury and safety hazard to you and other people, and perform the operation safely. Please read this manual
thoroughly before starting any operations.
Also, this manual must be kept in a safe place, so that you can read it whenever required.
When alert labels are directly attached to the equipment, always read the content.
This manual is intended for the LTE system installation personnel and operation and maintenance personnel of a network
operator.
Safety Instructions
The "Safety Instructions" provides safety instructions for the LTE system installation operations. For other items, read the
equipment manuals.
Definitions of Alert Categories
The following symbols categorize the dangers and level of damage that occurs when the content is ignored or wrong
procedure was performed.
DANGER:
This symbol indicates that there is explicit life-threatening danger that may cause death or
serious injuries if this item is ignored and the equipment is handled wrongly.
WARNING:
This symbol indicates that it may cause death or serious injuries if this item is ignored and the
equipment is handled wrongly.
CAUTION:
This symbol indicates that it may cause injuries and physical damage if this item is ignored and
the equipment is handled wrongly.
Precautions
Alert Labels
The following shows the alert labels attached to the equipment. If an alert label is attached, always follow the instruction
written on the label.
Federal Communications Commission
Changes or modifications not expressly approved by NEC Corporation could void the user s authority to operate the
equipment. (Section 15.21)
Section 15.105 (a) Class A Warning Label
NOTE: This equipment has been tested and found to comply with the limits for a Class A digital device, pursuant to part 15
of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference when the
equipment is operated in a commercial environment. This equipment generates, uses, and can radiate radio frequency energy
and, if not installed and used in accordance with the instruction manual, may cause harmful interference to radio
communications. Operation of this equipment in a residential area is likely to cause harmful interference in which case the
user will be required to correct the interference at his own expense.
About the Safety Instructions
When you find a safety instruction in this manual, be sure to read the instruction before starting the work.
The following safety instructions, especially regarding items that may cause death or injury to you and other people in this
manual are listed by their alert categories.
Precautions
Alert Category: CAUTION
CAUTION:
About the Work in General
•
Before starting the work, check the area of evacuation at the time of disaster.
•
Do not work wearing slippers. They may cause injury by falling, etc.
•
Be careful not to stumble over cables, parts and tools while working. It may cause
injuries and accidents.
•
Be careful not to get the sleeves and hems of the working clothes caught. It may
cause injuries and accidents.
•
Do not place liquid such as water into the equipment, and do not touch the
equipment with wet hands. Moisture in the equipment may cause electrocution
and equipment failure. In case liquid gets into the equipment, turn off the
equipment power and request repair.
•
Do not dismantle or alter the equipment. It may cause electrocution, fire and
equipment failure.
•
When installing or removing the equipment, cure the floor surface of the installed
location to prevent damage by dropping parts.
About Handling the eNB Equipment and SFP
•
When handling eNB equipment itself and SFP, wear globes (thin cotton gloves).
Working with bare hands may cause burns, injury and accidents.
•
Use correctly the parts for testing such as SFP, tester and cable referring to their
user manuals.
•
When handling the eNB equipment and the SFP, wear a wrist band as an antistatic
measure. If you do not take any antistatic measures, the static electricity may
damage the equipment and the SFP.
About Handling High Voltage/ High Current
•
Only the installation worker can touch the eNB equipment . Inside eNB
equipment, there are high voltage/ high currents flows, and they may cause
accidents.
•
Always perform ground connection. Not following this instruction would cause
system failure by lightening and electrocution.
•
When measuring voltage/ current, take appropriate insulating measures such as
covering the measurement terminal and the unused tool parts with insulating
tapes. Contact of measurement terminal and other terminals, or short-circuit by
tools may cause electrocution and accidents.
Precautions
Notes on Running the System
In "Notes on Running the System", the notes to protect the equipment from failure are described. To run the system normally,
follow the notes to operate.
Environment Conditions on Running the System
The following shows the usage conditions of eNB equipment. To run the system normally, consider the following items
during installation operation.
Category
Details
Installation
Install in a limited access area.
Temperature and
humidity
- Do not ventilate outside air.
- Refer to the following and check that the temperature and humidity
are appropriate. Also, check that there is no condensation.
Vertical Setup
-33ºC to +50ºC (No sunlight)
-33ºC to +45ºC (With sunlight)
Horizontal setup
-33ºC to +45ºC (No sunlight)
-33ºC to +40ºC (With sunlight)
The above temperature limits of operation environment drops by
2.5ºC for every 1km of altitude rise.
Liquid
- Do not place liquid such as water and oil near eNodeB.
Vibration
eNodeB is a precision instrument, so do not expose to vibration of
standard level (Telcordia NEBS GR-63-CORE Zone4) or more.
Heat dissipation
- Natural cooling of eNB satisfies all the environmental conditions.
- To gain the expected heat dissipation, eNB has a radiator for natural
cooling on its surface. Natural cooling radiator, for its physical
characteristic, must be set up so that the fin part is vertical or
horizontal.
- No cooling method such as cooling by fans is used for eNodeB.
- There is no periodic replacement parts such as air filters.
- No always-driving part such as a fan is used for eNodeB.
Precautions
Notes on Running the System in General
•
Before installing the equipment, remove all connector caps attached to the equipment side external interface connectors
to which external cables are planned to be connected.
Removing the connector caps, etc. in a high place may result in the connector caps dropping.
- If external cables are not connected right after equipment installation, place outdoor weather resistant tapes on the
temporary connector caps as waterproof treatment.
•
In case you touch the equipment for maintenance, there may be places on the equipment reaching high temperature.
Wear protection such as gloves when handling the equipment.
•
Do not allow foreign objects such as screws, wire rods and metal scraps inside the eNB Equipment. They may cause eNB
equipment failure by equipment damage and short-circuit.
