UMCUMC--I210C Module Installation GuideI210C Module Installation Guide□Normal     □Internal Use  □Confidential  □Restricted ConfidentialRev. 0.12015/06/12
Parts’ OverviewCoverFrom MeterTransparent MaskFrom MeterWhen the UMC-I210C is installed in GE I-210+c meter (i.e. host device), the FCC labelis placed on the outside of the GE I-210+cmeter transparent mask which must coverthe info, something like “contains the FCCID: NKR- CB1GI210C”2□Normal     □Internal Use  □Confidential  □Restricted ConfidentialFrom MeterUMC-I210CBaseAntenna unitFrom WNCFrom WNC>>>>> LTE Antenna unitand UMC-I210C are from WNC.>>>>> Transparent mask, cover and base are from GE I-210+c meter.
Overview of Installation StepsPut antenna and PCB upside down.Connect cable to PCBTop side3□Normal     □Internal Use  □Confidential  □Restricted ConfidentialScrew in with screw driverConnect cables to main board.Connect cover and base.Finish with transparent mask
Installation LTE Antenna Unit into UMC-I210C4□Normal     □Internal Use  □Confidential  □Restricted ConfidentialxyzHooks are designed in holder that would help assembly of antenna and PCB.
Connecting LTE Antenna Cables into IMG03clip5□Normal     □Internal Use  □Confidential  □Restricted ConfidentialConnect antenna cable to PCB.Cables are fixed with IPEX on the module.
Installation UMC-I210C with Antenna Unit into Meter6□Normal     □Internal Use  □Confidential  □Restricted Confidential