•
Wear antistatic shoes while working.
•
When working after rain, wipe the water drops on the equipment before opening the maintenance window.
Precautions
Notes on Handling the eNB Equipment and SFP
•
10
To prevent static electricity, always wear globes (thin cotton gloves) and a wrist band as antistatic measures when
working on the eNB equipment, inserting or removing SFP into/from the equipment.
By static electricity the electrical parts of the equipment or the SFP may be damaged. The grounding terminal of the wrist
band is connected to the earth bonding point in the maintenance window of the equipment.
Precautions
Notes on Handling the Power
•
Do not turn the power ON/ OFF unless required.
Notes on Handling the Cables and Connectors
•
Do not swing or bend the cable with force. It may cause the cable to break or damage the connector.
•
Do not remove the optical connector cap unless connecting the connector. If the optical connector is damaged or gets
dust on it, it may cause communication failure.
•
Use the tools and parts such as cables correctly, referring to their user manuals.
•
Tie the external cables without putting stress, meaning without twisting and pulling on the equipment connector part.
•
When removing the connector or the waterproof cap to mate again, clean the mating parts.
•
Depending on the environment condition, the FullAXS connector surface may become rough, and touching it by bare
hands may cause the plastic toughening agent to irritate the skin. If the toughening agent gets on to your skin, wash it
thoroughly.
11
Table of Content
Table of Content
Revision History . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Precautions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
12
1.1
1.2
1.3
Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
System Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Equipment Names . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Main Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Equipment Appearance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Equipment Installation Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
4.1
4.2
4.2.1
4.2.2
4.2.3
Interface Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Cable Connection System Diagram. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
External Interface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Bottom Face External Interface Locations/ Names and Interface Details. . . . . . . . . . . . . . . . 22
Top Face External Interface Locations/ Names and Details. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Maintenance Window Interface Locations/ Names and Details . . . . . . . . . . . . . . . . . . . . . . . . 24
5.1
5.1.1
5.1.2
5.1.3
5.2
5.2.1
5.3
5.3.1
5.3.2
5.3.3
5.3.4
5.3.5
5.4
Equipment Installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
Cautions on Carrying the Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
Temporary Placement of Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
Carrying the Equipment by the Handles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Carrying Equipment by Hoisting Up/ Down. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Equipment Installation Forms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Installation Examples of Ladder/ Wall/ Pole/ Cross arm/ Suspension Mount . . . . . . . . . . . . 29
Ladder/ Wall/ Pole/ Cross Arm/ Suspension Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
Dedicated Mounting Hardware for Installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
Installation Method . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
Installation Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
C-COVER (Connector Cover) Installation Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
F-COVER (Front Cover) Installation Procedure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
List of Attachments and Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
6.1
6.2
6.2.1
6.2.2
6.2.2.1
6.2.2.2
6.3
6.3.1
6.3.1.1
6.3.2
6.3.2.1
6.3.3
Cable Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
List of Used Cables and Connectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
Power Cable Connection (-48V DC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
Power Cable Connection Composition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
Power Cable Connection Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
Floating Type Cable Connection Procedure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
Fixed Type Cable Connection Procedure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
Backhaul Cable Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
Metal Type Backhaul Cable Connection (BH(E)) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
Backhaul Cable Connection Procedure (Electrical) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
Optical Type Backhaul Cable Connection (BH(O)) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
Backhaul Cable Connection Procedure (Optical) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
Notes on Handling Optical Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
Table of Content
6.4
6.4.1
6.5
6.5.1
6.6
6.6.1
6.7
6.7.1
6.8
6.8.1
6.9
6.9.1
6.9.2
6.9.3
GPS Cable Connection (GPS) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
GPS Cable Connection Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
External Alarm Interface Cable Connection (EXT ALM) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
External Alarm Interface Cable Connection Procedure (EXT ALM) . . . . . . . . . . . . . . . . . . . . . 64
FG Cable Connection (FG) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
FG Cable Connection Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
Antenna Tilt Control Cable Connection (RET) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
Antenna Tilt Control (RET) Cable Connection Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
Antenna Cable Connection (ANT0/ANT1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
Antenna Cable Connection Procedure (ANT0/ANT1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
Connector Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
Power Connector Pin Allocation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
Antenna Tilt Control Connector (IEC60130-9). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72
External Alarm Interface (EXT ALM) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
7.1
7.2
Voltage Check. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
Cable Side Power Connector Pin Location Polarity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
Voltage Check Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75
13
Overview
Overview
This manual describes the installation of eNodeB (hereafter called eNB) NL Rel 3.0.
1.1
This manual is created as a standard version.
System Structure
The installation target in this manual, All-in-one Type eNB is a micro-miniature base station equipment which can be
installed out of doors. Its micro-miniaturization was accomplished by unification of the parts: the interface part to upper level
lines, call processing control part, monitor control part, Baseband processing part (BB part), TRXBB part, radio amplifier part
and radio function part. By this, the space required for installation, installation man-hours, installation parts and maintenance
man-hours are all reduced and the degree of freedom in selecting the installation location and direction is increased.
Figure 1 shows the installation image of All-in-one Type eNB.
Figure 1
14
All-in-one Type eNB Installation Image
Overview
1.2
Equipment Names
Table 1 shows the equipment type and displayed code applicable to this manual.
Table 1
Equipment List
No.
Equipment Type
Display Code
Note
Band 13: 700MHz
MB4300-n313
Power source: DC -48V
Transmission output: 5w x 2ports
1.3
Main Specifications
Table 2 shows the main specifications of All-in-one Type eNB.
Table 2
Main Specifications of All-in-one Type eNB
No.
Item
Performance/ Characteristic/ Applied Method
Transmission/ Reception
Frequency
[DL] 746 - 756MHz
Dimensions
251.0 ± 2.5[mm](W)
[UL] 777 - 787MHz
562.0 ± 4.0[mm](H)
149.0 ± 2.5[mm](D)
(Excluding protrusions)
Mass
17.0[kg]
Excluding mounting hardware, F-COVER (Front Cover) and CCOVER (Connector Cover).
Power Specification
DC-48 [V]: -43.2V to -57.0V
Rated current
7[A]
Maximum Power
Consumption
Including AISG consumption:
206.6[W]
Excluding AISG consumption:
198.6[W]
Operation Environment
Temperatures
Vertical setup
-33ºC to +50ºC (No sunlight)
-33ºC to +45ºC (With sunlight)
Horizontal setup
-33ºC to +45ºC (No sunlight)
-33ºC to +40ºC (With sunlight)
The above temperature limits of operation environment drops
by 2.5ºC for every 1km of altitude rise.
Relative Humidity
5% - 95%
15
Overview
Table 2
Main Specifications of All-in-one Type eNB
No.
Item
Performance/ Characteristic/ Applied Method
Quake Resistance
- Telcordia NEBS GR-63-CORE Zone 4
- IEC 60721-2-6: Zone 4
10
EMC Standard
FCC Part15 Subpart B Class A
11
Waterproof/Dustproof
IP65 (IP66 with cover)
12
Surge Limit
- Power voltage (outdoors)
Conforms to CE marking
L-E 1.2/50µs, ± 0.5kV 8/20µs
L-L 1.2/50µs, ± 0.5kV 8/20µs
- External alarm interface
Conforms to CE marking
L-E 1.2/50µs, ± 1kV 8/20µs
- Backhaul interface
Conforms to CE marking
L-E 1.2/50µs, ± 1kV 8/20µs
- Lightening SURGE
L-E 1.2/50µs, 10kV 8/20µs, 5kA
L-L 1.2/50µs, 2.5kV 8/20µs, 1.25kA
13
16
Safety Standards
CSA 60950-1, 60950-22
Equipment Appearance
Equipment Appearance
The following shows the equipment appearance and equipment flat surface appearance of All-in-one Type eNB.
Equipment Appearance
Figure 2
Equipment Appearance
17
Equipment Appearance
Equipment Flat Face Appearance
Figure 3
18
Equipment Flat Face Appearance
Equipment Installation Conditions
Equipment Installation Conditions
The following shows the clearance condition for single installation of All-in-one Type eNB. (In case of "Ladder mount/ wall
mount/ pole mount/ cross arm mount or suspension mount .)
Figure 4
Single Installation Clearance
Make sure the temperature is 50ºC or lower at all the front, back, left and right sides.
Make sure air ventilation is possible through the top face.
19
Interface Conditions
Interface Conditions
4.1
Cable Connection System Diagram
Figure 5 shows the cable connection system diagram for All-in-one Type eNB. Table 3 shows the list of connectors and
legends.
Figure 5
Cable Connection System Diagram
20
Install dedicated power supply cable and breaker to the eNB equipment from the power source facility (DCPD).
Breaker would work as the equipment's breaker.
Connector type on the backhaul network side depends on the remote equipment.
Figure 5 omits ACPDB master, ACPDB, storage battery, UPS equipment, etc.
Broken line in Figure 5 may change depending on installation contract, scope of work and installation design.
Interface Conditions
Table 3
Symbol
Connector List/ Legend
Details
Out of preparation range
Symbol
Detail
Round waterproof (P)
IEC60130-9
Attachment to equipment main
body/ installation cables
Round waterproof (J)
N type waterproof (P)
Optical 2-core waterproof
boots (P)
N type waterproof (J)
Optical 2-core waterproof
boots (J)
Out of preparation range, or
parts different by office
condition or design
Square waterproof boots
(P)
RJ-45+waterproof boots (P)
Square waterproof boots
(J)
RJ-45+ waterproof boots (J)
M6 crimping terminal
IEC60130-9
21
Interface Conditions
4.2
External Interface
The following shows the interface locations, names and details on bottom face, top face and maintenance window of All-inone Type eNB.
4.2.1
Bottom Face External Interface Locations/ Names and Interface Details
Bottom Face External Interface Locations and Names
Figure 6
External Interface Locations and Names (Bottom Face)
Interface Details
Table 4
22
External Interface Details (Bottom Face)
No. in Fig
External Interface Label
External Interface Name
(1)
BH (O)
Backhaul interface (Optical)
(2)
BH (E)
Backhaul interface (Electrical)
(3)
EXT ALM
External alarm interface
(4)
-48V DC
Power input interface
(5)
RET
Antenna tilt control interface
(6
FG
Frame ground
(7)
GPS
L1 GPS interface
Interface Conditions
4.2.2
Top Face External Interface Locations/ Names and Details
Top Face External Interface Locations and Names
Figure 7
External Interface Locations and Names (Top Face)
Interface Details
Table 5
External Interface (Top Face)
No. in Fig
External Interface Label
External Interface Name
(1)
ANT 0
RF antenna interface 0
(2)
ANT 1
RF antenna interface 1
23
Interface Conditions
4.2.3
Maintenance Window Interface Locations/ Names and Details
Maintenance Window Interface Locations and Names
Figure 8
Maintenance Window Image
Interface Details
Table 6
24
Maintenance Window Interface Details
No. in Fig
External Interface Label
External Interface Name
(1)
LMT
LMT interface
Equipment Installation
Equipment Installation
This section shows the installation procedure of All-in-one Type eNB.
Before installing the equipment, remove all connector caps attached to the equipment side external interface
connectors to which external cables are planned to be connected.
Removing the connector caps, etc. in a high place may result in the connector caps dropping.
5.1
If external cables are not connected right after equipment installation, place outdoor weather resistant tapes on
the temporary connector caps as waterproof treatment.
Cautions on Carrying the Equipment
The following shows the cautions on when carrying the All-in-one Type eNB.
5.1.1
Carrier of All-in-one Type eNB must wear working gloves and shoes.
When carrying the equipment into the premise, perform required curing on the route.
Carry the equipment in its package box to prevent damage while carrying.
When the equipment goes through the inspection door, cure the opening to prevent damage to the building
and equipment.
Temporary Placement of Equipment
If temporarily placing All-in-one Type eNB on the floor, place it carefully as shown in Figure 9 to prevent damage to
connectors and protrusions.
Figure 9
Temporary Placement Image
25
Equipment Installation
5.1.2
Carrying the Equipment by the Handles
When carrying All-in-one Type eNB, the flange part (shaded part) on both sides of the main body can be used as handles.
Refer to Figure 10.
Figure 10
Handling Parts Used for Carrying
When handling the equipment, be careful not to damage the connectors on the bottom face of equipment.
If you place the equipment vertically on the floor, it may damage the connectors on the bottom face.
26
Equipment Installation
5.1.3
Carrying Equipment by Hoisting Up/ Down
When hoisting the equipment up/ down, use eye-bolts and follow the procedure below.
Insert eye-bolts into the screw holes on the sides of the equipment as shown in Figure 11.
Figure 11
Attaching eye-bolts
Hoist the equipment using a crane, etc. up to a higher place or down to a lower place by placing ropes in the eyebolts as shown in Figure 12.
After carrying the equipment, remove the eye-bolts.
27
Equipment Installation
Figure 12
28
Hoist up/down Image
Equipment Installation
5.2
Equipment Installation Forms
All-in-one Type eNB has the following installation forms considering the ease of installation.
•
Ladder mount/ Wall mount/ Pole mount
Vertical setup
•
Cross arm mount/Suspension mount
Horizontal setup
5.2.1
Installation Examples of Ladder/ Wall/ Pole/ Cross arm/ Suspension Mount
The following shows the images of ladder/ wall/ pole/ cross arm/ suspension mount of All-in-one Type eNB.
Ladder mount/ Wall mount/ Pole mount
Figure 13
Installation Images Part 1
29
Equipment Installation
Cross Arm Mount/ Suspension Mount
Figure 14
30
Installation Images Part 2
When setting up the equipment horizontally, set it so that the mounting hardware is on the top face.
Equipment Installation
5.3
Ladder/ Wall/ Pole/ Cross Arm/ Suspension Installation
5.3.1
Dedicated Mounting Hardware for Installation
All-in-one Type eNB (ladder/ wall/ pole/ cross arm/ suspension mount) is installed using the dedicated mounting hardware
which is the standard installation method. For details on the dedicated mounting hardware, refer to the following figure.
Figure 15
Dedicated Mounting Hardware
31
Equipment Installation
5.3.2
Installation Method
The following shows the method to install All-in-one Type eNB (ladder/ wall/ pole/ cross arm/ suspension mount).
The following shows the image to mount the dedicated mounting hardware on the installation surface.
Wall/ Ladder Mount
Figure 16
32
Wall/ Ladder Mount Installation Image
Equipment Installation
Pole Mount
Figure 17
Pole Mount Installation Image
The bands and any ledge to put on the mounting hardware must be prepared by the installation company or
the customer.
33
Equipment Installation
Cross Arm/ Suspension Mount
Figure 18
34
Cross Arm/ Suspension Mount Installation Image
Cross Arms, suspension parts and cross arm fixing bolts on the power source column, etc., suspension part
mounting bolts, wires between poles must be prepared by the installation company or the customer.
Equipment Installation
5.3.3
Installation Procedure
The following shows the procedure to install All-in-one Type eNB (ladder/ wall/ pole/ cross arm/ suspension mount).
Installing the dedicated mounting hardware (ladder/ wall/ pole/ cross arm/ suspension)
This equipment requires electrical insulation with the installed surface, so when fixing by M8 bolts, insulating bushes
are used.
Refer to Figure 19, and fix using M8 bolt with the bushes in the correct order.
If there is no male screw, fix with M8 nut, etc.
Finally, tighten the bolts again, and mark the bolts. (M8: torque 17 ± 1 N• m)
If there is no hole to install the equipment on the installed surface (ladder/ wall/ pole/ electrical pole/
suspension parts), perform drilling referring to the dedicated mounting hardware installation hole
dimensions (Figure 15).
Be careful not to deform the mounting hardware when fixing the equipment.
Figure 19
Dedicated Mounting Hardware Installation
35
Equipment Installation
Installing the Equipment to Dedicated Mounting Hardware
Insert the 4 fixing bolts into the screw holes on the top, bottom, left and right side of equipment (the back side hole
out of the 3 screw holes in a row) for about the half of their length and temporarily fix them. Refer to Figure 20 for
installation of fixing bolts
Figure 20
36
Fixing Bolts Installation
Equipment Installation
Hang the equipment by the four M8 bolts (attached to equipment) temporarily fixed in step (1) onto the chases
on top/ bottom/ left and right of the dedicated mounting hardware. Refer to Figure 20 for installation onto the
mounting hardware.
Figure 21
Installing the Equipment onto the Mounting Hardware
37
Equipment Installation
Tighten the four M8 bolts temporarily fixed in step (1). Lastly, tighten the bolts further and mark the bolts, and
the installation is complete (torque value M8: 17 ± 1 N• m).
Figure 22
38
Tightening the Fixing Bolts
Equipment Installation
5.3.4
C-COVER (Connector Cover) Installation Procedure
C-COVER is an optional part.
Check the screw holes (the center of the 3 screw holes) on the left and right sides of eNB equipment.
Figure 23
Right Side Fixing Bolt Installation Location (Reference)
Insert the two fixing bolts into the screw holes on the left and right sides of the equipment bottom part (the center
of the 3 screw holes) for half of its length and fix temporarily.
Figure 24
Installing Fixing Bolts
39
Equipment Installation
Set a RAC-NUT into the round hole on the mounting hardware, with the screw side facing inward.
Figure 25
40
Installing RAC-NUT
Equipment Installation
Set the C-COVER chase to the protruding parts on the left and right of dedicated mounting hardware, and pull
the C-COVER a little downwards to hang the C-COVER on the mounting hardware.
Figure 26
Temporarily Installing the C-COVER
Fix the drop-proof wire of the C-COVER using a TORX screw (M5) onto the dedicated mounting hardware
(torque value M5: 4 ± 0.5 N• m).
Figure 27
Installing the Drop-Proof Wire
Pulling the drop-proof wire of the C-COVER strongly may cut it off. If the wire is cut, there is a risk of the
C-COVER dropping when trying to remove it.
41
Equipment Installation
Lift the C-COVER upwards (in direction indicated by the blue arrow), and insert (red arrow) the C-COVER nails
into the gaps of two fixing bolts of the left and right side, which were temporarily fixed in step (2).
Figure 28
Tighten the fixing bolts which were temporarily fixed in step (2). Finally, tighten the bolts again and mark the
bolts, and the installation procedure is complete (torque value M8: 17 ± 1 N•m).
Figure 29
42
Temporarily Installing the C-COVER
Tightening the Fixing Bolts
Equipment Installation
5.3.5
F-COVER (Front Cover) Installation Procedure
F-COVER is an optional part.
Check the screw holes (front side hole out of the three screw holes) on the top, bottom, left and right to set the
fixing bolts.
Figure 30
Installation Location of Fixing Bolts on the Right Side Top and Bottom (Reference)
Insert the four fixing bolts (attached parts) into the screw holes (front side hole out of the three screw holes) on
the top, bottom, left and right of equipment for half of their length and fix temporarily.
Figure 31
Installing Fixing Bolts
43
Equipment Installation
Insert the F-COVER chase into the gap of fixing bolts temporarily fixed in step (2).
Figure 32
Tighten the four fixing bolts on top, bottom, left and right which were temporarily fixed in step (2). Finally, tighten
the bolts again and mark the bolts, and the installation procedure is complete (torque value M8: 17 ± 1 N•m).
Figure 33
44
Installing the F-COVER
Tightening the Fixing Bolts
Equipment Installation
5.4
List of Attachments and Tools
The following lists the attachments and tools required for equipment installation.
Table 7
Attachment List
Item Name
Quantity
Note
For FG (M6 + pan head screw)
Mount on equipment
Connector caps
1 set
Mount on equipment
Dedicated mounting hardware
1 set
Including installation parts
F-COVER
1 set
Optional, including installation parts
C-COVER
1 set
Optional, including installation parts
Table 8
Tool List
Item Name
Used for
M6 + Standard driver
FG
TORX T25 size screw driver
C-COVER drop-proof wire fixing screw
and maintenance window
Hexagonal spanner (For M8)
Dedicated mounting hardware, C-COVER
and F-COVER
Note
With tamper-resistant pin
45
Cable Work
Cable Work
6.1
List of Used Cables and Connectors
Table 9 shows the cables and connectors used for this equipment.
Table 9
External Interface/
Name
46
Used Cables and Connectors
Connectors on Equipment
Connectors on Cable
Connector
type
1st line: Vender name
Connector
type
1st line: Vender name
Power source input
interface -48V DC
Square bipolar
TE
FullAXS
TE
GPS interface / GPS
N type
waterproof (J)
DDK
External alarm
interface / EXT ALM
RJ-45
Optical BH interface /
BH(O)
LC 2-core
(MMF core
radius 50 µm)
TE
LC 2-core
(MMF core
radius 62.5
µm)
TE
LC 2-core
(SMF)
TE
Metal BH interface /
BH(E)
RJ-45
TE
Antenna tilt control
input interface / RET
Round
waterproof (J)
IEC60130-9
2nd line: Vender model
name
2nd line: Vender model
name
FullAXS POWER
FLOATING or FullAXS
POWER FIXED
FOAC FullAXS
BULKHEAD HOUSING +
square bipolar
N-SR-J-1.5D
N type
waterproof
General-purpose
connector. No vender/
model name specified.
TE
RJ-45
TE
FullAXS SIGNAL
FLOATING
FOAC FullAXS
BULKHEAD HOUSING +
RJ45
LC 2-core
FOMM50 LEAD4.8mm
FullAXS LC/DPXLC/DPX
FOAC FullAXS
BULKHEAD HOUSING +
LC 2-core
LC 2-core
LC 2-core
TE
FOSM LEAD4.8mm
FullAXS LC/DPXLC/DPX
FOAC FullAXS
BULKHEAD HOUSING +
LC 2-core
RJ-45
TE
FullAXS SIGNAL
FLOATING
FOAC FullAXS
BULKHEAD HOUSING +
RJ45
AISG-RECE-CONNESOCKET-TYPE01
TE
FOMM62.5 LEAD4.8mm
FullAXS LC/DPXLC/DPX (Model name not
fixed: in discussion with
TE)
FOAC FullAXS
BULKHEAD HOUSING +
LC 2-core
Amphenol
TE
Round
waterproof (P)
IEC60130-9
AISG general-purpose
Cable Work
Table 9
External Interface/
Name
RF antenna interface /
ANT0, ANT1
Used Cables and Connectors
Connectors on Equipment
Connectors on Cable
Connector
type
1st line: Vender name
Connector
type
1st line: Vender name
N type
waterproof (J)
N(F)4H BULKHEEAD
18.0-7.0
N type
waterproof (P)
General-purpose
connector. No vender/
model name specified.
2nd line: Vender model
name
2nd line: Vender model
name
47
Cable Work
6.2
Power Cable Connection (-48V DC)
Figure 34 shows the position of the connector used to connect the power cable.
Figure 34
48
Bottom Face Cable Connection Position (Power Connector)
Cable Work
6.2.1
Power Cable Connection Composition
The following shows the connection composition of the power cable. There are two types of power cable: the Floating type
and the Fixed type.
Figure 35
Power Connection Cable Composition
49
Cable Work
6.2.2
Power Cable Connection Procedure
The following shows the procedure to connect the power cable.
50
Check that the corresponding breaker is OFF when mating the power connector.
Move the Inner and Outer straight to the insertion direction. Inserting them at an angle or twisting them may
damage the connector.
Perform the connection while holding the cables close to the equipment, so that the connectors do not drop out
by the cable weight, etc.
The Outer, Inner and the connectors are made out of plastic. Stepping on them or banging them may damage
them, so handle them with care.
Even if the Outer is fixed, twisting the cable may place load to the internal connector and damage it. When
laying cables, be careful not to twist them.
After mating, discard the waterproof cap attached to the cable. The wind, etc. may break the cord, and the cap
may drop.
When disconnecting the power cable, turn the power off from the power source.
When laying cables, always keep the bend radius to 66 mm or more.
Cable Work
6.2.2.1
Floating Type Cable Connection Procedure
The following shows the procedure to connect the Floating type cable.
Insert the connector part of the power cable to the equipment side connector.
(1) Connect the connector latch of the power cable towards the mounting hardware side of eNB equipment.
51
Cable Work
(2) Push in the connector of the power cable in until the latch mates.
Pushing in by force holding the mold part may damage the connector part. Make sure to hold the
connector part when connecting.
Insert the power cable Inner straight into the connector on the equipment.
When inserting the power cable Inner, there would be friction between the inner cable and the Inner, so
hold the cable with your hand while inserting.
After inserting the power cable Inner, pull the cable while still holding the cable with your hand, to closely
fit the mold part and the Inner.
52
Cable Work
Rotate the power cable Outer clockwise to fix it in place.
53
Cable Work
6.2.2.2
Fixed Type Cable Connection Procedure
The following shows the procedure to connect the Fixed type cable.
54
Inserting the power cable by force at a wrong connector position or with the connector facing upside down may
damage the connector and the printed circuit board inside the equipment. Do not insert the cable by force, and check
the direction of the power cable connector again.
Positioning with the white marking, insert the power cable into the equipment connector until the Inner is beside
the guide on the equipment side connector.
Pushing the power cable Outer, rotate it clockwise to fix it.
Cable Work
6.3
Backhaul Cable Connection
6.3.1
Metal Type Backhaul Cable Connection (BH(E))
Figure 36 shows the location of the connector to connect the backhaul (Electrical) cable.
Figure 36
eNB Bottom Face Cable Connection Position (Backhaul interface (Electrical))
The following shows the composition of the backhaul connection cable (Electrical).
Figure 37
Backhaul Connection Cable (Electrical) Composition
55
Cable Work
6.3.1.1
Backhaul Cable Connection Procedure (Electrical)
The following shows the procedure to connect the backhaul cable (Electrical).
56
Move the Inner and Outer straight to the insertion direction. Inserting them at an angle or twisting them may
damage the connector.
Perform the connection while holding the cables close to the equipment, so that the connectors do not drop out
by the cable weight, etc.
The Outer, Inner and the connectors are made out of plastic. Stepping on them or banging them may damage
them, so handle them with care.
Even if the Outer is fixed, twisting the cable may place load to the internal connector and damage it. When
laying cables, be careful not to twist them.
After mating, discard the waterproof cap attached to the cable. The wind, etc. may break the cord, and the cap
may drop.
When laying cables, always keep the bend radius to 22 mm or more.
Insert the RJ45 connector part to the equipment connector, until the latch mates.
Cable Work
Insert the Inner straight into the equipment connector.
When inserting the Inner, there would be friction between the inner cable and the Inner, so hold the cable
with your hand while inserting.
Rotate the Outer clockwise to fix it in place.
57
Cable Work
6.3.2
Optical Type Backhaul Cable Connection (BH(O))
Figure 38 shows the position of the connector to connect the backhaul (Optical) cable.
For notes on handling the optical cable, refer to section 6.3.3.
Figure 38
eNB Bottom Face Cable Connection Position (Backhaul Interface (Optical))
The following shows the backhaul connection cable (Optical) composition.
Figure 39
58
Backhaul Connection Cable (Optical) Composition
Cable Work
6.3.2.1
Backhaul Cable Connection Procedure (Optical)
The following shows the procedure to connect the backhaul cable (Optical).
When connecting cable to BH(O), remove the waterproof cap on BH(O) and put it on BH(E).
Move the Inner and Outer straight to the insertion direction. Inserting them at an angle or twisting them may
damage the connector.
Perform the connection while holding the cables close to the equipment, so that the connectors do not drop out
by the cable weight, etc.
The Outer, Inner and the connectors are made out of plastic. Stepping on them or banging them may damage
them, so handle them with care.
Even if the Outer is fixed, twisting the cable may place load to the internal connector and damage it. When
laying cables, be careful not to twist them.
After mating, discard the waterproof cap attached to the cable. The wind, etc. may break the cord, and the cap
may drop.
When laying cables, always keep the bend radius to 30 mm or more.
Insert the LC 2-core connector part into the equipment SFP, until the latch mates.
59
Cable Work
Insert the Inner straight into the equipment SFP.
60
When inserting the Inner, there would be friction between the inner cable and the Inner, so hold the cable
with your hand while inserting.
Rotate the Outer clockwise to fix it in place.
Cable Work
6.3.3
Notes on Handling Optical Cables
The following shows the notes on handling the optical cables.
When applying surplus treatment to the optical cable connecting the BH(O) connector of this equipment and
the termination box, keep the outdoor armored cable bend radius to 120 mm (240 mm in diameter) or more.
When applying surplus treatment inside the termination box, keep the able bend radius to 30 mm (60 mm in
diameter) or more for the parts without outdoor armored cable.
Applying too much force on the optical cable may damage it. Connect the optical cable so that it is not twisted.
When fixing the optical cable, tie the optical cable so that it is not twisted.
Figure 40
•
Surplus Treatment of Optical Cable
Cleaning Equipment SFP and Optical Cable LC Connector
Use the cleaning utensil (stick type) (for φ 1.25) to wash the ferrule (pin-shaped) end-face and side-face of the contact
terminal on the SFP and optical cable LC connector mating part. (Alcohol cannot be used together)
G Do not reuse the cleaning utensil already used once. Invisible dust is attached on the used utensil so reusing it
may damage or contaminate the optical cable.
61
Cable Work
6.4
GPS Cable Connection (GPS)
Figure 41 shows the position of the connector to connect the GPS cable.
Figure 41
6.4.1
Bottom Face Cable Connection Position (GPS connector)
GPS Cable Connection Procedure
The following shows the procedure to connect the GPS cable.
Insert the GPS connector into the GPS connector on the eNB equipment.
After holding the ring on the GPS cable against the GPS connector on the eNB equipment, tighten until the male
screw ridges of the GPS connector on the eNB equipment are invisible.
Recommended tightening torque is 0.7 N•m to 1.1 N•m.
62
Cable Work
Figure 42
GPS Cable Connection
To prevent the mating part loosening, it is recommended to protect the connector on the eNB equipment up to
the cable (so that the cable side connector is completely covered) with outdoor weather-proof tape.
Figure 43
GPS Cable Connector Protection Example
Figure 44
GPS Cable (with Waterproof Cap)
63
Cable Work
6.5
External Alarm Interface Cable Connection (EXT ALM)
Figure 45 shows the position of the connector to connect the external alarm interface cable.
Figure 45
Bottom Face Cable Connection Position (External Alarm Interface (EXT ALM))
The following shows the external alarm interface connection cable composition.
Figure 46
6.5.1
External Alarm Interface Connection Cable Composition
External Alarm Interface Cable Connection Procedure (EXT ALM)
The connection procedure of the external alarm interface cable is the same as that of the metal type backhaul cable, so refer
to section 6.3.1 .
64
Cable Work
6.6
FG Cable Connection (FG)
Figure 47 shows the position of the Frame Ground (FG) connector screw to connect the FG cable.
Figure 47
6.6.1
Bottom Face Cable Connection Position (FG)
FG Cable Connection Procedure
The following shows the procedure to connect the FG line.
Use the M6 + pan head screw installed on the FG terminal to connect the FG cable to the equipment.
Figure 48
FG Terminal Connection Part
65
Cable Work
The recommended tightening torque is 4 N•m.
When connecting the FG cable, connect it so that it would take the shortest way to the ground point
in the office.
To prevent loosening, it is recommended to protect the connector on the eNB equipment + pan-head screw to the
FG line (so that the FG line side crimping terminal is completely covered) with outdoor weather-proof tape.
Apply protection after checking the voltage referring to section 7. If protection is applied before checking
the voltage, some voltage check procedure cannot be performed.
Figure 49
66
Crimping Terminal Mounting Screw Protection Example
Cable Work
6.7
Antenna Tilt Control Cable Connection (RET)
Figure 50 shows the position of the connector to connect the antenna tilt control cable.
Figure 50
6.7.1
Bottom Face Cable Connection Position (RET)
Antenna Tilt Control (RET) Cable Connection Procedure
The following show the procedure to connect the antenna tilt control (RET) cable.
Insert the antenna tilt control cable connector into the antenna tilt control connector on the eNB equipment.
Holding the ring of the antenna tilt control cable against the antenna tilt connector on the eNB equipment, use
your hand to tighten the ring on the cable clockwise.
Recommended tightening torque is 1.0 N•m to 1.2 N•m.
67
Cable Work
Figure 51
68
Antenna Tilt Control Connector Connection
To prevent the mating part loosening, it is recommended to protect the connector on the eNB equipment up to
the cable (so that the cable side connector is completely covered) with outdoor weather-proof tape.
Figure 52
Connector Protection Example (RET)
Figure 53
Waterproof Cap Protection Example
Cable Work
6.8
Antenna Cable Connection (ANT0/ANT1)
Figure 54 shows the positions of the connectors to connect the antenna cable.
Figure 54
6.8.1
Top Face Cable Connection Position (Antenna Cable)
Antenna Cable Connection Procedure (ANT0/ANT1)
The following shows the procedure to connect the antenna cable.
Insert the antenna cable connector into the RF connector on the eNB equipment.
Holding the ring on the antenna cable against the RF connector on the equipment, tighten the ring of the antenna
cable until the male screw ridges of the RF connector on the equipment are invisible.
Recommended tightening torque is 0.7 N•m to 1.1 N•m.
69
Cable Work
Figure 55
To prevent the mating part loosening, it is recommended to protect the connector on the eNB equipment up to
the cable (so that the cable side connector is completely covered) with outdoor weather-proof tape.
Figure 56
70
Antenna Cable Connection
Connector Protection Example (ANT)
Cable Work
6.9
Connector Details
6.9.1
Power Connector Pin Allocation
The following shows the pin allocations on the power connector installed on the eNB equipment.
Table 10
Terminal Number and Signal Names
Pin No.
Signal name
-48V DC
0V
Figure 57
Power Connector Pin Allocations
71
Cable Work
6.9.2
Antenna Tilt Control Connector (IEC60130-9)
The following shows the pin allocations for the antenna tilt control connector on the eNB equipment.
Table 11
Pin No.
Signal name
AISG Requirement
+12V DC nominal
Not supported
-48V DC nominal
Not supported
RS485 B
Would be supported
RS485 GND
For eNB, it is supported. Whether it is used or note depends on RET
support situation.
RS485 A
Would be supported
10V -30V DC
Would be supported
DC return
Would be supported
N/C
Reserved for future extension.
Figure 58
72
Terminal Number and Signal Names
Pin Allocations for Antenna Tilt Control Connector
Cable Work
6.9.3
External Alarm Interface (EXT ALM)
The following shows the pin allocations of the external alarm interface (EXT ALM) on the eNB equipment.
Table 12
Pin Number and Signal Name
Pin No.
Signal name
Output 1 (Make)
Output 1 (Break)
Output 1 (Common)
Input 1-G
Input 1
Input 2-G
Input 2
Figure 59
Pin Allocation for External Alarm Interface (EXT ALM) Connector
73
Voltage Check
Voltage Check
7.1
Cable Side Power Connector Pin Location Polarity
The following shows the pin location polarity image and details of the cable side power connected to the Power Distribution
Board (PDB) side breaker.
Figure 60
74
Cable Side Power Connector Pin Location Polarity
Voltage Check
7.2
Voltage Check Procedure
The following show the procedure to check the voltage.
Prepare the tester in advance. Check that the tester operates normally before starting the test.
Check the target location by sight and by reading out.
Insulate and cure the necessary parts of the cable side power connector, DC power distribution board and DC
breaker to prevent short-circuit accidents.
No voltage check of the breaker
Check that the target breaker on the power distribution board side is turned OFF by sight, and perform no voltage
check on the power distribution board side using the tester.
Check that the red lead bar is connected to the + on the tester, and black lead bar to the –COM on the tester.
Change the tester range to VDC range. For a tester with the Ampere range, check with two people or more
that the measurement is not performed in Ampere range and that the test bar insertion positions to the tester
are correct.
Connect the red lead bar of the tester to the plus (+) pole of the target power distribution board breaker, and
the black lead bar to its minus (-) pole.
Check that the value displayed on the tester is 0V (no voltage, logical value).
Disconnect both the lead bars of the tester from the breaker terminals.
Cable Side Power Connecter Voltage Check
Check that the target power distribution side breaker is turned OFF by sight, and perform no voltage check of the
cable side power connecter using the tester.
Connect the red lead bar of the tester to the 0V terminal (pin 2) on the cable side power connector, and the
black lead bar to its -48V terminal (pin 1).
Check that the value displayed on the tester is 0V (no voltage, logical value).
75
Voltage Check
Keep each lead bar (red and black) of the tester connected as is, and instruct another worker to turn ON the target
breaker.
76
After the worker checks the position of the target breaker by the drawing, the target device name displayed
on the power distribution and the destination plate attached to the power cable, the worker turns ON the
target breaker. Moreover, the supervisor would always be present and checks on the work.
Check that the breaker switch is turned ON, and 48V (logical value) is displayed on the tester.
Keeping the red lead bar connected to the 0V terminal (pin 2) of the cable side power connector, slowly move the
black lead bar to the grounding terminal (E or FG) and connect to it. Upon connection, check that the voltage
changes from 48V to 0V (logical value).
Voltage Check
Keep the black lead bar connected to the grounding terminal (E or FG), slowly move the red lead bar from the 0V
terminal (pin 2) of the cable side connector to the -48V terminal (pin 1), and connect to it. Upon connection, check
that the voltage changes from 0V to -48V.
10
Check that the polarities of the logical value and the actual measurement value are the same, the voltage value is
almost the same as the above logical value, in a range allowed by the device characteristics, or is an appropriate
voltage specified by the rectifier.
11
When the voltage check is complete, check the target breaker again and turn the breaker OFF (upon turning OFF,
check again that the cable side power connector is in 0V (no voltage)).
12
Remove the cure materials, and attach the power distribution board breaker terminal protection cover (fix by
screws and check the tightening).
13
Connect the cable side power connecter to the power connector on the equipment side.
14
Clean up the site.
77

Source Exif Data:
File Type                       : PDF
File Type Extension             : pdf
MIME Type                       : application/pdf
PDF Version                     : 1.6
Linearized                      : No
Encryption                      : Standard V4.4 (128-bit)
User Access                     : Print, Extract, Print high-res
Create Date                     : 2012:04:10 11:04:34Z
Modify Date                     : 2012:08:16 14:51:21-04:00
XMP Toolkit                     : Adobe XMP Core 5.2-c001 63.139439, 2010/09/27-13:37:26
Format                          : application/pdf
Creator                         : 
Title                           : 
Creator Tool                    : FrameMaker 8.0
Metadata Date                   : 2012:08:16 14:51:21-04:00
Producer                        : Acrobat Distiller 9.0.0 (Windows)
Document ID                     : uuid:b075de4c-7a82-4ff9-9352-ceb43891bade
Instance ID                     : uuid:b7378546-a32b-4636-9b14-73a88659ff35
Page Mode                       : UseOutlines
Page Count                      : 77
EXIF Metadata provided by EXIF.tools
FCC ID Filing: DI407208901